RE: [XP] Customer requests irregular iteration lengths

Expand Messages
  • Morris, Chris
    ... From the page: [She wanted this bunch of things, however long it would take, and then these other things, however long they would take. This would have
    Message 1 of 3 , Nov 1, 2000
      > This was something that came up in a planning session yesterday. More
      > info at
      > http://www.xpdeveloper.com/cgi-bin/wiki.cgi?IrregularIterations
      >
      > I'd like to get your opinions about this (and on that page, please).

      From the page:
      [She wanted this bunch of things, however long it would take, and then these
      other things, however long they would take. This would have resulted in two
      differing, long iterations.]

      I'd say try to sell her on what you technical people need to do to increase
      feedback (regular iterations) without trying to convince her that her
      schedule must be your schedule. Treat her schedule as project milestones,
      under which regular iterations occur. My $0.02.

      Chris
    • Phlip
      From: Keith Braithwaite ... Sounds like a job for http://c2.com/cgi/wiki?XpFixedPlanningGame Phlip ======= http://users.deltanet.com/~tegan/home.html =======
      Message 2 of 3 , Nov 1, 2000
        From: "Keith Braithwaite"

        > This was something that came up in a planning session yesterday. More
        > info at
        > http://www.xpdeveloper.com/cgi-bin/wiki.cgi?IrregularIterations
        >
        > I'd like to get your opinions about this (and on that page, please).

        Sounds like a job for

        http://c2.com/cgi/wiki?XpFixedPlanningGame

        Phlip
        ======= http://users.deltanet.com/~tegan/home.html =======
      • Curtis Cooley
        ... That s what I was thinking. During the long iteration, just do internal iterations on your regular schedule. ... Curtis Cooley RADSoft / Training,
        Message 3 of 3 , Nov 1, 2000
          --- "Morris, Chris" <ChrisM@...> wrote:
          > > This was something that came up in a planning session yesterday. More
          > > info at
          > > http://www.xpdeveloper.com/cgi-bin/wiki.cgi?IrregularIterations
          > >
          > > I'd like to get your opinions about this (and on that page, please).
          >
          > From the page:
          > [She wanted this bunch of things, however long it would take, and then these
          > other things, however long they would take. This would have resulted in two
          > differing, long iterations.]
          >
          > I'd say try to sell her on what you technical people need to do to increase
          > feedback (regular iterations) without trying to convince her that her
          > schedule must be your schedule. Treat her schedule as project milestones,
          > under which regular iterations occur. My $0.02.
          >
          That's what I was thinking. During the 'long' iteration, just do internal
          iterations on your regular schedule.

          =====
          ---------------------------------------------------------
          Curtis Cooley RADSoft / Training, Mentoring and Consulting in:
          curtis@... - Java, UML Modeling and OOD Principles
          http://www.RADSoft.com - User Centered E-Commerce Development
          - Rapid Software Delivery process
          - Catalysis Certified Instructors/Practitioners

          __________________________________________________
          Do You Yahoo!?
          From homework help to love advice, Yahoo! Experts has your answer.
          http://experts.yahoo.com/
        Your message has been successfully submitted and would be delivered to recipients shortly.