Re: [scrumdevelopment] Re: Kanban vs. Scrum

Expand Messages
  • Steve Berczuk
    ... Yes, that was my point. The team MAKES the decisions. The SM can be the point of contact, is also the one to help those decisions get made. In some ways
    Message 1 of 224 , Nov 2, 2008
    • 0 Attachment
      On Sat, Nov 1, 2008 at 1:39 PM, Ron Jeffries <ronjeffries@...> wrote:
      > Hello, Steve. On Saturday, November 1, 2008, at 10:40:33 AM, you
      > wrote:
      >
      >> Thinking about this some more, would the "point of contact" for the
      >> team be the Scrum Master? While not the "Manager" isn't one role of
      >> the scrum master to facilitate team interactions (internally and with
      >> the PO)?
      >
      >> While not quite the same as decision maker, I can imagine that, in the
      >> absence of the team coming to a decision, that the SM can be the one
      >> to narrow down the choices.
      >
      > Not as I understand it. The SM makes few if any decisions. Her job
      > is to get the /team/ to make decisions.

      Yes, that was my point. The team MAKES the decisions. The SM can be
      the point of contact, is also the one to help those decisions get
      made. In some ways analogous to the committee of product owners.
      (though not exactly the same). With all of those caveats, what I said
      was probably not helping the discussion ;)


      Steve

      --
      Steve Berczuk | steve@... | http://www.berczuk.com
      SCM Patterns: Effective Teamwork, Practical Integration
      www.scmpatterns.com
    • Doug Swartz
      ... XP differs from kanban in many of the same ways as Scrum. It is batch pull, not continuous pull. Instead of a sprint, XP calls it an iteration. In XP, like
      Message 224 of 224 , Nov 19, 2008
      • 0 Attachment
        Wednesday, November 19, 2008, 3:05:08 PM, Dillon Weyer wrote:

        > In this case how is XP different to Kanban then?

        XP differs from kanban in many of the same ways as Scrum. It
        is batch pull, not continuous pull. Instead of a sprint, XP
        calls it an iteration. In XP, like scrum, but not kanban, each
        story has a high level estimate attached to it during release
        planning, which is similar, but somewhat different from
        backlog grooming in scrum.

        Doug Swartz


        > aacockburn wrote

        > --- In scrumdevelopment@yahoogroups.com
        > <mailto:scrumdevelopment%40yahoogroups.com> , Graeme Matthew <scrum@...>
        > wrote:
        >>
        >> Whats the difference between a product backlog and kanban they both
        > act
        >> as signaling system to trigger action?
        >>
        >>

        > The kanban is continuous pull, the backlog is batch pull.

        > With the backlogs, each month you *promise* how much you'll do, and
        > pull a *batch* of items from the product to the sprint backlog.
        > You're now locked.

        > With kanban, you pull directly from the product backlog to the
        > work list, one at a time. There is no work estimate attached to the
        > item - you just work on it till you're done, then pull the next.
        > Some teams put size limits on the work list, so you can't work on
        > more than e.g. 5 items at a time.

        > That's quite a difference.

        > Alistair