Re: [XP] iterations - NEWBIE question

Expand Messages
  • J. B. Rainsberger
    Robert G Palmer Jr wrote: Everything here is opinion. Start each sentence with I think or I recommend , if needed. ... Run iterations like clockwork. An
    Message 1 of 10 , Sep 2, 2003
    • 0 Attachment
      Robert G Palmer Jr wrote:

      Everything here is opinion. Start each sentence with "I think" or "I
      recommend", if needed.

      > After the iteration has been planned, if the stories are taking too
      > long, are you supposed to do the next iteration plan on the original
      > schedule, or wait till the stories are done?

      Run iterations like clockwork. An incomplete story counts for 0 towards
      velocity. When you estimate the next iteration, do not lower the
      estimates on the incomplete stories. Your customer may not like this,
      but assure her that if you finish this iteration ahead of schedule that
      you will ask her for more work. Tell her that at this early stage
      velocity fluctuates wildly and you are doing your best to minimize the
      variation.

      Remember the goal of measuring velocity: to tend towards predictable
      delivery.

      > We planned on a 2 week iteration, we finished 3 of our stories
      > completely, but 2 each have one more task to complete. Should we do
      > the next iteration plan and make those tasks part of a new story?

      Those tasks belong with the old story, see above.

      There is a clue in that last sentence. Your team has something to learn
      about the way it signs up for stories or tasks. Could you have finished
      one of those stories and left the other mostly incomplete? If so, what
      decisions would you have had to make differently to achieve that?

      > How do you adjust velocity - the story that has a task missing was
      > originally marked with 2points (weeks). Most of the task took about
      > 1.5 weeks the last task is taking almost a full week in itself. Do we
      > say the story is complete and give it 1.5 points? then create a new
      > story out of the remaining task?

      You do not divide stories; only the customer does. Do not change the
      estimates. Let the correction happen naturally.

      Take care.
      --
      J. B. Rainsberger,
      Diaspar Software Services
      http://www.diasparsoftware.com :: +1 416 791-8603
      Let's write software that people understand
    • Curtis Cooley
      ... This is very important, IMHO. We pin the story and task cards to a wall/board/cardboard box. The stories across the top in order from left to right based
      Message 2 of 10 , Sep 2, 2003
      • 0 Attachment
        Kiel Hodges wrote:
        > For example, a team I coached a couple of years ago abondoned
        > cards in favor of a whiteboard that listed stories and tasks.
        > When a pair finished the last task for a story, they were
        > expected to make sure that the story as a whole really was
        > complete and check it off.
        >
        > The board served as an Information Radiator that provided the
        > current status of the iteration. With the information readily
        > available and the team very aware of the importance of finishing
        > /stories/, we stayed on track rather well from that point forward.
        >
        This is very important, IMHO. We pin the story and task cards to a
        wall/board/cardboard box. The stories across the top in order from left
        to right based on priority with the tasks below the stories:

        Story1 Story2 Story3
        Task Task Task
        Task Task Task

        When a task is completed, it gets a green dot. When all tasks on a story
        are green, the story is green. Anyone walking into the room can
        instantly see our progress.

        So now, if it's the Tuesday of the second week of the iteration and
        Story2 and Story3 are not done, everyone can see it and the team can
        focus on getting Story2 done then getting as much of Story3 done as
        possible.
        --
        ======================
        Curtis R Cooley
        RADSoft
        Better software faster
        curtis@...
        ----------------------
        Do what comes naturally. Seethe and fume and throw a tantrum.
      • Arlo Belshee
        ... Hi all. I use a method very similar to Bill s, and find it to work quite well. The reason is that people tend to be consistent, over time. A team that
        Message 3 of 10 , Dec 20, 2003
        • 0 Attachment
          > From: "Steve Bate" <steve@...>
          >
          > It's not uncommon for our team to realize we've overlooked some engineering
          > aspect of a story when tasking it. During planning we mostly focus on a
          > high level business-oriented view of the story. During tasking we are
          > looking
          > at it more from a programming perspective. If we missed something when
          > doing the high level analysis we want to incorporate an estimate of that
          > extra work into a more accurate story estimate. The increased accuracy helps
          > us to "better predict the future", therefore the task estimates /not/
          > extraneous by your definition.

          Hi all.

          I use a method very similar to Bill's, and find it to work quite well.

          The reason is that people tend to be consistent, over time. A team that misses
          one design task on one task, tends to miss one on each story. A consistently
          optimistic team is common. A consistently pessimistic team is common. An
          inconsistent team (over a 1 mo. rolling average) is extremely rare.

          Thus, since you are only estimating task size, your inaccuracies make no
          difference in the final number. As long as you _never_ estimate tasks when
          making plans, and never assume that your estimates for story completion have
          any relation to the sum of the estimates for tasks, then everything works out.

          To clarify: we actually use two different units to estimate stories and tasks.
          We estimate tasks for the purpose of deciding what we're going to do this
          week, and in what orders. We estimate stories for the purpose of predicting
          the future. Thus, we actually have two _independent_ velocities - one used for
          release planning, the other for iteration.

          Since we are fairly consistent in what we miss while looking at the big
          stories (and in what we are afraid of and so overestimate), our velocity is
          fairly stable. Likewise, our task velocity is stable. While we can measure the
          difference, and determine a conversion factor between release units and
          iteration units, it's not really necessary: when release planning, sum the
          story estimates and use release velocity; when iteration planning, sum the
          task estimates and use iteration velocity.

          That way, we never have to estimate the individual tasks (which entails
          planning how that part of the system will work, at least a little), until the
          iteration that we do the feature. If we tried to use task estimates for
          release planning, then we would have to plan the system for the future, which
          would lock us in and break simplest thing.

          See ya'alls,
          Arlo
        • Steve Bate
          ... Wow. Apparently I ve only worked on rare teams during the last few decades. Every team I ve ever worked on overestimated required effort sometimes and
          Message 4 of 10 , Dec 20, 2003
          • 0 Attachment
            > From: Arlo Belshee [mailto:xppdx@...]
            > The reason is that people tend to be consistent, over time. A
            > team that misses one design task on one task, tends to miss one on
            > each story. A consistently optimistic team is common. A consistently
            > pessimistic team is common. An inconsistent team (over a 1 mo.
            > rolling average) is extremely rare.

            Wow. Apparently I've only worked on rare teams during the last few
            decades. Every team I've ever worked on overestimated required
            effort sometimes and underestimated it at other times. In "Characterizing
            People as Non-Linear, First-Order Components in Software Development"
            Alistair Cockburn describes inconsistency as a common human failure
            mode.

            The XP literature also states in several places that people tend to
            improve their estimation skills with practice. That matches my experience
            as well. Some people feel that this learning only happens with point
            estimates and not with ideal time. I don't know why there'd be a difference.
            I know I've seen people improve their estimation abilities on our team
            over the years while using ideal time estimates.

            >...
            > To clarify: we actually use two different units to estimate
            > stories and tasks.
            > We estimate tasks for the purpose of deciding what we're going to do this
            > week, and in what orders. We estimate stories for the purpose of
            > predicting the future. Thus, we actually have two _independent_
            velocities -
            > one used for release planning, the other for iteration.

            Interesting. Are both the units of effort called "points"? How do you
            translate between the two measurement units?

            >...
            > That way, we never have to estimate the individual tasks (which entails
            > planning how that part of the system will work, at least a
            > little), until the
            > iteration that we do the feature. If we tried to use task estimates for
            > release planning, then we would have to plan the system for the
            > future, which would lock us in and break simplest thing.

            This sounds similar to what we do. We only task stories to refine
            estimates for relatively short term activities (an iteration in our case).
            I agree that it's a good idea to do only very limited up front design
            (planning for the future) during release planning. As I've said before,
            we do short releases so that's not much of an issue for us anyway.
          • Ron Jeffries
            ... I m really trying to understand what you do, and I m just not getting it. Let me describe a project using points which happen, through luck or design, to
            Message 5 of 10 , Dec 20, 2003
            • 0 Attachment
              On Saturday, December 20, 2003, at 6:03:18 PM, Steve Bate wrote:

              > This sounds similar to what we do. We only task stories to refine
              > estimates for relatively short term activities (an iteration in our case).
              > I agree that it's a good idea to do only very limited up front design
              > (planning for the future) during release planning. As I've said before,
              > we do short releases so that's not much of an issue for us anyway.

              I'm really trying to understand what you do, and I'm just not getting it.

              Let me describe a project using points which happen, through luck or
              design, to be ideal days.

              We have 100 stories. Each has an estimate of 1 point. We have ten
              programmers. We assume that we can do ten stories an iteration, sign up for
              ten, and go.

              At the end of the first iteration, we have five stories done. Using YW, we
              conclude that we have 19 iterations to go, and that we should sign up for
              five stories in each iteration.

              Over the course of the release, the team's "inherent" velocity remains the
              same. We have about the same overhead in every iteration as in the first.
              Our estimation error is about the same on every story. So in every
              iteration, we get about five done, and after 20 iterations, we're done.

              That's a description of a simple points (or ideal day) project. Now I'm
              going to try to describe what you do with the same situation, not because I
              think I have it but so that you can correct me -- or just throw away what I
              write and do it over:

              Let's suppose that your stories are also estimated at one day each. So your
              customer shows up with ten. You task them, and some show 8 hours, some show
              ten, some show 6. It averages out, so you undertake the ten just like we
              did.

              At the end of the iteration, you have five done. The actuals for the tasks
              are recorded /and overhead, i.e. non-working time is not counted/. (The
              italicized bit is my understanding, correct me if I'm wrong.)

              One possibility is that your estimates are all exactly correct, and the
              team has 50 percent overhead. Another possibility is that your estimates
              are an average of half of what they should be and the team has zero
              overhead. The real case is somewhere in between, most likely. So let's
              suppose for the discussion that you have 25% overhead and the stories are
              50% low in estimate vs actual. You are getting 7.5 days of work out of your
              ten programmers, and since the estimates are 50%, you can get five days of
              stories done, which is what happened.

              Now what happens next time? Do you reestimate all stories at 1.5 days? I
              believe you said that you do not. So what do you do in the next iteration?
              The figures seem to say that you should sign up for 7.5 days of stories.

              If you do, you'll get 5 of them done, and they will take, on the average,
              1.5 days to do.

              What I'm not getting is how, without reestimating the stories, you ever
              come to the conclusion that (a) you should do five a week, and (b) that the
              project will take 20 weeks.

              Please try to take my situation and explain how it would work. I'm assuming
              a simple though impossible case: all the stories are alike; the team has
              constant "inherent" velocity throughout; it's going to take twenty weeks to
              get done / we can do five a week.

              Give that situation, and trying to estimate in actual, what does the team
              do?

              I'm so confused ...

              Ron Jeffries
              www.XProgramming.com
              Reason is and ought only to be the slave of the passions. -- David Hume
            • Steve Bate
              ... I didn t say we never reestimate stories, but that we seldom have to do estimation revision on all remaining stories. In this specific example (which is
              Message 6 of 10 , Dec 20, 2003
              • 0 Attachment
                > From: Ron Jeffries [mailto:ronjeffries@...]
                > Let's suppose that your stories are also estimated at one day
                > each. So your customer shows up with ten. You task them, and
                > some show 8 hours, some show ten, some show 6. It averages out,
                > so you undertake the ten just like we did.
                >
                > At the end of the iteration, you have five done. The actuals for the tasks
                > are recorded /and overhead, i.e. non-working time is not counted/. (The
                > italicized bit is my understanding, correct me if I'm wrong.)
                >
                > One possibility is that your estimates are all exactly correct, and the
                > team has 50 percent overhead. Another possibility is that your estimates
                > are an average of half of what they should be and the team has zero
                > overhead. The real case is somewhere in between, most likely. So let's
                > suppose for the discussion that you have 25% overhead and the stories are
                > 50% low in estimate vs actual. You are getting 7.5 days of work
                > out of your ten programmers, and since the estimates are 50%, you can '
                > get five days of stories done, which is what happened.
                >
                > Now what happens next time? Do you reestimate all stories at 1.5 days? I
                > believe you said that you do not. So what do you do in the next iteration?
                > The figures seem to say that you should sign up for 7.5 days of stories.

                I didn't say we never reestimate stories, but that we seldom have to do
                estimation revision on all remaining stories. In this specific example
                (which is quite different from our team's actual experiences) you defined
                all stories to be very alike. I assume that the intent is to force a
                sitation where an error in the estimate of one story implies an error in
                the estimate of all future stories. If so, then we'd be forced to
                reestimate all future stories to 1.5 days. Again, we've never had this
                happen IRL.

                > If you do, you'll get 5 of them done, and they will take, on the average,
                > 1.5 days to do.
                >
                > What I'm not getting is how, without reestimating the stories, you ever
                > come to the conclusion that (a) you should do five a week, and
                > (b) that the project will take 20 weeks.

                B follows from A and the 100 story count. A is determined by 1.5 day
                stories and a velocity of 7.5 days/iteration.

                > Please try to take my situation and explain how it would work.
                > I'm assuming a simple though impossible case: all the stories are alike;
                > the team has constant "inherent" velocity throughout; it's going to take
                > twenty weeks to get done / we can do five a week.
                >
                > Give that situation, and trying to estimate in actual, what does the team
                > do?

                Does the reestimation clear up the issue?

                > I'm so confused ...

                I'm not sure why it's so confusing. After rereading portions of the Planning
                Extreme Programming book it sounds like we're almost a perfect fit
                to the approaches described by Kent Beck and Martin Fowler. Our stories are
                usually smaller than the examples in the book, but the time-based estimating
                and task-level programmer estimates are described there. What do you think
                is
                different about the approach I've been describing (possibly not very well)?
              • Ron Jeffries
                ... Somehow we re not communicating. I haven t been able to formulate a question that elicits an answer that I can understand. Enough time spent. Thanks. Ron
                Message 7 of 10 , Dec 20, 2003
                • 0 Attachment
                  On Saturday, December 20, 2003, at 10:10:36 PM, Steve Bate wrote:

                  > I'm not sure why it's so confusing. After rereading portions of the Planning
                  > Extreme Programming book it sounds like we're almost a perfect fit
                  > to the approaches described by Kent Beck and Martin Fowler. Our stories are
                  > usually smaller than the examples in the book, but the time-based estimating
                  > and task-level programmer estimates are described there. What do you think
                  > is
                  > different about the approach I've been describing (possibly not very well)?

                  Somehow we're not communicating. I haven't been able to formulate a
                  question that elicits an answer that I can understand. Enough time spent.
                  Thanks.

                  Ron Jeffries
                  www.XProgramming.com
                  If not now, when? -- The Talmud