When do "story points" get frozen?

Expand Messages
  • Sam Roberts
    For stuff that is 1 or 2 sprints out we just slap points on them in a rough way (we use days as our units to make it seem a bit concrete, but with no
    Message 1 of 6 , Nov 1, 2007
    • 0 Attachment
      For stuff that is 1 or 2 sprints out we just slap points on them in a
      rough way (we use "days" as our units to make it seem a bit concrete,
      but with no expectation that it actually means a single day of work).

      As it gets closer to inclusion in a sprint, we break it apart into
      smaller demonstrable chunks of work, and the points gets more precise
      (often grows, sometimes shrinks).

      I know that part of the fuzziness of all the estimating is good - you
      give rough estimates, they aveage over time, and you measure velocity,
      so the roughness and biases smooth out.

      But when do we freeze this process?

      Should adjustments of story points be done in the sprint planning
      meeting?

      What about if half-way through the sprint we realize that something we
      thought would be a few days work and worth a few points can be done in a
      few hours? Won't counting this as many points distory the accuracy of
      the velocity measurement?


      Cheers,
      Sam
    • Ryan Cooper
      I don t have a good answer to how far ahead of a sprint to lock down your estimates, but I would strongly advise against re-estimating after starting work on
      Message 2 of 6 , Nov 1, 2007
      • 0 Attachment
        I don't have a good answer to how far ahead of a sprint to "lock down"
        your estimates, but I would strongly advise against re-estimating
        after starting work on a story.

        The predictive power of your velocity exists because you are comparing
        'a priori' estimates of features previously completed to 'a priori'
        estimates of features to be completed in the future. If you revise an
        estimate after starting work on a story, it becomes an 'a posteriori'
        estimate. This will make your velocity a more "real" measure of how
        much work you did, but will make velocity a less useful predicting
        tool (since you can't have a posteriori estimates of work that will be
        done in the future)

        Mike Cohn covers this idea in more depth here:
        http://blog.mountaingoatsoftware.com/?p=13

        Cheers,
        Ryan


        On Nov 1, 2007 2:17 PM, Sam Roberts <sroberts@...> wrote:

        > What about if half-way through the sprint we realize that something we
        > thought would be a few days work and worth a few points can be done in a
        > few hours? Won't counting this as many points distory the accuracy of
        > the velocity measurement?
        >
        >
        > Cheers,
        > Sam
        >
        >
        >
        > To Post a message, send it to: scrumdevelopment@...
        > To Unsubscribe, send a blank message to: scrumdevelopment-unsubscribe@...
        > Yahoo! Groups Links
        >
        >
        >
        >
      • Arnette, Bill
        I understand that you don t want to re-estimate the story points during a sprint. But how about if you esitmate a story for the product backlog thinking
        Message 3 of 6 , Nov 1, 2007
        • 0 Attachment
          I understand that you don't want to re-estimate the story points during a sprint.  But how about if you esitmate a story for the product backlog thinking you'll do it one way, but then for the sprint, realize that you could do it another way that still meets the story but can be done in half the time?  Re-estimate the story during the sprint planning?
           
           
          --
          Bill Arnette
           
           


          From: scrumdevelopment@yahoogroups.com [mailto:scrumdevelopment@yahoogroups.com] On Behalf Of Ryan Cooper
          Sent: Thursday, November 01, 2007 1:28 PM
          To: scrumdevelopment@yahoogroups.com
          Subject: Re: [scrumdevelopment] When do "story points" get frozen?

          I don't have a good answer to how far ahead of a sprint to "lock down"
          your estimates, but I would strongly advise against re-estimating
          after starting work on a story.

          The predictive power of your velocity exists because you are comparing
          'a priori' estimates of features previously completed to 'a priori'
          estimates of features to be completed in the future. If you revise an
          estimate after starting work on a story, it becomes an 'a posteriori'
          estimate. This will make your velocity a more "real" measure of how
          much work you did, but will make velocity a less useful predicting
          tool (since you can't have a posteriori estimates of work that will be
          done in the future)

          Mike Cohn covers this idea in more depth here:
          http://blog. mountaingoatsoft ware.com/ ?p=13

          Cheers,
          Ryan

          On Nov 1, 2007 2:17 PM, Sam Roberts <sroberts@uniserve. com> wrote:

          > What about if half-way through the sprint we realize that
          something we
          > thought would be a few days work and worth a few points can
          be done in a
          > few hours? Won't counting this as many points distory the
          accuracy of
          > the velocity measurement?
          >
          >
          >
          Cheers,
          > Sam
          >
          >
          >
          > To Post a message, send it
          to: scrumdevelopment@ eGroups.com
          >
          To Unsubscribe, send a blank message to: scrumdevelopment- unsubscribe@ eGroups.com
          >
          Yahoo! Groups Links
          >
          >
          >
          >

        • Rodney Wynn
          Do not get hung up on the numbers it is an estimate. Let the product owner know during planning the estimate is high and therefore you want to treat it at X
          Message 4 of 6 , Nov 1, 2007
          • 0 Attachment
            Do not get hung up on the numbers it is an estimate. 

            Let the product owner know during planning the estimate is high and therefore you want to treat it at "X" umber now.
            Then continue with the planning under the "re-estimated" value!

            Rodney

            "Arnette, Bill" <billa@...> wrote:
            I understand that you don't want to re-estimate the story points during a sprint.  But how about if you esitmate a story for the product backlog thinking you'll do it one way, but then for the sprint, realize that you could do it another way that still meets the story but can be done in half the time?  Re-estimate the story during the sprint planning?
             
             
            --
            Bill Arnette
             
             


            From: scrumdevelopment@ yahoogroups. com [mailto:scrumdevelo pment@yahoogroup s.com] On Behalf Of Ryan Cooper
            Sent: Thursday, November 01, 2007 1:28 PM
            To: scrumdevelopment@ yahoogroups. com
            Subject: Re: [scrumdevelopment] When do "story points" get frozen?

            I don't have a good answer to how far ahead of a sprint to "lock down"
            your estimates, but I would strongly advise against re-estimating
            after starting work on a story.

            The predictive power of your velocity exists because you are comparing
            'a priori' estimates of features previously completed to 'a priori'
            estimates of features to be completed in the future. If you revise an
            estimate after starting work on a story, it becomes an 'a posteriori'
            estimate. This will make your velocity a more "real" measure of how
            much work you did, but will make velocity a less useful predicting
            tool (since you can't have a posteriori estimates of work that will be
            done in the future)

            Mike Cohn covers this idea in more depth here:
            http://blog. mountaingoatsoft ware.com/ ?p=13

            Cheers,
            Ryan

            On Nov 1, 2007 2:17 PM, Sam Roberts <sroberts@uniserve. com> wrote:

            > What about if half-way through the sprint we realize that something we
            > thought would be a few days work and worth a few points can be done in a
            > few hours? Won't counting this as many points distory the accuracy of
            > the velocity measurement?
            >
            >
            > Cheers,
            > Sam
            >
            >
            >
            > To Post a message, send it to: scrumdevelopment@ eGroups.com
            > To Unsubscribe, send a blank message to: scrumdevelopment- unsubscribe@ eGroups.com
            > Yahoo! Groups Links
            >
            >
            >
            >

            __________________________________________________
            Do You Yahoo!?
            Tired of spam? Yahoo! Mail has the best spam protection around
            http://mail.yahoo.com

          • Mark Graybill
            The power of user stories is how they are estimated and for what context they are used, and that they are separated from sprint planning in terms of hours.
            Message 5 of 6 , Nov 1, 2007
            • 0 Attachment
              The power of user stories is how they are estimated and for what context they are used, and that they are separated from sprint planning in terms of hours.  They should be done before sprint planning - they need to be done in purity in their own context.

              The context is in the realm of the business and product/release planning, not task-level development forecasting.  It should be in units that do not even sound like hours (triggers different thought processes and cognitions, veering us way off).  It should also be done on gut hunch at the team level in the fashion of individual forcasting in private before sharing with team.  This reduces group process loss (psych) and thus less skewed.  Finally, the gut hunch if done well can be taught - our "Thin Slicing".
               
              There is actually quite a bit of corroborating scientific evidence explaing this.
               
              Cheers!
              Mark
               
               
              ----- Original Message -----
              Sent: Thursday, November 01, 2007 1:47 PM
              Subject: RE: [scrumdevelopment] When do "story points" get frozen?

              I understand that you don't want to re-estimate the story points during a sprint.  But how about if you esitmate a story for the product backlog thinking you'll do it one way, but then for the sprint, realize that you could do it another way that still meets the story but can be done in half the time?  Re-estimate the story during the sprint planning?
               
               
              --
              Bill Arnette
               
               


              From: scrumdevelopment@ yahoogroups. com [mailto:scrumdevelo pment@yahoogroup s.com] On Behalf Of Ryan Cooper
              Sent: Thursday, November 01, 2007 1:28 PM
              To: scrumdevelopment@ yahoogroups. com
              Subject: Re: [scrumdevelopment] When do "story points" get frozen?

              I don't have a good answer to how far ahead of a sprint to "lock down"
              your estimates, but I would strongly advise against re-estimating
              after starting work on a story.

              The predictive power of your velocity exists because you are comparing
              'a priori' estimates of features previously completed to 'a priori'
              estimates of features to be completed in the future. If you revise an
              estimate after starting work on a story, it becomes an 'a posteriori'
              estimate. This will make your velocity a more "real" measure of how
              much work you did, but will make velocity a less useful predicting
              tool (since you can't have a posteriori estimates of work that will be
              done in the future)

              Mike Cohn covers this idea in more depth here:
              http://blog. mountaingoatsoft ware.com/ ?p=13

              Cheers,
              Ryan

              On Nov 1, 2007 2:17 PM, Sam Roberts <sroberts@uniserve. com> wrote:

              > What about if half-way through the sprint we realize that something we
              > thought would be a few days work and worth a few points can be done in a
              > few hours? Won't counting this as many points distory the accuracy of
              > the velocity measurement?
              >
              >
              > Cheers,
              > Sam
              >
              >
              >
              > To Post a message, send it to: scrumdevelopment@ eGroups.com
              > To Unsubscribe, send a blank message to: scrumdevelopment- unsubscribe@ eGroups.com
              > Yahoo! Groups Links
              >
              >
              >
              >

            • Martin Schapendonk
              ... No problem to re-estimate during the sprint planning. It happens all the time as a PO clarifies user stories and negotiates the sprint backlog. When the
              Message 6 of 6 , Nov 2, 2007
              • 0 Attachment
                On 11/1/07, Arnette, Bill <billa@...> wrote:
                > I understand that you don't want to re-estimate the story points during a sprint. But how
                > about if you esitmate a story for the product backlog thinking you'll do it one way, but then
                > for the sprint, realize that you could do it another way that still meets the story but can be
                > done in half the time? Re-estimate the story during the sprint planning?

                No problem to re-estimate during the sprint planning. It happens all
                the time as a PO clarifies user stories and negotiates the sprint
                backlog.

                When the sprint planning is over, the sprint backlog has been
                committed to and the sprint has started, that is the moment to freeze
                your story point estimates, for reasons already pointed out (estimates
                become less valuable for predictions if adjusted with knowledge not
                normally known during the estimation process).

                Martin

                --
                Martin Schapendonk, martin@...