46522Re: [scrumdevelopment] Scrum master's effort tracking

Expand Messages
  • Ron Jeffries
    Apr 19, 2010
    • 0 Attachment
      Hello, poojawandile. On Monday, April 19, 2010, at 6:33:32 AM,
      you wrote:

      > I have a query on scrum master's effort tracking.
      > If a project has dedicated scrum master who is not doing any
      > development tasks, but only monitoring Scrum process, do we have
      > to consider his effort while calculating velocity? How and where his effort gets accounted?

      Velocity is the number of stories completed per unit time. It does
      not include any measure of "effort".

      Ron Jeffries