Re: [CMMi Process Improvement] CMMi specific RSKM?

Expand Messages
  • Aravind Raman
    Hi Monica, Preparing a Risk Management Plan consists of following activities: Assumptions: 1. You have a database/repository of risks mainatained & updated
    Message 1 of 3 , Feb 2, 2003
    View Source
    • 0 Attachment

      Hi Monica,

      Preparing a Risk Management Plan consists of following activities:

      Assumptions:

      1. You have a database/repository of risks mainatained & updated regularly.(Categorization in the repository is advisable)

      2. Your Level 2 KPAs are followed in letter & spirit.

      Process Steps (Minimal to be defined):

      1. Look for a similar project & identify risks.

      2. Look in the risk repository for likely risks relevant to the project as well as the   mitigation plan & what worked & what did'nt.

      3. Plan for the risks and group the risks.

      4. Categorize the risks on the basis of say people, technology, environement, etc.

      HTH,

      Aravind Raman

      +91-80-207 35 27

       

       

       

       

       

       Monica Srivastava <monasrivastava@...> wrote:

      Hi All

      I am going through the Risk Management PA of CMMI but i am not able to come
      to a conclusion what model or architectural definition should be defined,
      such as the SG 1 talks about Prepare a Risk M Plan - Determine sources and
      Categorize, parameters and establish strategy.

      Now other book such As Pressman and Jalotae directly comes to the Risk
      Identification activity, at that stage they used priority, impact etc.

      I am trying to map all the sub-practise of RSKM but sometimes it seems that 
      it is unnecessary.

      I saw the earlier link provided for the .pdf file, that is good but writing
      process in still finding difficult.

      Regards
      Monica


      _________________________________________________________________
      The new MSN 8: advanced junk mail protection and 2 months FREE*
      http://join.msn.com/?page=features/junkmail


      To unsubscribe from this group, send an email to:
      cmmi_process_improvement-unsubscribe@yahoogroups.com



      Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.



      Do you Yahoo!?
      Yahoo! Mail Plus - Powerful. Affordable. Sign up now

    • Bhanu Kumar
      Monica / Arvind and others, From what I understand as Risk as in CMMI, I feel we need to come out with at minimum the following: 1.. Existence of Risk Database
      Message 2 of 3 , Feb 3, 2003
      View Source
      • 0 Attachment
        Monica / Arvind and others,
         
        From what I understand as Risk as in CMMI, I feel we need to come out with at minimum the following:
         
        1. Existence of Risk Database
        2. Proof of managing risk
          1. In terms of Static and
          2. Dynamic Risks
        By static risks I mean the risks that are clear ones upfront and we know we need to manage and dynamic are those wherein we need to check the happenings (typical case of: Yes a risk but mitigation can wait) and then decide whether we need to manage or not.  For this we need to come out with the Organization Threshold values based on which we know when to have a mitigation and when not.
         
        This as far as I understand will result in Probable, Live, Mitigated, Closed risks in our database.
         
        Please validate whether my understanding is correct
         
        Thanks
        ----- Original Message -----
        Sent: Monday, February 03, 2003 9:40 AM
        Subject: Re: [CMMi Process Improvement] CMMi specific RSKM?

        Hi Monica,

        Preparing a Risk Management Plan consists of following activities:

        Assumptions:

        1. You have a database/repository of risks mainatained & updated regularly.(Categorization in the repository is advisable)

        2. Your Level 2 KPAs are followed in letter & spirit.

        Process Steps (Minimal to be defined):

        1. Look for a similar project & identify risks.

        2. Look in the risk repository for likely risks relevant to the project as well as the   mitigation plan & what worked & what did'nt.

        3. Plan for the risks and group the risks.

        4. Categorize the risks on the basis of say people, technology, environement, etc.

        HTH,

        Aravind Raman

        +91-80-207 35 27

         Monica Srivastava <monasrivastava@...> wrote:

        Hi All

        I am going through the Risk Management PA of CMMI but i am not able to come
        to a conclusion what model or architectural definition should be defined,
        such as the SG 1 talks about Prepare a Risk M Plan - Determine sources and
        Categorize, parameters and establish strategy.

        Now other book such As Pressman and Jalotae directly comes to the Risk
        Identification activity, at that stage they used priority, impact etc.

        I am trying to map all the sub-practise of RSKM but sometimes it seems that 
        it is unnecessary.

        I saw the earlier link provided for the .pdf file, that is good but writing
        process in still finding difficult.

        Regards
        Monica


        _________________________________________________________________
        The new MSN 8: advanced junk mail protection and 2 months FREE*
        http://join.msn.com/?page=features/junkmail


        To unsubscribe from this group, send an email to:
        cmmi_process_improvement-unsubscribe@yahoogroups.com



        Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.



        Do you Yahoo!?
        Yahoo! Mail Plus - Powerful. Affordable. Sign up now
        To unsubscribe from this group, send an email to:
        cmmi_process_improvement-unsubscribe@yahoogroups.com



        Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.

      Your message has been successfully submitted and would be delivered to recipients shortly.