  • Andrew Burrows
    Oct 5, 2007
    • 0 Attachment

      Hi Fredrik,

       

      I’m pretty new to Scrum Development myself, but I find it best to stick to cycles that are the same duration rather than constrain them from Monday to Friday. 

       

      What this means to us is that while starting a ten-day sprint on a Thursday instead of a Monday, for example, isn’t as neat in the calendar, it allows the team to develop a rhythm for each sprint and also gives us a fairer sprint velocity calculation.

       

      This is only my take on the issue, however – I’d be keen to hear from other people on this subject also.

       

      Thanks.

       


      From: scrumdevelopment@yahoogroups.com [mailto:scrumdevelopment@yahoogroups.com] On Behalf Of freka423
      Sent: Friday, October 05, 2007 5:32 AM
      To: scrumdevelopment@yahoogroups.com
      Subject: [scrumdevelopment] Sprint cycles?

       

      Hi

      We have been discussing pros and cons of running a sprint from Monday
      to Friday (we use 2 week sprints so it is actually Monday to next
      Friday) compared to having another "cycle", say Wednesday to Tuesday.

      We have always used Mo - Fr, so I would very much like to hear
      opinions from people using another "cycle"

      Thanks,

      Fredrik