Sprints, Plans and CCB's

Expand Messages
  • Mike Dwyer
    Recently began a very complicated sprint where an IT Team has multiple customers (hey that is life) the customers teamed, came up with a single list of
    Message 1 of 1 , Feb 24, 2006
    • 0 Attachment

      Recently began a very complicated sprint where an IT Team has multiple customers (hey that is life)  the customers teamed, came up with a single list of priorities, negotiated with the IT team and it worked like a watch – almost.  One task did not get done because the teammember was sick the last day.  Oh well retro says must take more Vitamin C.

       

      Another task took 5 days to do a 4 hour estimate.  Why?   CCB could not meet.

       

      (I’m letting the business owner’s take that forward.)

       

      Michael F. Dwyer

       

      "Planning constantly peers into the future for indications as to where a solution may emerge."

      "A Plan is a complex situation, adapting to an emerging solution." 

       