Consistent sprint lengths

Expand Messages
  • CJ
    Why is consistent sprint length so important? Are there exceptions (like different points in the project)?
    Message 1 of 5 , Mar 1, 2008
      Why is consistent sprint length so important? Are there exceptions
      (like different points in the project)?
    • David H.
      ... If you search the archive of this list you will find a multitude of answers. The one I like to give most is: 1.) Commitment 2.) Batch sizes (amount of work
      Message 2 of 5 , Mar 1, 2008
        >
        > Why is consistent sprint length so important? Are there exceptions
        > (like different points in the project)?
        >
        If you search the archive of this list you will find a multitude of
        answers. The one I like to give most is:

        1.) Commitment
        2.) Batch sizes (amount of work you do)
        3.) Adaptability
        4.) Predictability
        5.) Self-organisation patterns that develop.

        By having a steady heartbeat your team can feel at ease in the
        environment they have to work in. There is no reason at all to have
        varying sprint lengths. If you started out with 20 days and after 5
        sprints your teams wants to go to 10day sprints, by all means do.

        -d

        >



        --
        Sent from gmail so do not trust this communication.
        Do not send me sensitive information here, ask for my none-gmail accounts.

        "Therefore the considerations of the intelligent always include both
        benefit and harm." - Sun Tzu
      • tony pagliocco
        From my experience, sprint lenght consistency is important because it allows there to be estimation set on certain products in the backlog based on their
        Message 3 of 5 , Mar 1, 2008
          From my experience, sprint lenght consistency is important because it allows there to be estimation set on certain products in the backlog based on their priority in the list.
           
          If you were to change length of the sprint each time , it would never allow for accurate destimation because there would never be a proper determination of how many story points should go into each sprint.
           
          The books I've read have all said that sprint go 4 weeks , but our team is using 2 week sprints since we started and find them working well.
           
          Tony

          CJ <laraidah@...> wrote:
          Why is consistent sprint length so important? Are there exceptions
          (like different points in the project)?



          Be a better friend, newshound, and know-it-all with Yahoo! Mobile. Try it now.

        • Andreas Leidig
          Another aspect is the external view of your project: it is much easier to make outside stakeholders shut up for a while if you give them a clear picture of
          Message 4 of 5 , Mar 2, 2008
            Another aspect is the external view of your project: it is much easier
            to make outside stakeholders shut up for a while if you give them a
            clear picture of when they can influence the project and especially
            when they will receive feedback.

            Consider the following situation as an example:

            You are in a "consolidating middleware project". Your product
            communicates with a multitude of backend systems and is used by quite
            a number of different frontends. Typically one fronted is for one
            specific customer and often associated with one distinct backend.
            If you are trying to co-ordinate the different customers as well as
            the different systems it will help you very much if you can tell these
            outsiders: OK, but we have a 3-week rhythm of delivering results.

            In this example the other systems didn't use scrum and were not part
            of our organization. But at the point they understood that this rhythm
            is short enough to adapt to customer's delivery wishes and also long
            enough to get productive in developping, they were really happy and
            synchronized with our beat.

            Hope this helps illustrating the importance.

            Andreas
          • andybrandt_dot_net
            Hi! ... team is using 2 week sprints since we started and find them working well. Same here. We started with 4 weeks but it didn t work well. On Mike Cohn s
            Message 5 of 5 , Mar 4, 2008
              Hi!

              --- In scrumdevelopment@yahoogroups.com, tony pagliocco >
              > The books I've read have all said that sprint go 4 weeks , but our
              team is using 2 week sprints since we started and find them working well.

              Same here. We started with 4 weeks but it didn't work well. On Mike
              Cohn's advice we switched to 2 weeks and it worked great for more than
              a year now on few projects. But now on one project we've even switched
              to 1 week sprints and first impressions of the team are quite positive.

              Best regards,
              Andy

              >
              > Tony
              >
              > CJ <laraidah@...> wrote:
              > Why is consistent sprint length so important? Are there
              exceptions
              > (like different points in the project)?
              >
              >
              >
              >
              >
              >
              > ---------------------------------