RE: [scrumdevelopment] SCRUM process with other methodologies

Expand Messages
  • Mike Cohn
    Hi Michael-- I have experimented before with exactly what you describe. In introducing Scrum to a couple of different organizations I couldn t get them to
    Message 1 of 22 , Apr 5, 2004
    • 0 Attachment
      Hi Michael--

      I have experimented before with exactly what you describe. In introducing
      Scrum to a couple of different organizations I couldn't get them to
      initially accept the idea that we didn't need to think up all the
      requirements upfront. To get the project moving I had them do a two week
      "Requirements Capture Sprint" which focused just on getting initial
      requirements written down. We still went very lightweight, using much of the
      advice in Cockburn's "Effective Use Cases" book. They also couldn't get
      around the idea that there'd be no upfront architecting so we did another
      two week "Analysis and Design Sprint" (ADS) that was intended to allay that
      fear.

      Some advice:
      --realize this is a crutch and try to stop it as soon as you can. I never
      had to do it more than once, right at the start. By the second project no
      one needed it.
      --It does work well so there's no problem with it, except developers could
      be tempted to turn it into 4 weeks then 6, then 8.
      --Although when I've done a Requirements Capture Sprint in the past I've
      done it with use cases, I'd probably do it these days with it even shorter
      (1 week instead of 2) and use stories instead of use cases.

      This is written up (in only slightly more detail) in a paper I did for IEEE
      Computer last year. You can read it at:
      http://www.mountaingoatsoftware.com/articles.php and select "Introducing An
      Agile Process to an Organization."

      Good luck,

      --Mike Cohn
      Author of User Stories Applied for Agile Software Development
      www.userstories.com


      -----Original Message-----
      From: Michael Dowling [mailto:mdowling@...]
      Sent: Monday, April 05, 2004 11:42 AM
      To: scrumdevelopment@yahoogroups.com
      Subject: [scrumdevelopment] SCRUM process with other methodologies

      Hey all:

      The company I work for is implementing a SCRUM process for our
      development teams, and so far so good! I've worked with SCRUM before,
      but I've also almost always used SCRUM during development only, and
      using other methodologies and artifacts from other methodologies (i.e.
      JAD to gather requirements BEFORE the item is placed on a backlog and
      some of UP's artifacts such as sequence and class diagrams for effective
      communication of a design idea to your SCRUM team) for other parts of
      the process as a whole.

      I would like to hear whether any one else has experimented with this
      approach, and what their results were? Any recommendations?

      Best regards,

      -Michael

      --

      Michael Dowling
      mdowling@...
      PlanetOut Partners, Inc.
      415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
      www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com




      To Post a message, send it to: scrumdevelopment@...
      To Unsubscribe, send a blank message to:
      scrumdevelopment-unsubscribe@...
      Yahoo! Groups Links
    • Michael Dowling
      ... So, basically Gather Requirements on Feature X be a backlog item to be prioritized? That priority is implicit - engineering work cannot be done on a
      Message 2 of 22 , Apr 5, 2004
      • 0 Attachment
        > Sounds like it would work for me, but why aren't the analysis and
        > artifact construction teaks part of the backlog so that they can be
        > prioritized with the rest?

        So, basically "Gather Requirements on Feature X" be a backlog item to be
        prioritized? That priority is implicit - engineering work cannot be
        done on a "feature" or "bug" without proper analysis (be it short or
        lengthy, depending on the organization and/or team). This is why I
        assume that a backlog item should already have gone through the
        requirements phase already - it is generally, almost always during this
        time that features and needs are found to be either a) necessary, b)
        unnecessary, or c) nifty, but not yet important. From there one can
        pass it to a backlog for prioritization, but only after knowing what the
        heck one wants.

        I know - this does sound a little waterfallish. But think of it this
        way - collaborative waterfall. JAD is similar to SCRUM whereas all
        members of a JAD team collaborate on the project. You're just
        "waterfalling" the collaboration from one phase to the next. And SCRUM
        allows for the (certain and expected) changes in those requirements.


        > Dan Rawsthorne, PhD, Sr. Consultant
        > www.netobjectives.com
        > DrDan@...
        > office: 425-269-8628

        Off-topic - hey - are you from the same group that did (does?) the
        lectures/seminars in Bellvue on proper design techniques? You guys did
        a fabulous job, and with each lecture I walked away with a new idea of
        better design. Do you ever hold these lectures in the SF Bay Area
        (yeah, had to return to San Francisco - Seattle was too wet for me! :) ).


        --

        Michael Dowling
        mdowling@...
        PlanetOut Partners, Inc.
        415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
        www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com
      • Michael Dowling
        Excellent, Mike. For us, its going to take some time to sprint everything. Although - for us, having 2-week requirements gathering might be a bit much. 1
        Message 3 of 22 , Apr 5, 2004
        • 0 Attachment
          Excellent, Mike. For us, its going to take some time to "sprint"
          everything. Although - for us, having 2-week requirements gathering
          might be a bit much. 1 week max I would hope. But I see your point -
          the basic framework can be applied to each phase, slightly customized
          given the context.

          We're also considering the use of XPlanner as a tool (www.xplanner.org)
          to help us track our sprints and create burn graphs for management much
          easier. I've used it before (and *adore* it), but some folks also want
          to take a look at some other tools (excel just doesn't cut it). Basic
          requirement is that it be as simple as scrum itself.

          What have you had success in?

          Thank you for your comments - much appreciated!

          -Michael

          Mike Cohn wrote:

          > Hi Michael--
          >
          > I have experimented before with exactly what you describe. In introducing
          > Scrum to a couple of different organizations I couldn't get them to
          > initially accept the idea that we didn't need to think up all the
          > requirements upfront. To get the project moving I had them do a two week
          > "Requirements Capture Sprint" which focused just on getting initial
          > requirements written down. We still went very lightweight, using much of the
          > advice in Cockburn's "Effective Use Cases" book. They also couldn't get
          > around the idea that there'd be no upfront architecting so we did another
          > two week "Analysis and Design Sprint" (ADS) that was intended to allay that
          > fear.
          >
          > Some advice:
          > --realize this is a crutch and try to stop it as soon as you can. I never
          > had to do it more than once, right at the start. By the second project no
          > one needed it.
          > --It does work well so there's no problem with it, except developers could
          > be tempted to turn it into 4 weeks then 6, then 8.
          > --Although when I've done a Requirements Capture Sprint in the past I've
          > done it with use cases, I'd probably do it these days with it even shorter
          > (1 week instead of 2) and use stories instead of use cases.
          >
          > This is written up (in only slightly more detail) in a paper I did for IEEE
          > Computer last year. You can read it at:
          > http://www.mountaingoatsoftware.com/articles.php and select "Introducing An
          > Agile Process to an Organization."
          >
          > Good luck,
          >
          > --Mike Cohn
          > Author of User Stories Applied for Agile Software Development
          > www.userstories.com
          >
          >
          > -----Original Message-----
          > From: Michael Dowling [mailto:mdowling@...]
          > Sent: Monday, April 05, 2004 11:42 AM
          > To: scrumdevelopment@yahoogroups.com
          > Subject: [scrumdevelopment] SCRUM process with other methodologies
          >
          > Hey all:
          >
          > The company I work for is implementing a SCRUM process for our
          > development teams, and so far so good! I've worked with SCRUM before,
          > but I've also almost always used SCRUM during development only, and
          > using other methodologies and artifacts from other methodologies (i.e.
          > JAD to gather requirements BEFORE the item is placed on a backlog and
          > some of UP's artifacts such as sequence and class diagrams for effective
          > communication of a design idea to your SCRUM team) for other parts of
          > the process as a whole.
          >
          > I would like to hear whether any one else has experimented with this
          > approach, and what their results were? Any recommendations?
          >
          > Best regards,
          >
          > -Michael
          >

          --

          Michael Dowling
          mdowling@...
          PlanetOut Partners, Inc.
          415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
          www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com
        • Roberts, David J (CNSP N6124V13)
          Anyone interested, I find developers to be the most fearful of incremental development (without admitting). You mean I have to revisit my code? I thought I
          Message 4 of 22 , Apr 5, 2004
          • 0 Attachment

            Anyone interested,

             

            I find developers to be the most fearful of incremental development (without admitting).

             

            "You mean I have to revisit my code? I thought I was done with that..."

             

            David Roberts

            InnovaSystems

             

            -----Original Message-----
            From: Mike Cohn [mailto:mike@...]
            Sent
            :
            Monday, April 05, 2004 12:28 PM
            To: scrumdevelopment@yahoogroups.com
            Subject: RE: [scrumdevelopment] SCRUM process with other methodologies

             

            Hi Michael--

            I have experimented before with exactly what you describe. In introducing
            Scrum to a couple of different organizations I couldn't get them to
            initially accept the idea that we didn't need to think up all the
            requirements upfront. To get the project moving I had them do a two week
            "Requirements Capture Sprint" which focused just on getting initial
            requirements written down. We still went very lightweight, using much of the
            advice in Cockburn's "Effective Use Cases" book. They also couldn't get
            around the idea that there'd be no upfront architecting so we did another
            two week "Analysis and Design Sprint" (ADS) that was intended to allay that
            fear.

            Some advice:
            --realize this is a crutch and try to stop it as soon as you can. I never
            had to do it more than once, right at the start. By the second project no
            one needed it.
            --It does work well so there's no problem with it, except developers could
            be tempted to turn it into 4 weeks then 6, then 8.
            --Although when I've done a Requirements Capture Sprint in the past I've
            done it with use cases, I'd probably do it these days with it even shorter
            (1 week instead of 2) and use stories instead of use cases.

            This is written up (in only slightly more detail) in a paper I did for IEEE
            Computer last year. You can read it at:
            http://www.mountaingoatsoftware.com/articles.php and select "Introducing An
            Agile Process to an Organization."

            Good luck,

            --Mike Cohn
            Author of User Stories Applied for Agile Software Development
            www.userstories.com


            -----Original Message-----
            From: Michael Dowling [mailto:mdowling@...]
            Sent: Monday, April 05, 2004 11:42 AM
            To: scrumdevelopment@yahoogroups.com
            Subject: [scrumdevelopment] SCRUM process with other methodologies

            Hey all:

            The company I work for is implementing a SCRUM process for our
            development teams, and so far so good!  I've worked with SCRUM before,
            but I've also almost always used SCRUM during development only, and
            using other methodologies and artifacts from other methodologies (i.e.
            JAD to gather requirements BEFORE the item is placed on a backlog and
            some of UP's artifacts such as sequence and class diagrams for effective
            communication of a design idea to your SCRUM team) for other parts of
            the process as a whole.

            I would like to hear whether any one else has experimented with this
            approach, and what their results were?  Any recommendations?

            Best regards,

            -Michael

            --

            Michael Dowling
            mdowling@...
            PlanetOut Partners, Inc.
            415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
            www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com




            To Post a message, send it to:   scrumdevelopment@...
            To Unsubscribe, send a blank message to:
            scrumdevelopment-unsubscribe@...
            Yahoo! Groups Links







            To Post a message, send it to:   scrumdevelopment@...
            To Unsubscribe, send a blank message to: scrumdevelopment-unsubscribe@...




          • Mike Cohn
            Michael-- For the most part you really want to do all that analysis work as part of the sprint. Keep in mind that requirements are like inventory and we don t
            Message 5 of 22 , Apr 5, 2004
            • 0 Attachment
              Michael--
              For the most part you really want to do all that analysis work as part of
              the sprint. Keep in mind that requirements are like inventory and we don't
              want to pile up too much inventory that may never turn into finished
              software. Plus, if you do it too soon you lose the ability to have new
              learning impact those requirements and the knowledge goes stale quite
              quickly. A couple of short, to-the-point, upfront conversations don't hurt
              but when you start writing it all down, referring back to it, pointing to it
              as though it means something, then you've done too much requirements work
              upfront.

              --Mike Cohn
              Author of User Stories Applied for Agile Software Development
              www.userstories.com


              -----Original Message-----
              From: Michael Dowling [mailto:mdowling@...]
              Sent: Monday, April 05, 2004 1:48 PM
              To: scrumdevelopment@yahoogroups.com
              Subject: Re: [scrumdevelopment] SCRUM process with other methodologies

              > Sounds like it would work for me, but why aren't the analysis and
              > artifact construction teaks part of the backlog so that they can be
              > prioritized with the rest?

              So, basically "Gather Requirements on Feature X" be a backlog item to be
              prioritized? That priority is implicit - engineering work cannot be
              done on a "feature" or "bug" without proper analysis (be it short or
              lengthy, depending on the organization and/or team). This is why I
              assume that a backlog item should already have gone through the
              requirements phase already - it is generally, almost always during this
              time that features and needs are found to be either a) necessary, b)
              unnecessary, or c) nifty, but not yet important. From there one can
              pass it to a backlog for prioritization, but only after knowing what the
              heck one wants.

              I know - this does sound a little waterfallish. But think of it this
              way - collaborative waterfall. JAD is similar to SCRUM whereas all
              members of a JAD team collaborate on the project. You're just
              "waterfalling" the collaboration from one phase to the next. And SCRUM
              allows for the (certain and expected) changes in those requirements.


              > Dan Rawsthorne, PhD, Sr. Consultant
              > www.netobjectives.com
              > DrDan@...
              > office: 425-269-8628

              Off-topic - hey - are you from the same group that did (does?) the
              lectures/seminars in Bellvue on proper design techniques? You guys did
              a fabulous job, and with each lecture I walked away with a new idea of
              better design. Do you ever hold these lectures in the SF Bay Area
              (yeah, had to return to San Francisco - Seattle was too wet for me! :) ).


              --

              Michael Dowling
              mdowling@...
              PlanetOut Partners, Inc.
              415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
              www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com



              To Post a message, send it to: scrumdevelopment@...
              To Unsubscribe, send a blank message to:
              scrumdevelopment-unsubscribe@...
              Yahoo! Groups Links
            • Dan Rawsthorne
              Yes, Analyze XXX is a backlog item. One wouldn t do it unless XXX had a high enough priority to do it, right? In a system where we think of 50 use cases up
              Message 6 of 22 , Apr 5, 2004
              • 0 Attachment
                Yes, "Analyze XXX" is a backlog item. One wouldn't do it unless XXX had
                a high enough priority to do it, right? In a system where we think of 50
                use cases up front we don't analyze all of them up front, we analyze
                them as we go.

                So, these analysis tasks must be on somebody's backlog. If that somebody
                is another, analysis, team, that's ok, but I prefer my team to be one,
                big, happy, one - including analysts, coders, testers, etc - with one,
                big, happy product backlog...

                Dan ;-)

                Dan Rawsthorne, PhD, Sr. Consultant
                www.netobjectives.com
                DrDan@...
                office: 425-269-8628

                Net Objectives' vision is effective software development without
                suffering. Our mission is to assist software development teams in
                accomplishing this through a combination of training and mentoring.


                > -----Original Message-----
                > From: Michael Dowling [mailto:mdowling@...]
                > Sent: Monday, April 05, 2004 1:48 PM
                > To: scrumdevelopment@yahoogroups.com
                > Subject: Re: [scrumdevelopment] SCRUM process with other methodologies
                >
                > > Sounds like it would work for me, but why aren't the analysis and
                > > artifact construction teaks part of the backlog so that they can be
                > > prioritized with the rest?
                >
                > So, basically "Gather Requirements on Feature X" be a backlog item to
                be
                > prioritized? That priority is implicit - engineering work cannot be
                > done on a "feature" or "bug" without proper analysis (be it short or
                > lengthy, depending on the organization and/or team). This is why I
                > assume that a backlog item should already have gone through the
                > requirements phase already - it is generally, almost always during
                this
                > time that features and needs are found to be either a) necessary, b)
                > unnecessary, or c) nifty, but not yet important. From there one can
                > pass it to a backlog for prioritization, but only after knowing what
                the
                > heck one wants.
                >
                > I know - this does sound a little waterfallish. But think of it this
                > way - collaborative waterfall. JAD is similar to SCRUM whereas all
                > members of a JAD team collaborate on the project. You're just
                > "waterfalling" the collaboration from one phase to the next. And
                SCRUM
                > allows for the (certain and expected) changes in those requirements.
                >
                >
                > > Dan Rawsthorne, PhD, Sr. Consultant
                > > www.netobjectives.com
                > > DrDan@...
                > > office: 425-269-8628
                >
                > Off-topic - hey - are you from the same group that did (does?) the
                > lectures/seminars in Bellvue on proper design techniques? You guys
                did
                > a fabulous job, and with each lecture I walked away with a new idea of
                > better design. Do you ever hold these lectures in the SF Bay Area
                > (yeah, had to return to San Francisco - Seattle was too wet for me!
                :) ).
                >
                >
                > --
                >
                > Michael Dowling
                > mdowling@...
                > PlanetOut Partners, Inc.
                > 415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
                > www.gay.com * www.planetout.com * www.kleptomaniac.com *
                > www.outandabout.com
                >
                >
                >
                > To Post a message, send it to: scrumdevelopment@...
                > To Unsubscribe, send a blank message to: scrumdevelopment-
                > unsubscribe@...
                > Yahoo! Groups Links
                >
                >
                >
                >
                >
                >
                > ______________________________________________________________________
                > This email has been scanned by the MessageLabs Email Security System.
                > For more information please visit http://www.messagelabs.com/email
                > ______________________________________________________________________
              • Roberts, David J (CNSP N6124V13)
                Michael, I find the time features are found to be necessary always seems to come after you ve developed something. You re lucky if otherwise is true for you. I
                Message 7 of 22 , Apr 5, 2004
                • 0 Attachment

                  Michael,

                   

                  I find the time features are found to be necessary always seems to come after you've developed something. You're lucky if otherwise is true for you.

                   

                  I see developers having these meeting with customers. The developers leave thinking, "I've locked down these requirements!" and the customer leaves thinking "I know what they're going to build me". Both are problematic.

                   

                  What did you mean when you said: "You're just "waterfalling" the collaboration from one phase to the next".

                  What are these phases?

                   

                  David Roberts

                  TRMS Technical Lead

                  (619) 368-9621

                   

                  -----Original Message-----
                  From: Michael Dowling [mailto:mdowling@...]
                  Sent: Monday, April 05, 2004 1:48 PM
                  To: scrumdevelopment@yahoogroups.com
                  Subject: Re: [scrumdevelopment] SCRUM process with other methodologies

                   

                  > Sounds like it would work for me, but why aren't the analysis and
                  > artifact construction teaks part of the backlog so that they can be
                  > prioritized with the rest?

                  So, basically "Gather Requirements on Feature X" be a backlog item to be
                  prioritized?  That priority is implicit - engineering work cannot be
                  done on a "feature" or "bug" without proper analysis (be it short or
                  lengthy, depending on the organization and/or team).  This is why I
                  assume that a backlog item should already have gone through the
                  requirements phase already - it is generally, almost always during this
                  time that features and needs are found to be either a) necessary, b)
                  unnecessary, or c) nifty, but not yet important.  From there one can
                  pass it to a backlog for prioritization, but only after knowing what the
                  heck one wants.

                  I know - this does sound a little waterfallish.  But think of it this
                  way - collaborative waterfall.  JAD is similar to SCRUM whereas all
                  members of a JAD team collaborate on the project.  You're just
                  "waterfalling" the collaboration from one phase to the next.  And SCRUM
                  allows for the (certain and expected) changes in those requirements.


                  > Dan Rawsthorne, PhD, Sr. Consultant
                  > www.netobjectives.com
                  > DrDan@...
                  > office: 425-269-8628

                  Off-topic - hey - are you from the same group that did (does?) the
                  lectures/seminars in Bellvue on proper design techniques?  You guys did
                  a fabulous job, and with each lecture I walked away with a new idea of
                  better design.  Do you ever hold these lectures in the SF Bay Area
                  (yeah, had to return to San Francisco - Seattle was too wet for me!  :) ).


                  --

                  Michael Dowling
                  mdowling@...
                  PlanetOut Partners, Inc.
                  415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
                  www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com



                  To Post a message, send it to:   scrumdevelopment@...
                  To Unsubscribe, send a blank message to: scrumdevelopment-unsubscribe@...



                • Mike Cohn
                  I have successfully used: --cards --a wiki --rows in Excel --TestTrack (a defect tracker, with each story/task entered as a record) My preference is for cards
                  Message 8 of 22 , Apr 5, 2004
                  • 0 Attachment
                    I have successfully used:

                    --cards
                    --a wiki
                    --rows in Excel
                    --TestTrack (a defect tracker, with each story/task entered as a record)

                    My preference is for cards whenever we're collocated. I want to try out
                    XPlanner and VersionOne sometime but haven't tried either yet.

                    --Mike Cohn
                    Author of User Stories Applied for Agile Software Development
                    www.userstories.com


                    -----Original Message-----
                    From: Michael Dowling [mailto:mdowling@...]
                    Sent: Monday, April 05, 2004 4:53 PM
                    To: scrumdevelopment@yahoogroups.com
                    Subject: Re: [scrumdevelopment] SCRUM process with other methodologies

                    Excellent, Mike. For us, its going to take some time to "sprint"
                    everything. Although - for us, having 2-week requirements gathering
                    might be a bit much. 1 week max I would hope. But I see your point -
                    the basic framework can be applied to each phase, slightly customized
                    given the context.

                    We're also considering the use of XPlanner as a tool (www.xplanner.org)
                    to help us track our sprints and create burn graphs for management much
                    easier. I've used it before (and *adore* it), but some folks also want
                    to take a look at some other tools (excel just doesn't cut it). Basic
                    requirement is that it be as simple as scrum itself.

                    What have you had success in?

                    Thank you for your comments - much appreciated!

                    -Michael

                    Mike Cohn wrote:

                    > Hi Michael--
                    >
                    > I have experimented before with exactly what you describe. In introducing
                    > Scrum to a couple of different organizations I couldn't get them to
                    > initially accept the idea that we didn't need to think up all the
                    > requirements upfront. To get the project moving I had them do a two week
                    > "Requirements Capture Sprint" which focused just on getting initial
                    > requirements written down. We still went very lightweight, using much of
                    the
                    > advice in Cockburn's "Effective Use Cases" book. They also couldn't get
                    > around the idea that there'd be no upfront architecting so we did another
                    > two week "Analysis and Design Sprint" (ADS) that was intended to allay
                    that
                    > fear.
                    >
                    > Some advice:
                    > --realize this is a crutch and try to stop it as soon as you can. I never
                    > had to do it more than once, right at the start. By the second project no
                    > one needed it.
                    > --It does work well so there's no problem with it, except developers could
                    > be tempted to turn it into 4 weeks then 6, then 8.
                    > --Although when I've done a Requirements Capture Sprint in the past I've
                    > done it with use cases, I'd probably do it these days with it even shorter
                    > (1 week instead of 2) and use stories instead of use cases.
                    >
                    > This is written up (in only slightly more detail) in a paper I did for
                    IEEE
                    > Computer last year. You can read it at:
                    > http://www.mountaingoatsoftware.com/articles.php and select "Introducing
                    An
                    > Agile Process to an Organization."
                    >
                    > Good luck,
                    >
                    > --Mike Cohn
                    > Author of User Stories Applied for Agile Software Development
                    > www.userstories.com
                    >
                    >
                    > -----Original Message-----
                    > From: Michael Dowling [mailto:mdowling@...]
                    > Sent: Monday, April 05, 2004 11:42 AM
                    > To: scrumdevelopment@yahoogroups.com
                    > Subject: [scrumdevelopment] SCRUM process with other methodologies
                    >
                    > Hey all:
                    >
                    > The company I work for is implementing a SCRUM process for our
                    > development teams, and so far so good! I've worked with SCRUM before,
                    > but I've also almost always used SCRUM during development only, and
                    > using other methodologies and artifacts from other methodologies (i.e.
                    > JAD to gather requirements BEFORE the item is placed on a backlog and
                    > some of UP's artifacts such as sequence and class diagrams for effective
                    > communication of a design idea to your SCRUM team) for other parts of
                    > the process as a whole.
                    >
                    > I would like to hear whether any one else has experimented with this
                    > approach, and what their results were? Any recommendations?
                    >
                    > Best regards,
                    >
                    > -Michael
                    >

                    --

                    Michael Dowling
                    mdowling@...
                    PlanetOut Partners, Inc.
                    415.834.6500 main | 415.834.6306 direct | 415.834.6502 fax
                    www.gay.com * www.planetout.com * www.kleptomaniac.com * www.outandabout.com




                    To Post a message, send it to: scrumdevelopment@...
                    To Unsubscribe, send a blank message to:
                    scrumdevelopment-unsubscribe@...
                    Yahoo! Groups Links
                  • Ron Jeffries
                    ... Isn t that why Scrum ships software every month, and XP and Crystal even more often? Ron Jeffries www.XProgramming.com Anyone can make the simple
                    Message 9 of 22 , Apr 5, 2004
                    • 0 Attachment
                      On Monday, April 5, 2004, at 9:23:18 PM, Roberts, David J (CNSP N6124V13) wrote:

                      > I find the time features are found to be necessary always seems to come
                      > after you've developed something. You're lucky if otherwise is true for you.

                      > I see developers having these meeting with customers. The developers leave
                      > thinking, "I've locked down these requirements!" and the customer leaves
                      > thinking "I know what they're going to build me". Both are problematic.

                      Isn't that why Scrum ships software every month, and XP and Crystal even
                      more often?

                      Ron Jeffries
                      www.XProgramming.com
                      Anyone can make the simple complicated.
                      Creativity is making the complicated simple. -- Charles Mingus
                    • Jens Ƙstergaard
                      I ve used it before (and *adore* it), but some folks also want ... Basic ... Hi Michael I have had absolutely no problem using excel and find that it works vey
                      Message 10 of 22 , Apr 6, 2004
                      • 0 Attachment
                        I've used it before (and *adore* it), but some folks also want
                        > to take a look at some other tools (excel just doesn't cut it).
                        Basic
                        > requirement is that it be as simple as scrum itself.
                        >

                        Hi Michael

                        I have had absolutely no problem using excel and find that it works
                        vey well. If a team needs additional material for coordination, they
                        figure it out themselves.

                        If you sign in and look under files, I have posted an example of a
                        sprintlog that we use.

                        Jens
                      • Reginald Braithwaite-Lee
                        ... Whenever possible, I like to use corkboards or whiteboards. I m considering using a projector and a dedicated PC on my next project for things that don t
                        Message 11 of 22 , Apr 6, 2004
                        • 0 Attachment
                          --- Mike Cohn <mike@...> wrote:
                          > I have successfully used:
                          >
                          > --cards
                          > --a wiki
                          > --rows in Excel
                          > --TestTrack (a defect tracker, with each story/task entered as a
                          > record)

                          Whenever possible, I like to use corkboards or whiteboards. I'm
                          considering using a projector and a dedicated PC on my next project for
                          things that don't work well on paper.

                          http://www.braithwaite-lee.com/opinions/cork-board.html

                          --
                          Reginald Braithwaite-Lee
                          http://www.braithwaite-lee.com

                          "Even when my proposals are seen as significant improvements, they are
                          often rejected on the grounds that they are not intuitive. It is a
                          classic Catch-22: The client wants something that is significantly
                          superior to the competition. But if it is to be superior, it must be
                          different. (Typically, the greater the improvement, the greater the
                          difference.) Therefore, it cannot be intuitive, that is, familiar. What
                          the client wants is an interface with at most marginal differences from
                          current practice... that, somehow, makes a major improvement." --Jef
                          Raskin


                          __________________________________
                          Do you Yahoo!?
                          Yahoo! Small Business $15K Web Design Giveaway
                          http://promotions.yahoo.com/design_giveaway/
                        • Roberts, David J (CNSP N6124V13)
                          I would say so. That s why we do empirical. David Roberts TRMS Technical Lead (619) 368-9621 ... From: Ron Jeffries [mailto:ronjeffries@XProgramming.com] Sent:
                          Message 12 of 22 , Apr 6, 2004
                          • 0 Attachment

                            I would say so. That's why we do empirical.

                             

                            David Roberts

                            TRMS Technical Lead

                            (619) 368-9621

                             

                            -----Original Message-----
                            From: Ron Jeffries [mailto:ronjeffries@...]
                            Sent: Monday, April 05, 2004 7:23 PM
                            To: scrumdevelopment@yahoogroups.com
                            Subject: Re: [scrumdevelopment] SCRUM process with other methodologies

                             

                            On Monday, April 5, 2004, at 9:23:18 PM, Roberts, David J (CNSP N6124V13) wrote:

                            > I find the time features are found to be necessary always seems to come
                            > after you've developed something. You're lucky if otherwise is true for you.

                            > I see developers having these meeting with customers. The developers leave
                            > thinking, "I've locked down these requirements!" and the customer leaves
                            > thinking "I know what they're going to build me". Both are problematic.

                            Isn't that why Scrum ships software every month, and XP and Crystal even
                            more often?

                            Ron Jeffries
                            www.XProgramming.com
                            Anyone can make the simple complicated.
                            Creativity is making the complicated simple. -- Charles Mingus



                            To Post a message, send it to:   scrumdevelopment@...
                            To Unsubscribe, send a blank message to: scrumdevelopment-unsubscribe@...



                          • Claude Montpetit
                            We just implemented a Scrum process and there are many stories that were added just for requirement analysis. This became necessary because the product is
                            Message 13 of 22 , Apr 6, 2004
                            • 0 Attachment
                              We just implemented a Scrum process and there are many stories that
                              were added just for requirement analysis. This became necessary
                              because the product is already sold and installed at some customer
                              locations (a server product). These customers have custom
                              requirements that we do for them and they (generally) pay us. So we
                              need to estimate the work required for it. Producing an estimate is
                              therefore a story that must be prioritized. Once the estimate is
                              completed and the quote sent to the customer, another story is created
                              in the product backlog:

                              Implement request X for customer Y based on estimate Z

                              Implementing Scrum is very new to me and I am not sure about how to
                              deal with, for example, urgent estimates that must enter the current
                              sprint. Telling the salesman to wait for the next iteration for the
                              quote is not usually a good thing as it means that the implementation
                              would in theory start very late:

                              - month 1: submit the request
                              - month 2: produce the estimate
                              - month 3: implement the request

                              This is not practical of course so we have been inserting estimates in
                              the current sprint and informed the customer that he must decide in
                              the current month whether he wants to go ahead or not if he wants it
                              to be done in the next sprint.

                              One of the strongest problem I had (and still have) implementing this
                              process was to convince people outside of the development team
                              (client, marketing, sales) that they should know about details of the
                              products (bugs, certain improvements that look "too technical"...)

                              Once the product backlog was transfered to "clients", and when I asked
                              them to prioritize items, they thought that there was too many
                              details. I then realized that they felt this way because they did not
                              understand the product enough, and that the development team had been
                              driving the product on their own since day one. Changing this around
                              is a real challenge. For this reason, I am currently acting as both
                              the Scrum master and the product owner until I can find someone
                              outside the dev team that will take the product owner role and manage
                              priorities.

                              But overall, the implementation of a well defined process (Scrum) has
                              been welcomed by the client/marketing/sales side as they know what we
                              are working on now and they have control on what is next.

                              -
                              Claude Montpetit
                              http://www.montpetit.net
                            • Ron Jeffries
                              ... The teams I have worked with can estimate things at a rate of several hundred per day, so I would think that if all you need is an estimate, you could just
                              Message 14 of 22 , Apr 6, 2004
                              • 0 Attachment
                                On Tuesday, April 6, 2004, at 5:58:14 PM, Claude Montpetit wrote:

                                > Implementing Scrum is very new to me and I am not sure about how to
                                > deal with, for example, urgent estimates that must enter the current
                                > sprint. Telling the salesman to wait for the next iteration for the
                                > quote is not usually a good thing as it means that the implementation
                                > would in theory start very late:

                                The teams I have worked with can estimate things at a rate of several
                                hundred per day, so I would think that if all you need is an estimate, you
                                could just wander in and ask. But of course there's this pig / chicken rule
                                in Scrum, so I don't know what the official answer should be.

                                On the other hand, my experience with sales people suggests that often
                                things need not be as urgent as they tend to be described ...

                                Ron Jeffries
                                www.XProgramming.com
                                Fear is the mindkiller. --Bene Gesserit Litany Against Fear
                              • Mike Cohn
                                If these are truly one or two at a time I handle them in the next morning s Daily Scrum. We ll do the Scrum meeting as normal then everyone will stay for a few
                                Message 15 of 22 , Apr 6, 2004
                                • 0 Attachment
                                  If these are truly one or two at a time I handle them in the next morning's
                                  Daily Scrum. We'll do the Scrum meeting as normal then everyone will stay
                                  for a few minutes and we'll estimate a story or two from the previous day or
                                  that came up early in the morning.

                                  We routinely also slip in an occasional one-hour estimating session in each
                                  sprint just to look outward at future stories. That will eventually stop but
                                  we're working through a large backlog of unestimated stories.

                                  --Mike Cohn
                                  Author of User Stories Applied for Agile Software Development
                                  www.userstories.com

                                  -----Original Message-----
                                  From: Ron Jeffries [mailto:ronjeffries@...]
                                  Sent: Tuesday, April 06, 2004 6:04 PM
                                  To: scrumdevelopment@yahoogroups.com
                                  Subject: Re: [scrumdevelopment] Scrum and requirements (was Re: SCRUM
                                  process with other methodologies)

                                  On Tuesday, April 6, 2004, at 5:58:14 PM, Claude Montpetit wrote:

                                  > Implementing Scrum is very new to me and I am not sure about how to
                                  > deal with, for example, urgent estimates that must enter the current
                                  > sprint. Telling the salesman to wait for the next iteration for the
                                  > quote is not usually a good thing as it means that the implementation
                                  > would in theory start very late:

                                  The teams I have worked with can estimate things at a rate of several
                                  hundred per day, so I would think that if all you need is an estimate, you
                                  could just wander in and ask. But of course there's this pig / chicken rule
                                  in Scrum, so I don't know what the official answer should be.

                                  On the other hand, my experience with sales people suggests that often
                                  things need not be as urgent as they tend to be described ...

                                  Ron Jeffries
                                  www.XProgramming.com
                                  Fear is the mindkiller. --Bene Gesserit Litany Against Fear



                                  To Post a message, send it to: scrumdevelopment@...
                                  To Unsubscribe, send a blank message to:
                                  scrumdevelopment-unsubscribe@...
                                  Yahoo! Groups Links
                                • Claude Montpetit
                                  Just in case it was misunderstood, what I was referring to in my post were not the usual product backlog estimates, but estimates used to establish a fixed
                                  Message 16 of 22 , Apr 6, 2004
                                  • 0 Attachment
                                    Just in case it was misunderstood, what I was referring to in my post
                                    were not the usual product backlog estimates, but estimates used to
                                    establish a fixed price bid for some requested product extensions.
                                    Because they are for fixed price extensions, these estimation
                                    requests become stories on their own as opposed to the rough estimates
                                    that we set on most stories that enter the backlog.

                                    (I have personnally never worked on a team that can produce such
                                    estimates at a rate of hundred per day... must be great though ;)

                                    Claude

                                    --- In scrumdevelopment@yahoogroups.com, Ron Jeffries
                                    <ronjeffries@X...> wrote:
                                    > On Tuesday, April 6, 2004, at 5:58:14 PM, Claude Montpetit wrote:
                                    >
                                    >>Implementing Scrum is very new to me and I am not sure about how to
                                    >>deal with, for example, urgent estimates that must enter the current
                                    >>sprint. Telling the salesman to wait for the next iteration for the
                                    >>quote is not usually a good thing as it means that the implementation
                                    >>would in theory start very late:
                                    >
                                    >The teams I have worked with can estimate things at a rate of several
                                    >hundred per day, so I would think that if all you need is an
                                    estimate, you
                                    >could just wander in and ask. But of course there's this pig
                                    > / chicken rule in Scrum, so I don't know what the official answer
                                    should be.
                                    >
                                    >On the other hand, my experience with sales people suggests that
                                    >often things need not be as urgent as they tend to be described ...
                                    >
                                    > Ron Jeffries
                                    > www.XProgramming.com
                                    > Fear is the mindkiller. --Bene Gesserit Litany Against Fear
                                  • Ron Jeffries
                                    ... Yes. If it s a whole product, that would take a half-day or a day. I m talking about story estimates. If the group is commonly called upon to do that, I
                                    Message 17 of 22 , Apr 7, 2004
                                    • 0 Attachment
                                      On Tuesday, April 6, 2004, at 11:33:23 PM, Claude Montpetit wrote:

                                      > Just in case it was misunderstood, what I was referring to in my post
                                      > were not the usual product backlog estimates, but estimates used to
                                      > establish a fixed price bid for some requested product extensions.
                                      > Because they are for fixed price extensions, these estimation
                                      > requests become stories on their own as opposed to the rough estimates
                                      > that we set on most stories that enter the backlog.

                                      > (I have personnally never worked on a team that can produce such
                                      > estimates at a rate of hundred per day... must be great though ;)

                                      Yes. If it's a whole product, that would take a half-day or a day. I'm
                                      talking about story estimates.

                                      If the group is commonly called upon to do that, I guess I'd just plan for
                                      it in the team's velocity.

                                      Ron Jeffries
                                      www.XProgramming.com