56280Re: [scrumdevelopment] How to increase velocity

Expand Messages
  • Laurent Bossavit
    Nov 28, 2012
    • 0 Attachment
      > Your boss wants your team to deliver certain functionality by a certain date (deadline),

      How far away is that deadline: six days? Six weeks? Six months? A year or more?

      How large is the discrepancy between the date predicted by current velocity and the desired deadline?

      > More people?

      Won't work if the deadline is near.

      > Overtime?

      Won't work, and will lose talent you can't afford to lose.

      > What else to increase the velocity?

      That's not the only option; you can also cut scope.