Re: [scrumdevelopment] Re: Has anyone else seen teams use ranges in task estimation

Expand Messages
  • George Dinwiddie
    ... When asked for a three point estimate (usually when there wasn t enough information for one number) I used to take a guess and then bracket it with 50%
    Message 1 of 12 , Sep 25, 2008
    • 0 Attachment
      Rafael Sabbagh Armony wrote:
      > I sincerely see no point in using three guesses instead of one. The
      > result is still - a guess.
      > In my opinion, this is no better, no worse than making only one guess -
      > just more complicated.

      When asked for a three point estimate (usually when there wasn't enough
      information for one number) I used to take a guess and then bracket it
      with 50% less and 100% more.

      - George

      --
      ----------------------------------------------------------------------
      * George Dinwiddie * http://blog.gdinwiddie.com