Re: Metrics

Expand Messages
  • Deb
    My question about utilization stems from my understanding of the difference between efficiency & effectiveness : everybody busy? doesn t tell you much about
    Message 1 of 22 , May 1, 2006
    • 0 Attachment
      My question about utilization stems from my understanding of the
      difference between efficiency & effectiveness :

      "everybody busy?" doesn't tell you much about how well you are
      delivering value.

      In our sim, iteration 1 has specialists very busy in a waterfall
      producing pieces of things customers don't value because they are
      incomplete. In iteration 3, *generalists* are very busy producing
      little waste and 3x the customer value in the same space of time.

      In this thread, in fact the writer was measuring "% of busyness
      applied to sprint work" which is quite different. That's what I wanted
      to know :-)

      deb

      --- In scrumdevelopment@yahoogroups.com, Ron Jeffries
      <ronjeffries@...> wrote:
      >
      > On Sunday, April 30, 2006, at 1:57:46 PM, Deb wrote:
      >
      > > What exactly do you measure to track utilization?
      >
      > > I'm wondering because I'm currently working on a sim about metrics
      > > where both scenarios A and C have high utilization (people busy close
      > > to 100% of the time) but A produces 2 finished products during the
      > > time that C produces 7.
      >
      > Tell us more about what's going on in this sim? What's causing the
      > difference in productivity? What insight into the sim would you like
      > to have that you don't have?
      >
      > Ron Jeffries
      > www.XProgramming.com
      > Learn the principle, abide by the principle, and dissolve the principle.
      > -- Bruce Lee
      >
    • Mary Poppendieck
      Deb, I still don t understand what you are trying to measure. Utilization is a poisonous measurement and attempting to achieve high utilization is one of the
      Message 2 of 22 , May 1, 2006
      • 0 Attachment
        Deb,

        I still don't understand what you are trying to measure.

        Utilization is a poisonous measurement and attempting to achieve
        high utilization is one of the most sub-optimizing practices there
        is. Slack time IS NOT WASTE, it is required for rapid delivery, and
        because of this it underlies the ability to deliver high quality.

        This is not to say that you need to have low utilization - it is
        only to say that attempts to maximize utilization are virtually
        guaranteed to decrease it.

        If you were an operations manager and tried to optimize the
        utilization of your servers, you'd get fired. Development managers
        who try to optimize the utilization of their people have no sense of
        queueing theory, or perhaps think that the laws of mathematics do
        not apply to them. They are wrong.

        --- In scrumdevelopment@yahoogroups.com, "Deb" <deborah@...> wrote:
        >
        > My question about utilization stems from my understanding of the
        > difference between efficiency & effectiveness :
        >
        > "everybody busy?" doesn't tell you much about how well you are
        > delivering value.
        >
        > In our sim, iteration 1 has specialists very busy in a waterfall
        > producing pieces of things customers don't value because they are
        > incomplete. In iteration 3, *generalists* are very busy producing
        > little waste and 3x the customer value in the same space of time.
        >
        > In this thread, in fact the writer was measuring "% of busyness
        > applied to sprint work" which is quite different. That's what I
        wanted
        > to know :-)
        >
        > deb
        >
        > --- In scrumdevelopment@yahoogroups.com, Ron Jeffries
        > <ronjeffries@> wrote:
        > >
        > > On Sunday, April 30, 2006, at 1:57:46 PM, Deb wrote:
        > >
        > > > What exactly do you measure to track utilization?
        > >
        > > > I'm wondering because I'm currently working on a sim about
        metrics
        > > > where both scenarios A and C have high utilization (people
        busy close
        > > > to 100% of the time) but A produces 2 finished products during
        the
        > > > time that C produces 7.
        > >
        > > Tell us more about what's going on in this sim? What's causing
        the
        > > difference in productivity? What insight into the sim would you
        like
        > > to have that you don't have?
        > >
        > > Ron Jeffries
        > > www.XProgramming.com
        > > Learn the principle, abide by the principle, and dissolve the
        principle.
        > > -- Bruce Lee
        > >
        >
      • Deb
        Well, yes. The point of our sim is that when we organize around value we can produce more. When we organize around utilization, we get stuck because 100%
        Message 3 of 22 , May 1, 2006
        • 0 Attachment
          Well, yes.

          The point of our sim is that when we organize around value we can
          produce more. When we organize around utilization, we get stuck
          because 100% "busyness" seems to signal no change needed (or worse:
          more people needed - a total red herring). Our third iteration happens
          to have utilization near 100% but that's not what we are measuring. In
          that iteration we aim to maximize completed "products" i.e. customer
          value.

          Good point though: I'll make a note to mention slack directly during
          the sim :-) and to be sure that production of value is underlined as
          the aim of iteration 3!

          thanks, Mary
          deb

          --- In scrumdevelopment@yahoogroups.com, "Mary Poppendieck"
          <maryp@...> wrote:
          >
          > Deb,
          >
          > I still don't understand what you are trying to measure.
          >
          > Utilization is a poisonous measurement and attempting to achieve
          > high utilization is one of the most sub-optimizing practices there
          > is. Slack time IS NOT WASTE, it is required for rapid delivery, and
          > because of this it underlies the ability to deliver high quality.
          >
          > This is not to say that you need to have low utilization - it is
          > only to say that attempts to maximize utilization are virtually
          > guaranteed to decrease it.
          >
          > If you were an operations manager and tried to optimize the
          > utilization of your servers, you'd get fired. Development managers
          > who try to optimize the utilization of their people have no sense of
          > queueing theory, or perhaps think that the laws of mathematics do
          > not apply to them. They are wrong.
          >
          > --- In scrumdevelopment@yahoogroups.com, "Deb" <deborah@> wrote:
          > >
          > > My question about utilization stems from my understanding of the
          > > difference between efficiency & effectiveness :
          > >
          > > "everybody busy?" doesn't tell you much about how well you are
          > > delivering value.
          > >
          > > In our sim, iteration 1 has specialists very busy in a waterfall
          > > producing pieces of things customers don't value because they are
          > > incomplete. In iteration 3, *generalists* are very busy producing
          > > little waste and 3x the customer value in the same space of time.
          > >
          > > In this thread, in fact the writer was measuring "% of busyness
          > > applied to sprint work" which is quite different. That's what I
          > wanted
          > > to know :-)
          > >
          > > deb
          > >
          > > --- In scrumdevelopment@yahoogroups.com, Ron Jeffries
          > > <ronjeffries@> wrote:
          > > >
          > > > On Sunday, April 30, 2006, at 1:57:46 PM, Deb wrote:
          > > >
          > > > > What exactly do you measure to track utilization?
          > > >
          > > > > I'm wondering because I'm currently working on a sim about
          > metrics
          > > > > where both scenarios A and C have high utilization (people
          > busy close
          > > > > to 100% of the time) but A produces 2 finished products during
          > the
          > > > > time that C produces 7.
          > > >
          > > > Tell us more about what's going on in this sim? What's causing
          > the
          > > > difference in productivity? What insight into the sim would you
          > like
          > > > to have that you don't have?
          > > >
          > > > Ron Jeffries
          > > > www.XProgramming.com
          > > > Learn the principle, abide by the principle, and dissolve the
          > principle.
          > > > -- Bruce Lee
          > > >
          > >
          >
        • Deb
          ... negative), I m ... else had ... ask a ... recommend this ... product ... I like this! I m going to suggest it to my current client. Right now customer sat
          Message 4 of 22 , May 1, 2006
          • 0 Attachment
            --- In scrumdevelopment@yahoogroups.com, "MaryP" <mpoppendieck@...> wrote:
            >
            > >>From: mpkirby@...
            >
            > >>I've got a manager who asks the very simple question:
            >
            >
            >
            > >>"What metrics do I collect that tells me this agile stuff is actually
            > doing my group any good. If there is no benefit (positive or
            negative), I'm
            > much less inclined to make a change"
            >
            >
            >
            > >>I thought it was a good question, and I was wondering if anyone
            else had
            > >>similar questions.
            >
            >
            >
            > Mike,
            >
            >
            >
            > Here are the three metrics I recommend:
            >
            >
            >
            > 1) Cycle time
            >
            > 2) Business Case Realization
            >
            > 3) Net Promoter Score
            >
            >
            >
            > I'll take them in reverse order.
            >
            >
            >
            > Net Promoter Score - this is a measure of customer satisfaction. See
            > details in the book "The Ultimate Question" by Fred Reichheld. You
            ask a
            > simple question: on a scale of 0-10, how likely are you to
            recommend this
            > team/organization to a friend or colleague? There are three kinds of
            > customers: promoters (10s and 9s) who would recommend the product,
            > detractors (6s through 0s) who would recommend that people avoid the
            product
            > and neutral customers (7s and 8s) who have no bias one way or the other.
            > With this data you can calculate a "net promoter" score: subtract the
            > percentage of detractors from the percentage of promoters.

            I like this! I'm going to suggest it to my current client. Right now
            customer sat is a major goal but they wanted to do it anecdotally
            (small company). After public kudos last week, the time seems ripe to
            start asking this more formally.
            >
            >
            > Business Case Realization - Every product or project should be based
            on the
            > business case of some sort - Profit & Loss, ROI, whatever. Even
            non-profits
            > and government organizations have business cases. I propose that
            measuring
            > the *realization* of the business case is the best way to make the
            > appropriate tradeoffs between cost, schedule, etc. Yes, this is a
            long term
            > measurement, but aren't we trying to create long term value?
            >
            At a former client there was the whole "cost centre" thing... there
            are few business cases made at the customer level, so they know what a
            project costs but not what it's *worth* to the business. This is
            deadly for the reputation of a team - they can be perceived as a dead
            weight, when really they are committed and working hard! Talk about
            hiding your light under a bushel! Ambushelled, to coin a word :-)

            >
            >
            > Cycle Time - Here's an example of how to measure cycle time:
            >
            >
            >
            > 1. When a defect goes on your defect
            > list, give it a date. When it gets resolved, calculate how long it
            was on
            > the list. Keep track of two numbers: Average cycle time of resolved
            > defects and average age of items on the defect list.
            >
            > 2. When an item goes on the product
            > backlog, give it a date. If it is broken out into smaller pieces,
            each piece
            > keeps the original date. If two items are combined, the new item
            gets the
            > older date. When an item is deployed, subtract the original date
            from the
            > deployment date. This is its cycle time. Compute the average cycle
            time
            > and the standard deviation for the items in each release. Also
            compute the
            > average waiting time of each item still in the backlog.
            >
            > I have heard objections to this approach, particularly: I put big
            items on
            > the product backlog; no one has spent any time on them and customers
            don't
            > consider them an "order."
            >
            > 3. In this case you might divide
            backlog
            > items into three categories:
            >
            > A) Features customers think they have "ordered" or items that
            have had
            > any measurable investment of time.

            Mary, how would you relate this to the Scrum product backlog
            maintenance cycle? Current and next N releases? (I know, it will
            differ by client, just trying to get a feel)

            >
            > B) Stuff we need to break out in order to think about architecture,
            > estimate overall schedule, etc.

            This feels like "too big to put into a sprint as-is"
            or "requirement hasn't been well thought out yet" - definitely not
            stuff at the top of the prioritized backlog.
            >
            > C) Really big bullet product roadmap items
            >
            bottom-of-the-backlog stuff, "Replace General Ledger" etc.

            > Items go into the highest category that fits - so if there are customers
            > that are waiting for a roadmap item, it's an A.
            >
            > Date everything as it goes on the backlog. Add a new date if an item
            moves
            > from C to B. Add another date when it moves to A.
            >
            > When an item is deployed, compute three categories of cycle times:
            >
            > 1)
            Elapsed
            > time since being assigned Category A
            >
            > 2)
            Elapsed
            > time since being assigned Category B
            >
            > 3)
            Elapsed
            > time since being assigned Category C
            >
            > Every release, compute the average cycle time and standard deviation for
            > each of the three categories. See what the numbers tell you. If you need
            > different categories, create them.
            >
            This feels like drawing a line on the product backlog: real
            requirements, potential requirements, nice-to-haves. Am I wrong?

            > While you are at it, measure the average age of the A items left in the
            > backlog. Is it within a release or two of the average cycle time of
            the A
            > items in the release? What does this tell you?

            I need to think more about this one... :-)
            Thanks Mary.

            >
            >
            >
            > Best of luck!
            >
            >
            >
            > Mary Poppendieck
            >
            > www.poppendieck.com
            >
          • Steven Gordon
            ... I have been dismissing utilization as a valid metric for intuitive reasons that resemble yours. However, your server example makes me question that
            Message 5 of 22 , May 1, 2006
            • 0 Attachment
              On 5/1/06, Mary Poppendieck <maryp@...> wrote:
              Deb,

              I still don't understand what you are trying to measure.

              Utilization is a poisonous measurement and attempting to achieve
              high utilization is one of the most sub-optimizing  practices there
              is.  Slack time IS NOT WASTE, it is required for rapid delivery, and
              because of this it underlies the ability to deliver high quality.

              This is not to say that you need to have low utilization - it is
              only to say that attempts to maximize utilization are virtually
              guaranteed to decrease it.

              If you were an operations manager and tried to optimize the
              utilization of your servers, you'd get fired.  Development managers
              who try to optimize the utilization of their people have no sense of
              queueing theory, or perhaps think that the laws of mathematics do
              not apply to them.  They are wrong.
               
              I have been dismissing utilization as a valid metric for intuitive reasons that resemble yours.
               
              However, your server example makes me question that assumption now.  It is indeed standard practice to measure utilization of servers - in order to make sure that utilization is not too close to 100%.
               
              Maybe, we should be measuring utilization, but with a target of something like 70-80% rather than 100%.  Surely, < 50% utilization of resources is an indication of potential waste, just as more than 80% would be an indication of potential systemic inefficiency and unameliorated risk.
               
              Steven Gordon

               

               
            • leigh_mullin
              In my experience; utilisation, as measured by asking people to book time to various codes in a time system, some of which are seen as productive/revenue
              Message 6 of 22 , May 1, 2006
              • 0 Attachment
                In my experience; utilisation, as measured by asking people to book
                time to various codes in a time system, some of which are seen as
                productive/revenue generating and some as unproductive/non revenue
                generating, simply encourages people to book time to codes that keep
                managers happy. Sure, you get higher utilisation. But you don't get
                more productive/valuable code or design. Moreover, just because
                something is coded as revenue generating doesn't mean that those that
                are non revenue generating aren't important.

                Utilisation is a measure that finance or IT managers that aren't
                software literate like to look at. It makes them feel happy.

                --- In scrumdevelopment@yahoogroups.com, "Steven Gordon"
                <sgordonphd@...> wrote:
                >
                > On 5/1/06, Mary Poppendieck <maryp@...> wrote:
                > >
                > > Deb,
                > >
                > > I still don't understand what you are trying to measure.
                > >
                > > Utilization is a poisonous measurement and attempting to achieve
                > > high utilization is one of the most sub-optimizing practices there
                > > is. Slack time IS NOT WASTE, it is required for rapid delivery, and
                > > because of this it underlies the ability to deliver high quality.
                > >
                > > This is not to say that you need to have low utilization - it is
                > > only to say that attempts to maximize utilization are virtually
                > > guaranteed to decrease it.
                > >
                > > If you were an operations manager and tried to optimize the
                > > utilization of your servers, you'd get fired. Development managers
                > > who try to optimize the utilization of their people have no sense of
                > > queueing theory, or perhaps think that the laws of mathematics do
                > > not apply to them. They are wrong.
                >
                >
                > I have been dismissing utilization as a valid metric for intuitive
                reasons
                > that resemble yours.
                >
                > However, your server example makes me question that assumption now. It
                > is indeed standard practice to measure utilization of servers - in
                order to
                > make sure that utilization is not too close to 100%.
                >
                > Maybe, we should be measuring utilization, but with a target of
                something
                > like 70-80% rather than 100%. Surely, < 50% utilization of resources is
                > an indication of potential waste, just as more than 80% would be an
                > indication of potential systemic inefficiency and unameliorated risk.
                >
                > Steven Gordon
                >
              • mpkirby@frontiernet.net
                ... So I just got Mike Cohn s book today on agile estimating (it s a great book Mike). I haven t read it completely, but leafing through it I came to a
                Message 7 of 22 , May 1, 2006
                • 0 Attachment
                  On 1 May 2006 at 15:25, Mary Poppendieck wrote:

                  > Utilization is a poisonous measurement and attempting to achieve
                  > high utilization is one of the most sub-optimizing  practices there
                  > is.  Slack time IS NOT WASTE, it is required for rapid delivery, and
                  > because of this it underlies the ability to deliver high quality.

                  So I just got Mike Cohn's book today on agile estimating (it's a great book Mike). I haven't
                  read it completely, but leafing through it I came to a section that talked about Critical Chain
                  planning.

                  Specifically, it talked about how to introduce resource buffers into tasks.

                  let's say I have 3 tasks,

                  T1 is estimated at 10 hours (+/- 2 hours)
                  T2 is estimated at 20 hours (+/- 10 hours)
                  T3 is estimated at 5 hours (+/- 1 hour).

                  There are two ways to look at the confidences. I can ignore them (what most of us do :-), I
                  can extend the estimates for each task (T1 becomes 12 hours, T2 becomes 30 hours, and
                  T3 becomes 6 hours), or I can take the confidence factor, and collapse it together into a
                  resource buffer that is used by the entire project (35 hours of tasks, with 13 hours of buffer).

                  The question (and I appologize if it is covered in your book Mike, I just haven't gotten to it
                  yet), is it seems that the way to apply this to scrum is to reduce the amount of "capacity" of
                  the team by the size of the buffer.

                  So if I have 10 stories, covering 35 story points, with 10 story points of potential error, then I
                  should make sure the team is capable of completing at least 45 story points in that iteration.

                  The idea of reducing the overall "capacity" of the iteration to factor in probabaly estimation
                  error isn't something we've considered.

                  Do others do something like that? Or do we just adjust velocity over time based on actuals,
                  rather then try to deal with confidence numbers.

                  Mike

                  ---
                  mpkirby@...
                • David H.
                  ... Personally I always thought that people are off by a certain percentage and not by a fixed factor? I thought that is also the reason in planning
                  Message 8 of 22 , May 2, 2006
                  • 0 Attachment
                    mpkirby@... wrote:

                    >
                    > T1 is estimated at 10 hours (+/- 2 hours)
                    > T2 is estimated at 20 hours (+/- 10 hours)
                    > T3 is estimated at 5 hours (+/- 1 hour).
                    >

                    Personally I always thought that people are off by a certain
                    "percentage" and not by a fixed factor? I thought that is also the
                    reason in planning optimization to reduce the batch size? Did I misread
                    that?

                    -d
                  • mpkirby@frontiernet.net
                    ... In practice, we use a delphi process for doing the estimates. Depending on the spread, we calculate the error . Typically we add 1/2 a standard
                    Message 9 of 22 , May 2, 2006
                    • 0 Attachment
                      On 2 May 2006 at 10:08, David H. wrote:

                      > Personally I always thought that people are off by a certain
                      > "percentage" and not by a fixed factor?

                      In practice, we use a delphi process for doing the estimates. Depending on the spread, we
                      calculate the "error". Typically we add 1/2 a standard deviation to the estimates. It's
                      spreadsheet magic. It works pretty well, except for larger features, where we can't seem to
                      estimate right no matter what we do.

                      Mike

                      ---
                      mpkirby@...
                    • budcookson
                      ... It works pretty well, except for larger features, where we can t seem to ... Mike - there are two things that makes my estimating a lot more accurate.
                      Message 10 of 22 , May 3, 2006
                      • 0 Attachment
                        --- In scrumdevelopment@yahoogroups.com, mpkirby@... wrote:
                        It works pretty well, except for larger features, where we can't seem to
                        > estimate right no matter what we do.
                        >
                        > Mike
                        >

                        Mike - there are two things that makes my estimating a lot more
                        accurate. First is to make sure that you never estimate something
                        that you can't get your arms around. Typically, I say that anything
                        less than 40 hours is going to be pretty accurate because you can
                        easily comprehend what it is going to take to do the work. However,
                        this number will vary depending on the people and the environment.

                        The second thing that I do is to estimate the accuracy of my estimates
                        based on the unknowns in the estimating process. It doesn't take long
                        to master the technique and it doesn't have to be applied to every
                        estimate. Just those that are larger than you feel comfortable
                        accepting the risk of missing the estimate by X% (whatever that number
                        is).

                        Good estimating to all.

                        Bud Cookson