Re: [XP] what to hang on the wall

Expand Messages
  • Ron Jeffries
    ... Many teams that I observe have three areas on the wall for the iteration: Not yet started; In process; Done. They move the cards from one place to the
    Message 1 of 8 , Apr 2, 2007
      Hello, David. On Sunday, April 1, 2007, at 11:21:43 PM, you wrote:

      > We are now at a stage where we have gone through the whole system and
      > specified user stories. We have planned the first iteration.

      > Now how do we display the "first iteration" with the index cards ?

      > Once the development starts the developers should take the index cards that
      > they are working on from the wall right? Then they are missing from the
      > plan.

      Many teams that I observe have three "areas" on the wall for the
      iteration:
      Not yet started;
      In process;
      Done.

      They move the cards from one place to the next as appropriate.

      If there is so much written on a story card that the dev wants to
      carry it around, then there may be too much on it. I'd think about
      that, and meanwhile make a placeholder card with the name of the
      story and use it as above.

      > It should be possible to walk into our project room and get a feeling of the
      > whole project fairly quickly. What other things should we hang on the wall ?

      That's up to you. This article may give some ideas, and the way to
      go is to post what you, the team, currently want to communicate.
      (And if there is anything you DON'T want to communicate, you should
      probably post that too. ;-> )

      Ron Jeffries
      www.XProgramming.com
      You are to act in the light of experience as guided by intelligence.
      -- Nero Wolfe
    • Ron Jeffries
      ... Many teams that I observe have three areas on the wall for the iteration: Not yet started; In process; Done. They move the cards from one place to the
      Message 2 of 8 , Apr 2, 2007
        Hello, David. On Sunday, April 1, 2007, at 11:21:43 PM, you wrote:

        > We are now at a stage where we have gone through the whole system and
        > specified user stories. We have planned the first iteration.

        > Now how do we display the "first iteration" with the index cards ?

        > Once the development starts the developers should take the index cards that
        > they are working on from the wall right? Then they are missing from the
        > plan.

        Many teams that I observe have three "areas" on the wall for the
        iteration:
        Not yet started;
        In process;
        Done.

        They move the cards from one place to the next as appropriate.

        If there is so much written on a story card that the dev wants to
        carry it around, then there may be too much on it. I'd think about
        that, and meanwhile make a placeholder card with the name of the
        story and use it as above.

        > It should be possible to walk into our project room and get a feeling of the
        > whole project fairly quickly. What other things should we hang on the wall ?

        That's up to you. This article may give some ideas, and the way to
        go is to post what you, the team, currently want to communicate.
        (And if there is anything you DON'T want to communicate, you should
        probably post that too. ;-> )

        Oops, forgot the link:
        http://www.xprogramming.com/xpmag/BigVisibleCharts.htm

        Ron Jeffries
        www.XProgramming.com
        You are to act in the light of experience as guided by intelligence.
        -- Nero Wolfe
      • J. B. Rainsberger
        ... I like a big board with columns for * Not started * We have some customer tests/Ready to start * Started * Pending customer acceptance * Shipped and a
        Message 3 of 8 , Apr 2, 2007
          David Winslow wrote:
          >
          >
          > We are now at a stage where we have gone through the whole system and
          > specified user stories. We have planned the first iteration.
          >
          > Now how do we display the "first iteration" with the index cards ?

          I like a big board with columns for

          * Not started
          * We have some customer tests/Ready to start
          * Started
          * Pending customer acceptance
          * Shipped

          and a special column for

          * Stuck (waiting for someone/something outside the team)

          The cards start on the left and move to the right as we make progress.
          You can either pin cards to a bulletin board or affix Post-It brand
          index cards to the wall.

          > Once the development starts the developers should take the index cards that
          > they are working on from the wall right? Then they are missing from the
          > plan.

          They don't have to take the card. I've tried both and not noticed a
          difference between taking the card and making a local copy for myself.

          > It should be possible to walk into our project room and get a feeling of the
          > whole project fairly quickly. What other things should we hang on the wall ?

          Any other things you're measuring, like time lost to crappy version
          control system or time between question and answer or customer tests
          passing so far. Another would be your coding standards--Google "java
          coding standard on one page" for an example.

          That should give you enough to get started. The team will pull the rest
          of you as it notices things are missing.

          Of course, don't forget fun things, like Dilbert cartoons or whatever
          the local humor is.

          Take care.
          --
          J. B. (Joe) Rainsberger :: http://www.jbrains.ca
          Your guide to software craftsmanship
          JUnit Recipes: Practical Methods for Programmer Testing
          2005 Gordon Pask Award for contribution Agile Software Practice
        • Bob Koss
          In addition to the columns that Ron and JB mentioned, I like to have columns for the stories in the next few iterations. The content of these can change at the
          Message 4 of 8 , Apr 2, 2007
            In addition to the columns that Ron and JB mentioned, I like to have
            columns for the stories in the next few iterations. The content of
            these can change at the customer's discretion, but it shows that the
            team knows where they are going.


            ---
            Robert S. Koss, Ph. D.
            Senior Consultant
            www.objectmentor.com
          • Desilets, Alain
            In addition to User Story cards, I would put up a couple of posters that provide the big picture for the system. Things like: - 3-5 bottom line goals of the
            Message 5 of 8 , Apr 2, 2007
              In addition to User Story cards, I would put up a couple of posters that
              provide the "big picture" for the system. Things like:

              - 3-5 bottom line goals of the gold owner (why is he paying us to build
              this thing in the first place)
              - 3-5 bottom line goals of the end user (why the hell would he want to
              use this thing anyway?)

              These things provide context for the story cards. If you read a story
              card and you can't see how it relates fairly directly to one of those
              big picture things, then you probably don't understand the story, or
              maybe the story is wrong altogether. Either way, that's a sure sign to
              go talk to the person who wrote the story.

              Alain

              > -----Original Message-----
              > From: extremeprogramming@yahoogroups.com
              > [mailto:extremeprogramming@yahoogroups.com] On Behalf Of David Winslow
              > Sent: April 2, 2007 2:22 AM
              > To: extremeprogramming@yahoogroups.com
              > Subject: [XP] what to hang on the wall
              >
              > We are now at a stage where we have gone through the whole
              > system and specified user stories. We have planned the first
              > iteration.
              >
              > Now how do we display the "first iteration" with the index cards ?
              >
              > Once the development starts the developers should take the
              > index cards that they are working on from the wall right?
              > Then they are missing from the plan.
              >
              > It should be possible to walk into our project room and get a
              > feeling of the whole project fairly quickly. What other
              > things should we hang on the wall ?
              >
              >
              >
              > David
              >
              >
              >
              >
              >
              > [Non-text portions of this message have been removed]
              >
              >
              >
              > To Post a message, send it to: extremeprogramming@...
              >
              > To Unsubscribe, send a blank message to:
              > extremeprogramming-unsubscribe@...
              >
              > ad-free courtesy of objectmentor.com
              > Yahoo! Groups Links
              >
              >
              >
              >
            • Charlie Poole
              Hi David, ... Others have beat me to the punch on specifics, so I ll focus on a question you didn t ask: Who is the wall for? IMO, a visible display works best
              Message 6 of 8 , Apr 2, 2007
                Hi David,

                > We are now at a stage where we have gone through the whole
                > system and specified user stories. We have planned the first
                > iteration.
                >
                > Now how do we display the "first iteration" with the index cards ?
                >
                > Once the development starts the developers should take the
                > index cards that they are working on from the wall right?
                > Then they are missing from the plan.
                >
                > It should be possible to walk into our project room and get a
                > feeling of the whole project fairly quickly. What other
                > things should we hang on the wall ?

                Others have beat me to the punch on specifics, so I'll focus on
                a question you didn't ask: Who is the wall for?

                IMO, a visible display works best if all or almost all of the items
                on it are things the team believes it needs to see. There can be
                other places to hang up things that management wants to see or wants
                the team to see, but the wall in the team space should belong to
                the team.

                If the team controls the display, then it doesn't matter
                what's on it initially - it will eventually have what it needs. One
                way to facilitate this is to make sure what you do is not too fancy,
                things like carefully etched boundary lines tend to hold people back
                from making changes.

                On my team walls, I've had some or all of the following at different
                times...

                * Story card display
                * Theme of the iteration
                * Burndown chart
                * Acceptance test results
                * Unit test coverage
                * Red card area
                * Cartoons
                * Scratch area for graffiti

                Charlie