      Excellent advice.

      I would add that even if you do decide to do fixed price/scope still run it iteratively and get frequent feedback. That way you don't head down the wrong path. Also, if you are running late it's not a surprise and you can negotiate changes early. 

      Vet your customers carefully to make sure that they can provide the inputs and frequent feedback needed to run a successful Agile team. Don't chase bad money. The reputation of your team is more valuable than the revenue from a doomed project. 

      On Wed, Oct 16, 2013 at 10:53 AM, Vikrama Dhiman <vickydhiman@...> wrote:

      Hi Alex:

      I wrote about it several years ago. I think some if not all is still relevant. Here are some thumb rules (first 2 are sort of preachy - so skip to 4th for direct points);

      1. If you do want to do fixed price, you want to do it for less scope and not more (as it minimizes the risk).
      2. There is some literature on 1/3rd - 2/3rd contracts and some very little one on PS2000 contracts - dig into those.
      3. What starts as a custom fixed price billable project does not need to be so eventually too. You can easily convert a fixed-price to a more manageable time and material provided you show evidence of collaboration and business value delivery early on. So, get the project in how-so-ever you do it right now and then hopefully convert it later.
      4. Here is another technique which I have seen people use - float a RFP similar to work you would do and get 3-4 quotes yourself under a pseudo-name or something. Give you an idea of how much you should 'actually' bill. You could bill more if you have good presales team, domain expertise, proven record. 

      Good luck.

      -Vikrama Dhiman

      From: Adam Sroka <adam.sroka@...>
      To: "scrumdevelopment@yahoogroups.com" <scrumdevelopment@yahoogroups.com>
      Sent: Wednesday, October 16, 2013 8:07 PM
      Subject: Re: [scrumdevelopment] How to perform estimation for custom (billable) work

      The best way to do it is optional scope. Deliver something every sprint. When your customer is happy with what you have delivered they can quit. You should know what it costs to run the team for a sprint. Add your margin to that and you know what you have to charge (To mitigate risk maybe negotiate for a minimum number of sprints and/or add additional margin to cover downtime between projects.) 

      If you need to calculate how many sprints it will take to complete some quantity of work, and you haven't had time to establish a velocity yet, the most realistic way to accomplish that is to look at how long it took you to develop products in the past. Come up with a range based on past performance and assume that it will take similar effort this time. 

      That may seem like an oversimplification, but it has the advantage of being based on something you know. It blows my mind that people think a bunch of small guesses added together are somehow more efficacious than one big guess. At least with the big guess you still have your eye on the ball and aren't bogged down in minutiae. 

      On Thu, Oct 10, 2013 at 4:24 PM, <vilson_a@...> wrote:
      Hello everyone,
      I was wondering if you guys could help me out with this problem. Although I have worked in an Agile environment before, even as an Scrum Master, this is actually the first time I’m working in a company (currently implementing Agile) that does custom (billable) work.
      I am sure most of you have had the opportunity to deal with this situation, and I was wondering how you have worked it out.
      Estimation to price the “project” is currently done in hours, and of course it is a completely unrealistic number. Since I have been a Scrum master before, I am trying to help the Dev Manager figure this out.

      Just to clarify, for regular product roadmap items we do estimate in points (Fibonacci).
      Please let me know if any more detail is required.