37020Re: [scrumdevelopment] Should we take into account unplanned stories?

Expand Messages
  • Uma Menon
    Mar 12, 2009
    • 0 Attachment
      I don't think so. You'll need a few sprints to realise whether it is a one off occurence orĀ  it is common for this team to be asked to firefight. Build that into capacity.

      On Wed, Mar 11, 2009 at 8:31 AM, tiagomjorge <tiagomjorge@...> wrote:

      If a team has to stop what they are doing to fix some critical bugs, or make some critical enhancement, should us ask the team to estimate those stories and take that into account in the sprint velocity?


    • Show all 7 messages in this topic