      You should change view just to find fault so that you could reduce contractors bills,
      It will be better if you can frame good specifications, and supervise same so that quality doesn't hamper.
      Think and act positively
      Satish Tumne

      Sent from my iPad

      On Jul 29, 2013, at 12:02 PM, "boyka" <k3gnigth@...> wrote:

      > Respected sir/ engineer,
      >
      >
      > i like to ask some question plz answer if u can..
      >
      > 1} contractor submitted BOQ ,for bituminous road construction,I WANTED
      >
      > TO FIND FAULT WHICH HE MUST HAVE DONE TO INCREASE THE AMOUNT OF BILL ,
      >
      > BY SHOWING ACTIVITY ,OR QUANTITY ,WHICH WE CAN TRACE
      >
      > SO I WANTED TO KNOW WHICH ARE THE ACTIVITY OR THINGS WE HAVE TO SE TO
      >
      > CATCH THE CONTRACTOR FAULT...AND PROVE IT....
      >
      >
      > THANKS FOR ALL ENGINEER FRIENDS .....PLZ ANSWER ITS URGENT
      >
      >
      >
      > ------------------------------------
      >