    (responding to Hillel) ... IMHO Traceability, of itself, has no value. However some of the things that we DO value may be achieved readily if we have
    Message 1 of 137 , Mar 2, 2010
    • 0 Attachment
      (responding to Hillel)

      > Were Ron or George or many others on this list to assure that
      > traceability exists due to "other things they do", I'm quite
      > sure they have the experience to ensure that, indeed, those
      > other things accomplish the same outcome that traceability
      > practices are meant to perform.

      IMHO Traceability, of itself, has no value. However some of the
      things that we DO value may be achieved readily if we have
      Traceability. On the other hand, it is possible that they
      may be achieved more readily by means that do not include
      the ability to trace - say by checking the desired property
      directly. I hope that's an acceptable 'paraphrase'?

      > Unfortunately, most people in this field today aren't where
      > the experts in the field are and need more blunt forms of
      > traceability to mitigate the risks associated with managing
      > code that's changing over time, space, and multitudes of people
      > touching it that describes the context in which many
      > systems created by inexperienced people exist.

      Hmm... for many people, "Monkey see, Monkey do". I hope that's
      an acceptable 'paraphrase'? :-)

      Paul Oldfield
      Capgemini
    • john_hermann
      @Mark Couldn t we write the tests such that they don t look like tests, but rather requirements? With one, and only one formal specification, which
      Message 137 of 137 , Apr 20, 2010
      • 0 Attachment
        @Mark
        <quote>
        Couldn't we write the tests such that they don't look like tests, but rather requirements?

        With one, and only one formal specification, which also happens to be executable against the actual system, aren't we better off than having to split time between two possibly out-of-sync artifacts?
        </quote>

        ThoughtWorks has a testing tool called Twist, which uses something called Business Workflows. And now it has a nestable declarative aggregator called a "Concept" (what a concept!).

        http://www.thoughtworks-studios.com/agile-test-automation
        <snip>
        Twist is... designed to help you deliver applications fully aligned with your business. It eliminates requirements mismatch as business users directly express intent in their domain language.
        </snip>

        I have not used the tool myself. If anyone has, please add some insight.

        -johnny
        P.S. I have no affiliation w/ ThoughtWorks.


        --- In scrumdevelopment@yahoogroups.com, "woynam" <woyna@...> wrote:
        >
        >
        >
        > --- In scrumdevelopment@yahoogroups.com, "pauloldfield1" <PaulOldfield1@> wrote:
        > >
        > > (responding to George)
        > >
        > > > I feel like a broken record with my questions.
        > >
        > > I guess I need to learn to answer you better :-)
        > >
        > > > pauloldfield1 wrote:
        > > > > IMHO Traceability, of itself, has no value. However some of the
        > > > > things that we DO value may be achieved readily if we have
        > > > > Traceability.
        > > >
        > > > What are those things?
        > >
        > > Well, I gave you a list of 15 things that some people value.
        > > I guess we could take a lead from Hillel's sig line and say
        > > they are all various categories of attempting to use process
        > > to cover for us being too stupid to be agile.
        > >
        > > We value knowing that we are testing to see that our system does
        > > what the customer wants (but we're too stupid to write the
        > > requirements directly as tests)... etc. etc.
        >
        > And this continues to irk the sh*t out of me. Why do we create another intermediate artifact that has to be translated by an error-prone human into a set of tests? What does the requirements document provide that the tests don't? Couldn't we write the tests such that they don't look like tests, but rather requirements?
        >
        > With one, and only one formal specification, which also happens to be executable against the actual system, aren't we better off than having to split time between two possibly out-of-sync artifacts?
        >
        > If you continue to have a separate requirements document, and your tests don't reflect the entirety of the requirements, what mechanism do you use to verify the uncovered requirements? How is that working for you?
        >
        > Mark
        >
        > "A man with one watch knows what time it is; A man with two watches is never quite sure."
        >
        >
        > >
        > > Paul Oldfield
        > > Capgemini
        > >
        >
      Your message has been successfully submitted and would be delivered to recipients shortly.