39457Re: [scrumdevelopment] Re: Extending a Sprint

Expand Messages
  • Michael James
    Jul 1, 2009
      On Jul 1, 2009, at 9:47 AM, George Dinwiddie wrote:
      > BTW, I've seen teams do certain stories at the beginning of the
      > sprint,
      > taking them to done-done to meet a mid-sprint release, and then
      > continuing with the rest of the stories in the sprint. It causes a
      > little extra work, but came out pretty well.

      This is how I recall handling this while on a Scrum dev team.
      Acceptance criteria included "Deployed/released on x date", where x is
      within the Sprint. I don't recall it causing any real problem. This
      would allow the Sprint duration to stay constant.

      --mj
      .