1613Oil Rig Updates

Expand Messages
  • Bob Conrich
    Jan 3, 2007
      The following updates were provided by Saint FM Radio in St. Helena.

      27 December:

      MV Kelso arrived to Tristan da Cunha on Friday 22nd December with the advance salvage party plus
      the environmental team who will be completing the marine survey which Sue Scott started during her
      September visit. The salvage work to prepare the rig for floating began on 23rd December and will
      take an estimated three weeks.
      The 3180 tonne salvage tug De Hong, built in 2000 in China, has been chartered by salvors Titan and
      sailed from Cape Town on Christmas Eve, Sunday 24th December, and is expected to arrive at Tristan
      tomorrow, Thursday 28th December. So an attempt to re-float the rig and consign her to the deep, could
      be made in mid January.


      31 December:

      The 3180 tonne salvage tug De Hong, chartered by salvors Titan and sailed from Cape Town on
      Christmas Eve, Sunday 24th December, and arrived at Tristan on Friday 29th December.
      Captain Lu and his crew then took Towmaster Kees van Assem and the Titan new arrivals
      round to Trypot Bay. Once the tug is on station there, Kelso is expected to come up to the Settlement
      for supplies. So an attempt to re-float the rig and consign her to the deep, could be made before too
      long.