Re: Masters Thesis on Agile Projects

Expand Messages
  • woynam
    Exactly. We ve had several projects that were canceled within the first few sprints. The development team kept finding contradictions in the requirements, such
    Message 1 of 5 , Oct 2, 2007
    • 0 Attachment
      Exactly. We've had several projects that were canceled within the
      first few sprints. The development team kept finding contradictions in
      the requirements, such that the requirements couldn't be implemented
      without breaking some other critical aspect of the system.

      From a business standpoint, one might consider the projects a failure.
      However, Scrum did it's job quite well, and prevented us from spending
      months working on something that simply couldn't be delivered.

      Mark

      --- In scrumdevelopment@yahoogroups.com, "John-Mason P. Shackelford"
      <jpshack@...> wrote:
      >
      > Padhma,
      >
      > How do you defined failed for the purpose of your study?
      >
      > --
      > John-Mason Shackelford
      >
      > Software Development Coach
      > Pearson
      >
      > 2510 North Dodge St.
      > Iowa City, IA 52245
      > ph. 319-354-9200x6214
      > john-mason.shackelford@...
      > http://pearsonschool.com
      >
    • Emiliano Heyns
      ... Same here. The fact that we aborted sprint 2 was probably the one of the best things we ve done so far in our project. It sent a clear message that we
      Message 2 of 5 , Oct 2, 2007
      • 0 Attachment
        On 10/2/07, woynam <woyna@...> wrote:

        Exactly. We've had several projects that were canceled within the
        first few sprints. The development team kept finding contradictions in
        the requirements, such that the requirements couldn't be implemented
        without breaking some other critical aspect of the system.

        From a business standpoint, one might consider the projects a failure.
        However, Scrum did it's job quite well, and prevented us from spending
        months working on something that simply couldn't be delivered.

        Same here. The fact that we aborted sprint 2 was probably the one of the best things we've done so far in our project. It sent a clear message that we can't, and thus won't, work on a project that is doomed to fail. The message was received loud and clear, things have shaped up considerably since then, and we're back on track. Not perfect, but probably as good as the organization will allow right now.

        Emile