Re: [engineeringcivil] can you help me?

Expand Messages
  • jorge alberto uriarte perez
    The information you provide is too little. One option could be a prestreseed hollow box girder, or a steel box girder, but the class of structure or your
    Message 1 of 8 , Jul 7, 2009
    • 0 Attachment
      The information you provide is too little. One option could be a prestreseed hollow box girder, or a steel box girder, but the class of structure or your architectural limits can let you use those solutions or maybe not.


      From: AMBREEN OWAIS <amb1_2002@...>
      To: engineeringcivil@yahoogroups.com
      Sent: Monday, July 6, 2009 1:18:36 AM
      Subject: Re: [engineeringcivil] can you help me?

      thanks Boopathyraja
       
      Regards
      Ambreen Owais



      From: S. Boopathyraja <sboopa@...>
      To: "engineeringcivil@yahoogroups.com" <engineeringcivil@yahoogroups.com>
      Cc: AMBREEN OWAIS <amb1_2002@...>
      Sent: Thursday, June 4, 2009 8:56:22 PM
      Subject: RE: [engineeringcivil] can you help me?

      Dear Amreen,

       

                  Try your problems in any 3-D Analysis and Design software u can get clear picture of that. Generally we consider the secondary beam load as a point load in Primary Beam.

      Give ur problems in pictorial format that makes give clear idea to all…

      Boopathyraja. S | Senior Design Engineer | EDRC-Buildings & Factories

      Larsen & Toubro Limited-Ecc Divison |Chennai-600 089 |
      )| +91 98945 83549 | ( |044-2252 8134 |* sboopa@lntecc. com

      untitled

       



       

       

      From: engineeringcivil@ yahoogroups. com [mailto:engineering civil@yahoogroup s.com] On Behalf Of AMBREEN OWAIS
      Sent: Wednesday, June 03, 2009 3:41 PM
      To: muhammad talha; talha; Talha Junaid; civilengr@yahoogrou ps.com; engineeringcivil@ yahoogroups. com
      Subject: [engineeringcivil] can you help me?

       




      hi

      I have some problems if you can answer them?

      I have to design 110 ft long simply supported beam on which 5 point loads of 50kips are coming (point loads are basically support reactions of beams supported by this 110 ft simple span beam).UDL on the beam is of 3.19k/ft.I adopted an option of prestressed concrete design,but the problem is

      PROBLEM : The required section modulus is 84579 cubic inch,which is very large value.Moment due self weight is coming as 886k-ft while moment due point loads and UDL is 9777 k-ft.

      FURTHER COMMENTS:

      1.It is commented about the above case that we cannot assume that one beam will support other beams in the form of point loads, actually both the beams are supporting each other. Is it correct that we cannot assume or it is not happened in this way.

      2.Is it mandatory to go for 3D solution instead of 2D,means a combined behaviour with columns must be observed? 


       

      Regards
      Ambreen Owais

       



      "This Message and its contents is intended solely for the addressee and is proprietary. Information in this mail is for L&T Business Usage only. Any Use to other than the addressee is misuse and infringement to Proprietorship of L&T ECC.If you are not the addressee please return the mail to the sender.L&T ECC DIVISION"


    • Michelle Nuique
      yes it is true that 3d is the best solution for that kind of problem
      Message 2 of 8 , Jul 7, 2009
      • 0 Attachment
        yes it is true that 3d is the best solution for that kind of problem

      • civengbridge
        I will tell you something, I have designed bridges, one single span, 100 ft. long, supporting two t3s2r4 truck load, and the resulting prestressed beams were
        Message 3 of 8 , Jul 10, 2009
        • 0 Attachment
          I will tell you something, I have designed bridges, one single span, 100 ft. long, supporting two t3s2r4 truck load, and the resulting prestressed beams were aashto type IV modified, so more or less you need a 1.85 to 2.00 m. height prestressed girder, but AS I Told you, you must prove a prestressed concrete box girder or a steel box beam, it has a lot more torsional resuistance that other girders and i Hoope it would be a fair solution, that is if the architect do not denied it. Jorge, structural engineer., from mexico(Born culiacan, sinaloa ).
        • AMBREEN OWAIS
          thanks a lot Jorge,I am working over it...I tried  AASHTO Type IV but the issue is of section modulus.The procedure I am following is demanding to first
          Message 4 of 8 , Jul 12, 2009
          • 0 Attachment
            thanks a lot Jorge,I am working over it...I tried  AASHTO Type IV but the issue is of section modulus.The procedure I am following is demanding to first calculate "structural" section modulus.Structural section modulus means that the value is a function of "effectiveness ratio R",dead and live loads moments,allowable tensile stress immediately after transfer of prestress force and allowable compressive stress at service load after all loses.
            Any way thanks a lot for giving confident thoughts.
             
            Regards
            Ambreen Owais



            From: civengbridge <civengbridge@...>
            To: engineeringcivil@yahoogroups.com
            Sent: Friday, July 10, 2009 10:00:17 PM
            Subject: [engineeringcivil] Re: can you help me?

            I will tell you something, I have designed bridges, one single span, 100 ft. long, supporting two t3s2r4 truck load, and the resulting prestressed beams were aashto type IV modified, so more or less you need a 1.85 to 2.00 m. height prestressed girder, but AS I Told you, you must prove a prestressed concrete box girder or a steel box beam, it has a lot more torsional resuistance that other girders and i Hoope it would be a fair solution, that is if the architect do not denied it. Jorge, structural engineer., from mexico(Born culiacan, sinaloa ).


          • civengbridge
            Dear ambrim, I told you about aashto type IV modified, and the modification is that this has an more robust top flange, but the level of your loads is
            Message 5 of 8 , Jul 13, 2009
            • 0 Attachment
              Dear ambrim, I told you about aashto type IV modified, and the modification is that this has an more robust top flange, but the level of your loads is mandatory and the loads you wrote are really heavy. I want to tell you again, your solution is a medium box girder, prestressed concrete made or made with steel plates. Another solution could be a double tee prestressed concrete element. All in all another mandatory issue is your galibo or free vertical distance between floor level and bottom girder flange level, or installations (electrical, sanitaey,...). You have to make the choice. best and king regards, Jorge Alberto Uriarte Perez, c.e., s.e., dam structural elements designer, bridges, intakes, hydropower structures, hydropower electric generation structural elements designer, Crane Girder, Crane Bridge, etc.