12373RE: bill of quantity submitted by contractor for construction of road

Expand Messages
  • srikanthnaragund@ymail.com
    Sep 22, 2013

      Please refer book Indian Road Congress, ( Morth )  Specification and Manual Construction and supervision of Bituminous works.



      --- In engineeringcivil@yahoogroups.com, <engineeringcivil@yahoogroups.com> wrote:

      Respected sir/ engineer,


      i like to ask some question plz answer if u can..

      1} contractor submitted BOQ ,for bituminous road construction,I WANTED

      TO FIND FAULT WHICH HE MUST HAVE DONE TO INCREASE THE AMOUNT OF BILL ,

      BY SHOWING ACTIVITY ,OR QUANTITY ,WHICH WE CAN TRACE

      SO I WANTED TO KNOW WHICH ARE THE ACTIVITY OR THINGS WE HAVE TO SE TO

      CATCH THE CONTRACTOR FAULT...AND PROVE IT....


      THANKS FOR ALL ENGINEER FRIENDS .....PLZ ANSWER ITS URGENT
    • Show all 7 messages in this topic