    Hi Ribhu What do you do during the Project Kick-off Meetings? Obtain commitments to the plans? Some amount of reviews on the plans are also done during this
    Message 1 of 7 , Mar 30, 2012
    View Source
    • 0 Attachment

      Hi Ribhu

       

      What do you do during the Project Kick-off Meetings?

       

      Obtain commitments to the plans?

      Some amount of reviews on the plans are also done during this meeting?

       

      Hope you have some answers now from the Project Planning Process Area

       

      Cheers,

      Mathi Ezhil Arasu

       

      From: cmmi_process_improvement@yahoogroups.com [mailto:cmmi_process_improvement@yahoogroups.com] On Behalf Of Ribhu Lavania
      Sent: 29 March, 2012 3:47 PM
      To: cmmi_process_improvement@yahoogroups.com
      Subject: [CMMi Process Improvement] Project Kick-off meeting

       

       

      Which SPs are mapped to Project Kick-off meetings?
      Best Regards,
      Ribhu

    • Jeff Dalton
      Ribhu, I would consider thinking of it from a different angle. What is working about our kickoff meetings? What might we do to improve our kickoff meetings?
      Message 2 of 7 , Mar 30, 2012
      View Source
      • 0 Attachment
        Ribhu,

        I would consider thinking of it from a different angle.

        What is working about our kickoff meetings?  What might we do to improve our kickoff meetings?

        In order to improve our kickoff meeting, we  consider looking at practices in PP, PMC, MA, RSKM, IPM, and others.

        You may need to step back and look at the practices from those PAs that are "architectural" (e.g.; setting Risk strategy categories that you want to use for ALL projects), and "project based" (things you need to remember to focus on for that particular kickoff).

        Looking at it from the other perspective could lead you to create a "CMMI-centric" process, not a process that fits your business and your projects.

        Jeff


        Jeff Dalton, President
        Broadsword Solutions Corporation
        jeff@...
        248-341-3367 (office)
        248-709-4775 (cell)

        Certified SCAMPI Lead Appraiser
        Certified "Introduction to CMMI" Instructor
        Certified "CMMI Maturity Level 2 for Practitioners" Instructor
        SCAMPI Team Leader
        SEI Partner Advisory Board Member

        Visit our website at: http://www.broadswordsolutions.com

        Visit Jeff's Blog at: www.asktheCMMIAppraiser.com

        Follow Jeff on Twitter: CMMIAppraiser




        On Mar 29, 2012, at 6:16 AM, Ribhu Lavania wrote:

         

        Which SPs are mapped to Project Kick-off meetings?
        Best Regards,
        Ribhu


      • praveen
        Hello With PP it can be mapped to IPM also Thanks & Regards Praveen Harkawat L & T Mumbai India ... From: CQ Subject: RE: [CMMi Process
        Message 3 of 7 , Apr 8 4:29 AM
        View Source
        • 0 Attachment
          Hello

          With PP it can be mapped to IPM also

          Thanks & Regards

          Praveen Harkawat
          L & T Mumbai India

          --- On Fri, 3/30/12, CQ <627278@...> wrote:

          From: CQ <627278@...>
          Subject: RE: [CMMi Process Improvement] Project Kick-off meeting
          To: cmmi_process_improvement@yahoogroups.com
          Date: Friday, March 30, 2012, 2:59 PM

           

          Hi Ribhu

           

          What do you do during the Project Kick-off Meetings?

           

          Obtain commitments to the plans?

          Some amount of reviews on the plans are also done during this meeting?

           

          Hope you have some answers now from the Project Planning Process Area

           

          Cheers,

          Mathi Ezhil Arasu

           

          From: cmmi_process_improvement@yahoogroups.com [mailto:cmmi_process_improvement@yahoogroups.com] On Behalf Of Ribhu Lavania
          Sent: 29 March, 2012 3:47 PM
          To: cmmi_process_improvement@yahoogroups.com
          Subject: [CMMi Process Improvement] Project Kick-off meeting

           

           

          Which SPs are mapped to Project Kick-off meetings?
          Best Regards,
          Ribhu

        Your message has been successfully submitted and would be delivered to recipients shortly.