      +1 to Mark W's answer below.
       
      -------
      Charles Bradley
      http://www.ScrumCrazy.com




      From: woynam <woyna@...>
      To: scrumdevelopment@yahoogroups.com
      Sent: Tuesday, May 8, 2012 1:06 PM
      Subject: [scrumdevelopment] Re: Velocity Question


      No, that is not correct. The velocity for Sprint 1 will not include the unfinished stories. Thus, the full size of the stories will be part of the velocity calculation for Sprint 2. If you re-estimate the stories, the velocity will not reflect their original size.

      Again, this is the reason many recommend using a rolling average when calculating velocity. A 5 point story that's completed during the first day of the 2nd Sprint will contribute zero points towards the velocity of the first Sprint, and 5 points towards the velocity of the 2nd Sprint, even though there was only a small amount of work remaining.

      Mark


      --- In scrumdevelopment@yahoogroups.com, "gopinath" <gopinath_ram@...> wrote:
      >
      > I am in agreement with previous responses to this question.
      > However at the beginning of  Sprint 2 you should re-estimate the story points for the two partially finished stories carried over from Sprint 1.
      >
      > Gopinath
      >
      >
      > --- In scrumdevelopment@yahoogroups.com, Rama Bharti <ramabharti@> wrote:
      > >
      > > Hi,
      > >
      > > I have a question on velocity.
      > >
      > > For instance, you have sprint 1 and sprint 2.
      > >
      > > Sprint 1 has 5 stories which in total is 50 story points. Each story
      > > is of size 10 story point.
      > > Sprint 2 has 5 stories which in total is 50 story points. Each story
      > > is of size 10 story point.
      > >
      > > Now sprint 1 ends with 3 stories completed and 2 story partially
      > > completed( 80 %done). What will be velocity of Sprint 1? I assume it
      > > will be 30.
      > >
      > > Now pending 2 stories are moved to sprint 2. and at the end of sprint
      > > 2 , all seven stories are finished( 2 which were moved from Sprint1
      > > and 5 Sprint2 stories). So velocity of sprint 2 is  70.
      > >
      > > How do you explain this difference in velocity to management?
      > >
      > >
      > > Thanks.
      > >
      >




      ------------------------------------

      To Post a message, send it to:  scrumdevelopment@...
      To Unsubscribe, send a blank message to: scrumdevelopment-unsubscribe@...! Groups Links

      <*> To visit your group on the web, go to:
          http://groups.yahoo.com/group/scrumdevelopment/

      <*> Your email settings:
          Individual Email | Traditional

      <*> To change settings online go to:
          http://groups.yahoo.com/group/scrumdevelopment/join
          (Yahoo! ID required)

      <*> To change settings via email:
          scrumdevelopment-digest@yahoogroups.com
          scrumdevelopment-fullfeatured@yahoogroups.com

      <*> To unsubscribe from this group, send an email to:
          scrumdevelopment-unsubscribe@yahoogroups.com

      <*> Your use of Yahoo! Groups is subject to:
          http://docs.yahoo.com/info/terms/



    • Show all 29 messages in this topic