Re: [XP] Experiment on size of unit of work - how low can you go?

Expand Messages
  • Ron Jeffries
    Hi John ... Interesting experiment. My guess is, you almost always can, and you ll come to believe that when you cannot, it s about you, not about the problem.
    Message 1 of 10 , Jan 10, 2013
    • 0 Attachment
      Hi John

      On Jan 9, 2013, at 10:27 PM, John Carter <john.carter@...> wrote:

      > Can I break _everything_ I do down to "smaller than a work day" from plan,
      > to test, to work done and documented, to pushed done and dusted to
      > repository?
      >
      > By "done and dusted" I mean if I forgot, died, or went on to something
      > else... whatever I did could remain unchanged within the code base without
      > detriment, and preferable with benefit, to the customer.


      Interesting experiment. My guess is, you almost always can, and you'll come to believe that when you cannot, it's about you, not about the problem. Keep us posted please.

      Ron Jeffries
      www.XProgramming.com
      I know we always like to say it'll be easier to do it now than it
      will be to do it later. Not likely. I plan to be smarter later than
      I am now, so I think it'll be just as easy later, maybe even easier.
      Why pay now when we can pay later?



      [Non-text portions of this message have been removed]
    • Steven Gordon
      Hi John, I believe your idea would work well once there is some accepted, working software. However, I do not see how to get started from scratch. Would you
      Message 2 of 10 , Jan 10, 2013
      • 0 Attachment
        Hi John,

        I believe your idea would work well once there is some accepted, working
        software.

        However, I do not see how to get started from scratch. Would you start by
        making a series of changes that went from nothing working to nothing
        working until you magically got to something to deliver?

        On Wed, Jan 9, 2013 at 8:27 PM, John Carter <john.carter@...> wrote:

        > **
        >
        >
        > First, a thought experiment.
        >
        > Traditionally a "feature" was the unit of work to be planned, created,
        > integrated and tested.
        >
        > As we became more agile we broke these units of planning, creation and
        > test, and integration into smaller and smaller chunks...
        >
        > Question: How small can I go?
        >
        > What if I designed my efforts, from planning, to test, to creation, to
        > integration, to documentation, to pushed, done and dusted to _all_ be The
        > Smallest Change that will provably not break anything?
        >
        > How small can that go?
        >
        > So my experiment for the next month or so...
        >
        > Can I break _everything_ I do down to "smaller than a work day" from plan,
        > to test, to work done and documented, to pushed done and dusted to
        > repository?
        >
        > By "done and dusted" I mean if I forgot, died, or went on to something
        > else... whatever I did could remain unchanged within the code base without
        > detriment, and preferable with benefit, to the customer.
        >
        > --
        > John Carter Phone : (64)(3) 358 6639
        > Tait Electronics Fax : (64)(3) 359 4632
        > PO Box 1645 Christchurch Email : john.carter@...
        > New Zealand
        >
        >


        [Non-text portions of this message have been removed]
      • George Dinwiddie
        Steven, ... I ve done this, myself. It still takes awhile for the stories to add up to something releasable, but I ve been able to start from nothing and work
        Message 3 of 10 , Jan 10, 2013
        • 0 Attachment
          Steven,

          On 1/10/13 10:55 AM, Steven Gordon wrote:
          > Hi John,
          >
          > I believe your idea would work well once there is some accepted, working
          > software.
          >
          > However, I do not see how to get started from scratch. Would you start by
          > making a series of changes that went from nothing working to nothing
          > working until you magically got to something to deliver?

          I've done this, myself. It still takes awhile for the stories to add up
          to something releasable, but I've been able to start from nothing and
          work in tiny steps. It does take practice.

          - George

          >
          > On Wed, Jan 9, 2013 at 8:27 PM, John Carter <john.carter@...> wrote:
          >
          >> **
          >>
          >>
          >> First, a thought experiment.
          >>
          >> Traditionally a "feature" was the unit of work to be planned, created,
          >> integrated and tested.
          >>
          >> As we became more agile we broke these units of planning, creation and
          >> test, and integration into smaller and smaller chunks...
          >>
          >> Question: How small can I go?
          >>
          >> What if I designed my efforts, from planning, to test, to creation, to
          >> integration, to documentation, to pushed, done and dusted to _all_ be The
          >> Smallest Change that will provably not break anything?
          >>
          >> How small can that go?
          >>
          >> So my experiment for the next month or so...
          >>
          >> Can I break _everything_ I do down to "smaller than a work day" from plan,
          >> to test, to work done and documented, to pushed done and dusted to
          >> repository?
          >>
          >> By "done and dusted" I mean if I forgot, died, or went on to something
          >> else... whatever I did could remain unchanged within the code base without
          >> detriment, and preferable with benefit, to the customer.

          --
          ----------------------------------------------------------------------
          * George Dinwiddie * http://blog.gdinwiddie.com
          Software Development http://www.idiacomputing.com
          Consultant and Coach http://www.agilemaryland.org
          ----------------------------------------------------------------------
        • Charlie Poole
          As you go smaller and smaller, don t you reach the point where it s no longer a story? That is, no longer viewed as having value by the customer? I think we
          Message 4 of 10 , Jan 10, 2013
          • 0 Attachment
            As you go smaller and smaller, don't you reach the point where it's no
            longer a story? That is, no longer viewed as having value by the customer?

            I think we have to keep the distinction between units of work (tasks?) and
            stories clear in our minds. Clearly, we often have to do a lot of things
            that are not viewed as valuable by the customer in order to make some thing
            that is of value. The trick is to minimize how much effort we put into such
            things and move toward value as quickly as we can.

            One way I've found of going smaller is to work with the Customer to expand
            what is seen as having value. So, for example, the Customer may grow to see
            value in seeing that certain high-risk tasks are done successfully, because
            it increases the probability of project success, even if the results are
            not releasable. But we can't just go ahead and make that judgement
            ourselves - it's a key insight of XP that the Customer is the definer of
            value and I wouldn't want to forget that.

            Charlie


            On Thu, Jan 10, 2013 at 8:41 AM, George Dinwiddie
            <lists@...>wrote:

            > **
            >
            >
            > Steven,
            >
            > On 1/10/13 10:55 AM, Steven Gordon wrote:
            > > Hi John,
            > >
            > > I believe your idea would work well once there is some accepted, working
            > > software.
            > >
            > > However, I do not see how to get started from scratch. Would you start by
            > > making a series of changes that went from nothing working to nothing
            > > working until you magically got to something to deliver?
            >
            > I've done this, myself. It still takes awhile for the stories to add up
            > to something releasable, but I've been able to start from nothing and
            > work in tiny steps. It does take practice.
            >
            > - George
            >
            > >
            > > On Wed, Jan 9, 2013 at 8:27 PM, John Carter john.carter@...>
            > wrote:
            > >
            > >> **
            > >>
            > >>
            > >> First, a thought experiment.
            > >>
            > >> Traditionally a "feature" was the unit of work to be planned, created,
            > >> integrated and tested.
            > >>
            > >> As we became more agile we broke these units of planning, creation and
            > >> test, and integration into smaller and smaller chunks...
            > >>
            > >> Question: How small can I go?
            > >>
            > >> What if I designed my efforts, from planning, to test, to creation, to
            > >> integration, to documentation, to pushed, done and dusted to _all_ be
            > The
            > >> Smallest Change that will provably not break anything?
            > >>
            > >> How small can that go?
            > >>
            > >> So my experiment for the next month or so...
            > >>
            > >> Can I break _everything_ I do down to "smaller than a work day" from
            > plan,
            > >> to test, to work done and documented, to pushed done and dusted to
            > >> repository?
            > >>
            > >> By "done and dusted" I mean if I forgot, died, or went on to something
            > >> else... whatever I did could remain unchanged within the code base
            > without
            > >> detriment, and preferable with benefit, to the customer.
            >
            > --
            > ----------------------------------------------------------
            > * George Dinwiddie * http://blog.gdinwiddie.com
            > Software Development http://www.idiacomputing.com
            > Consultant and Coach http://www.agilemaryland.org
            > ----------------------------------------------------------
            >
            >
            >


            [Non-text portions of this message have been removed]
          • George Dinwiddie
            Charlie, ... Clearly, it depends. It depends on the people involved, and how they perceive value. It also depends on the amount of overhead you have in a
            Message 5 of 10 , Jan 10, 2013
            • 0 Attachment
              Charlie,

              On 1/10/13 11:49 AM, Charlie Poole wrote:
              > As you go smaller and smaller, don't you reach the point where it's no
              > longer a story? That is, no longer viewed as having value by the customer?

              Clearly, it depends. It depends on the people involved, and how they
              perceive value. It also depends on the amount of overhead you have in a
              story. If you're collocated, and just scribbling titles on index cards,
              the overhead can be very low. If you've got a lot of people, and you're
              estimating effort on stories, then the overhead is a lot higher.

              - George

              --
              ----------------------------------------------------------------------
              * George Dinwiddie * http://blog.gdinwiddie.com
              Software Development http://www.idiacomputing.com
              Consultant and Coach http://www.agilemaryland.org
              ----------------------------------------------------------------------
            • John Carter
              ... break, no dependencies, no legacy code... Fortunately or unfortunately, this late in the history of the industry, there is almost no green field coding
              Message 6 of 10 , Jan 10, 2013
              • 0 Attachment
                On Fri, Jan 11, 2013 at 4:55 AM, Steven Gordon <sgordonphd@...> wrote:

                > I believe your idea would work well once there is some accepted, working
                > software.
                >
                > However, I do not see how to get started from scratch.
                >
                > In a sense it is easiest to do in Green Fields programming. So little to
                break, no dependencies, no "legacy" code...

                Fortunately or unfortunately, this late in the history of the industry,
                there is almost no green field coding left...

                (So why is it that Green Field coding is almost the only sort that
                academics teach?
                Surely they must know there is not an entry level job on the planet doing
                that stuff?)


                --
                John Carter Phone : (64)(3) 358 6639
                Tait Electronics Fax : (64)(3) 359 4632
                PO Box 1645 Christchurch Email : john.carter@...
                New Zealand

                --

                ------------------------------
                This email, including any attachments, is only for the intended recipient.
                It is subject to copyright, is confidential and may be the subject of legal
                or other privilege, none of which is waived or lost by reason of this
                transmission.
                If you are not an intended recipient, you may not use, disseminate,
                distribute or reproduce such email, any attachments, or any part thereof.
                If you have received a message in error, please notify the sender
                immediately and erase all copies of the message and any attachments.
                Unfortunately, we cannot warrant that the email has not been altered or
                corrupted during transmission nor can we guarantee that any email or any
                attachments are free from computer viruses or other conditions which may
                damage or interfere with recipient data, hardware or software. The
                recipient relies upon its own procedures and assumes all risk of use and of
                opening any attachments.
                ------------------------------


                [Non-text portions of this message have been removed]
              • John Carter
                On Fri, Jan 11, 2013 at 5:49 AM, Charlie Poole ... It s one of the many blessings of distributed version control systems... you
                Message 7 of 10 , Jan 10, 2013
                • 0 Attachment
                  On Fri, Jan 11, 2013 at 5:49 AM, Charlie Poole <charliepoole@...>
                  wrote:

                  > As you go smaller and smaller, don't you reach the point where it's no
                  > longer a story? That is, no longer viewed as having value by the
                  > customer?
                  >snip<
                  >
                  > But we can't just go ahead and make that judgement
                  > ourselves - it's a key insight of XP that the Customer is the definer of
                  > value and I wouldn't want to forget that.


                  It's one of the many blessings of distributed version control systems...
                  you suddenly realize there is no real coupling between committing a
                  changeset and publishing your work to the rest of the team as "fit for
                  consumption".

                  So as soon as you realize that... you start committing all the time.

                  Every single time the write test / test fail / write code / test pass cycle
                  goes green.

                  Commit.

                  The point about version control systems is they make you brave about
                  changing things. (Because you always know _exactly_ what you changed, and
                  you can always revert it if it was A Bad Idea.)

                  Having got that insight... you suddenly start wondering what else you can
                  decouple.

                  Yup, as soon as I "push", I have declared my changes as "fit for
                  consumption by the rest of the team".

                  But I haven't declared it fit for consumption by my customer.

                  So what if I shift my "done done" point forward and decoupled that from
                  "showing it to the customer".

                  ie. The point where it is all Tested, documented, review(ed or
                  reviewable...preferably pair programmed, or if I can't do that... the diff
                  in a web base
                  collaboration tool http://www.reviewboard.org/), integrated, smoke tested,
                  pushed to central repository.

                  Sort of makes sense really... 90% of what I do to get anything to the "done
                  done" point is not really understandable by a customer. It's only when I
                  tie a whole bunch of stuff together with a vast bunch of existing stuff
                  that the customer goes "Oh cool, I needed that!".

                  I want the customer feedback ASAP... but I need (and can get) the feedback
                  from the build system, smoke test suite, other developers even faster.

                  If every changeset I push is so small "there is obviously nothing wrong
                  with it" I will be in a better state than if the answer is "there is
                  nothing obviously wrong with it".

                  The aim of the experiment is to find out whether it is feasible to decouple
                  "done done" from "get customer feedback", and what are the costs and
                  benefits.

                  I agree with you... anything that would decreasing the feedback from a
                  customer would be A Bad Thing.

                  How ever, sprint overruns happen sometimes... Priorities change. Shit
                  happens both internally and externally. Wouldn't I be in a better state if
                  I could point to a pile of "this stuff is done and dusted and I can go on
                  to other things if you really want and come back to it later, and this
                  other stuff isn't done at all." than sitting with a mouthful of teeth
                  mumbling... "Well, it's not done done yet".

                  The view of Scrum I'm starting to take is this.... "A Story is a Unit of
                  Bidding (amongst competing customer interests and values) for the Team's
                  attention."



                  --
                  John Carter Phone : (64)(3) 358 6639
                  Tait Electronics Fax : (64)(3) 359 4632
                  PO Box 1645 Christchurch Email : john.carter@...
                  New Zealand

                  --

                  ------------------------------
                  This email, including any attachments, is only for the intended recipient.
                  It is subject to copyright, is confidential and may be the subject of legal
                  or other privilege, none of which is waived or lost by reason of this
                  transmission.
                  If you are not an intended recipient, you may not use, disseminate,
                  distribute or reproduce such email, any attachments, or any part thereof.
                  If you have received a message in error, please notify the sender
                  immediately and erase all copies of the message and any attachments.
                  Unfortunately, we cannot warrant that the email has not been altered or
                  corrupted during transmission nor can we guarantee that any email or any
                  attachments are free from computer viruses or other conditions which may
                  damage or interfere with recipient data, hardware or software. The
                  recipient relies upon its own procedures and assumes all risk of use and of
                  opening any attachments.
                  ------------------------------


                  [Non-text portions of this message have been removed]
                • Steven Gordon
                  ... Easier to do, but less clear how your proposal applies. ... There are many new Android and IPhone apps put out every day. There might be more greenfield
                  Message 8 of 10 , Jan 10, 2013
                  • 0 Attachment
                    On Thu, Jan 10, 2013 at 2:02 PM, John Carter <john.carter@...> wrote:

                    > **
                    >
                    >
                    > On Fri, Jan 11, 2013 at 4:55 AM, Steven Gordon sgordonphd@...>
                    > wrote:
                    >
                    > > I believe your idea would work well once there is some accepted, working
                    > > software.
                    > >
                    > > However, I do not see how to get started from scratch.
                    > >
                    > > In a sense it is easiest to do in Green Fields programming. So little to
                    > break, no dependencies, no "legacy" code...
                    >

                    Easier to do, but less clear how your proposal applies.


                    >
                    > Fortunately or unfortunately, this late in the history of the industry,
                    > there is almost no green field coding left...
                    >

                    There are many new Android and IPhone apps put out every day. There might
                    be more greenfield projects today than ever before, but most of them are
                    tiny.


                    >
                    > (So why is it that Green Field coding is almost the only sort that
                    > academics teach?
                    > Surely they must know there is not an entry level job on the planet doing
                    > that stuff?)
                    >

                    You won't get me to defend what academia teaches. I left academia for what
                    it teaches, as well as how research and the university mission has
                    evolved.


                    >
                    > --
                    > John Carter Phone : (64)(3) 358 6639
                    > Tait Electronics Fax : (64)(3) 359 4632
                    > PO Box 1645 Christchurch Email : john.carter@...
                    > New Zealand
                    >
                    > --
                    >
                    > ------------------------------
                    > This email, including any attachments, is only for the intended recipient.
                    > It is subject to copyright, is confidential and may be the subject of
                    > legal
                    > or other privilege, none of which is waived or lost by reason of this
                    > transmission.
                    > If you are not an intended recipient, you may not use, disseminate,
                    > distribute or reproduce such email, any attachments, or any part thereof.
                    > If you have received a message in error, please notify the sender
                    > immediately and erase all copies of the message and any attachments.
                    > Unfortunately, we cannot warrant that the email has not been altered or
                    > corrupted during transmission nor can we guarantee that any email or any
                    > attachments are free from computer viruses or other conditions which may
                    > damage or interfere with recipient data, hardware or software. The
                    > recipient relies upon its own procedures and assumes all risk of use and
                    > of
                    > opening any attachments.
                    > ------------------------------
                    >
                    > [Non-text portions of this message have been removed]
                    >
                    >
                    >


                    [Non-text portions of this message have been removed]
                  • Charlie Poole
                    ... might imagine. Even centralized VCSs used to let you do that - although with much more work - by use of what some call promotion. ... Yes, I definitely
                    Message 9 of 10 , Jan 10, 2013
                    • 0 Attachment
                      On Thu, Jan 10, 2013 at 1:29 PM, John Carter <john.carter@...> wrote:

                      > **
                      >
                      >
                      > On Fri, Jan 11, 2013 at 5:49 AM, Charlie Poole charliepoole@...>
                      > wrote:
                      >
                      > > As you go smaller and smaller, don't you reach the point where it's no
                      > > longer a story? That is, no longer viewed as having value by the
                      > > customer?
                      > >snip<
                      > >
                      > > But we can't just go ahead and make that judgement
                      > > ourselves - it's a key insight of XP that the Customer is the definer of
                      > > value and I wouldn't want to forget that.
                      >
                      > It's one of the many blessings of distributed version control systems...
                      > you suddenly realize there is no real coupling between committing a
                      > changeset and publishing your work to the rest of the team as "fit for
                      > consumption".
                      >
                      > Indeed, although that notion isn't as strongly coupled to DVCSs as one
                      might imagine. Even centralized VCSs used to let you do that - although
                      with much more work - by use of what some call "promotion."

                      > So as soon as you realize that... you start committing all the time.
                      >
                      > Every single time the write test / test fail / write code / test pass cycle
                      > goes green.
                      >
                      > Commit.
                      >
                      Yes, I definitely do that locally. Makes it much easier to go back than
                      pushing ctrl-Z 500 times.

                      >
                      > The point about version control systems is they make you brave about
                      > changing things. (Because you always know _exactly_ what you changed, and
                      > you can always revert it if it was A Bad Idea.)
                      >
                      > Before distributed version control, I used to advocate just deleting your
                      changes.
                      Braveness in deleting code is an important value for agile programmers.
                      Version control gives you a better way to keep track of how far back you
                      need to erase.

                      > Having got that insight... you suddenly start wondering what else you can
                      > decouple.
                      >
                      > Yup, as soon as I "push", I have declared my changes as "fit for
                      > consumption by the rest of the team".
                      >
                      > Pre-XP, I worked on a project where the first level of commit meant the
                      code was good for me, the next level meant it was good for the team and
                      the third that it could be used by testing. When we introduced XP, the
                      third level became "for the customer." I've never heard anyone else
                      enunciate this distinction before! (BTW, we did this using Visual
                      SourceSafe,
                      probably the worst VCS ever written!)

                      > But I haven't declared it fit for consumption by my customer.
                      >
                      > So what if I shift my "done done" point forward and decoupled that from
                      > "showing it to the customer".
                      >
                      > ie. The point where it is all Tested, documented, review(ed or
                      > reviewable...preferably pair programmed, or if I can't do that... the diff
                      > in a web base
                      > collaboration tool http://www.reviewboard.org/), integrated, smoke tested,
                      > pushed to central repository.
                      >
                      > Sort of makes sense really... 90% of what I do to get anything to the "done
                      > done" point is not really understandable by a customer. It's only when I
                      > tie a whole bunch of stuff together with a vast bunch of existing stuff
                      > that the customer goes "Oh cool, I needed that!".
                      >
                      > I want the customer feedback ASAP... but I need (and can get) the feedback
                      > from the build system, smoke test suite, other developers even faster.
                      >
                      > If every changeset I push is so small "there is obviously nothing wrong
                      > with it" I will be in a better state than if the answer is "there is
                      > nothing obviously wrong with it".
                      >
                      > The aim of the experiment is to find out whether it is feasible to decouple
                      > "done done" from "get customer feedback", and what are the costs and
                      > benefits.
                      >
                      > I agree with you... anything that would decreasing the feedback from a
                      > customer would be A Bad Thing.
                      >
                      > Yes, that could be a potential cost of this approach. But not necessarily,
                      I think.

                      > How ever, sprint overruns happen sometimes... Priorities change. Shit
                      > happens both internally and externally. Wouldn't I be in a better state if
                      > I could point to a pile of "this stuff is done and dusted and I can go on
                      > to other things if you really want and come back to it later, and this
                      > other stuff isn't done at all." than sitting with a mouthful of teeth
                      > mumbling... "Well, it's not done done yet".
                      >
                      > The view of Scrum I'm starting to take is this.... "A Story is a Unit of
                      > Bidding (amongst competing customer interests and values) for the Team's
                      > attention."
                      >
                      > I don't want to over-generalize, but in my own experience, Scrum teams
                      (that I've worked on) were a bit more removed from the customer than
                      XP teams. It wasn't as easy to push the notion of customer value lower,
                      by spltting stories, so more attention was paid to (what we used to call)
                      tasks. Others may have had different experience, of course.

                      There is a further level beyond "ready for the customer" and that's
                      "ready for release." Just because the customer has learned to see value
                      in some piece of work that's accomplished does not necessarily mean
                      that the work can be released yet - some minimum level of incremental
                      value may be needed first or some other stories may need to be completed
                      before we reach a "minimal releasable feature."

                      Charlie

                      Charlie

                      > --
                      > John Carter Phone : (64)(3) 358 6639
                      > Tait Electronics Fax : (64)(3) 359 4632
                      > PO Box 1645 Christchurch Email : john.carter@...
                      > New Zealand
                      >
                      > --
                      >
                      > ------------------------------
                      > This email, including any attachments, is only for the intended recipient.
                      > It is subject to copyright, is confidential and may be the subject of
                      > legal
                      > or other privilege, none of which is waived or lost by reason of this
                      > transmission.
                      > If you are not an intended recipient, you may not use, disseminate,
                      > distribute or reproduce such email, any attachments, or any part thereof.
                      > If you have received a message in error, please notify the sender
                      > immediately and erase all copies of the message and any attachments.
                      > Unfortunately, we cannot warrant that the email has not been altered or
                      > corrupted during transmission nor can we guarantee that any email or any
                      > attachments are free from computer viruses or other conditions which may
                      > damage or interfere with recipient data, hardware or software. The
                      > recipient relies upon its own procedures and assumes all risk of use and
                      > of
                      > opening any attachments.
                      > ------------------------------
                      >
                      > [Non-text portions of this message have been removed]
                      >
                      >
                      >


                      [Non-text portions of this message have been removed]
                    Your message has been successfully submitted and would be delivered to recipients shortly.