    If colum ends @ slab level use M25 If column continue to further floor use M45 @ junction M A Jikare
    Message 1 of 3 , Feb 19, 2013
    • 0 Attachment
      If colum ends @ slab level use M25 If column continue to further floor use M45 @ junction



      M A Jikare
    • salim rawther
      Dear engineers,normally when the grades of concrete are different for columns and beams,what we do is use the higher grade concrete for filling the column
      Message 2 of 3 , Feb 21, 2013
      • 0 Attachment
        Dear engineers,
        normally when the grades of concrete are different for columns and beams,what we do is use the higher grade concrete for filling the column portion and allow this concrete to fill  the beam portion with 45 degree dispersion.And after filling the columns place the concrete on the beam portion.
        Regards
        salim