56588Re: no more work left in a sprint

Expand Messages
  • czahn777
    Feb 12, 2013
      Thank you for your great response.
      Should it really occur, that all the work is done before the sprint ends, i think we would add another small story to the sprint.
      I'll inform you ;)

      Thanks, regards,
      Christof

      --- In scrumdevelopment@yahoogroups.com, Michael James wrote:
      >
      > Agree with that. Though I want to emphasize that every time I've heard "we're done early" it turned out the work wasn't really *done*.
      >
      > --mj
      > http://ScrumReferenceCard.com
      >
      > On Feb 11, 2013, at 10:54 AM, Markus Gaertner wrote:
      >
      > > I'd get together with my team and my product owner, and decide about the best option to go for. That could mean to pay down some technical debt, add some more unit tests, develop some more business facing test automation, or pull the next tiny story suitable for the two days into the sprint, but not to commit on it. That could also mean to do some pre-planning on the stories to come, add some acceptance criteria, or, or, or...
      > >
      > >
      > > And I would let the Scrum team decide on that.
      > >
      > > Best
      > > Markus
      > >
      > > On Mon, Feb 11, 2013 at 5:23 PM, Christof Zahn wrote:
      > >
      > >
      > > hi group,
      > > this is my first topic in that fabulous discussion group! I'm so excited! :)
      > >
      > > Here's my question:
      > > We're now almost at the end of a sprint. There are 4 day left. When we take a look at our burndown chart, the forecast says we will finish the sprint two days earlier than planned.
      > > There is no more work left in the sprint backlog.
      > >
      > > So, what would you do, if the work will finish earlier?
      > > a) Stop/Finish the sprint, make the review and start into the next sprint?
      > > b) Add some more work from the product backlog that fit into these 2 days?
      > > c) Let the developer do something totally different?
      > >
      > > I look forward to your reply
      > >
      > > regards,
      > > christof
      > >
      > >
      > >
      > >
      > >
      > > --
      > > Dipl.-Inform. Markus Gärtner
      > > Author of ATDD by Example - A Practical Guide to Acceptance Test-Driven Development
      > > http://www.shino.de/blog
      > > http://www.mgaertne.de
      > > http://www.it-agile.de
      > > Twitter: @mgaertne
      > >
      > >
      >