REPORT: Tests In Progress Report

Expand Messages
  • Andrew Priest
    Dear Group This is one of two reports reporting on the status of current tests at BackpackGearTest.org. TEST MONITORS should review this report for any issues
    Message 1 of 5 , Oct 27, 2005
    • 0 Attachment
      Dear Group

      This is one of two reports reporting on the
      status of current tests at BackpackGearTest.org.

      TEST MONITORS should review this report for any
      issues requiring their attention. However,
      before commenting on the content please note the
      report date and check the second report!

      Test Monitors are also reminded that you are
      expected to monitor your tests and to follow up
      any reporting issues as per the Survival Guide.

      Regards
      Andrew Priest
      List Moderator


      REPORT DATE: 26 October 2005

      ===============
      REPORT CONTENTS
      ===============

      SPECIAL NOTICES
      LIST OF TESTS IN PROGRESS
      ...NOT YET STARTED
      ...INITIAL REPORTING
      ...FIELD TEST PHASE
      ...LONG-TERM TEST PHASE

      ===============
      SPECIAL NOTICES
      ===============

      We have 117 tests in progress at present.

      ==========================================
      CALLS CLOSED BUT YET TO COMMENCE REPORTING
      ==========================================

      Darn Tough Vermont - Boot Sock Full Cushion
      ...Status: MANUF NOTIFIED 10/25
      ...Monitor: NOT SELECTED YET - Moderator: Rebecca
      ...Tester: Gail Staisil
      ...Tester: John R Waters
      ...Tester: Roger Caffin

      Black Diamond Equipment - Spot Headlamp
      ...Status:
      ...Monitor: Rick Allnutt - Moderator: Rick
      ...Tester: Andrew Henrichs
      ...Tester: Bill Jeffrey
      ...Tester: Josh Cormier

      Magellan - EXplorist 600
      ...Status: MANUF NOTIFIED 10/18
      ...Monitor: Kathleen Waters - Moderator: Rebecca
      ...Tester: Bill Jeffrey
      ...Tester: Pam Wyant
      ...Tester: Steve Nelson

      Magellan - Mapsend Topo 3D USA
      ...Status:
      ...Monitor: Chuck Kime - Moderator: ...Tester: Bill Jeffrey
      ...Tester: Rebecca (Becki) Rose Stacy
      ...Tester: Steve Nelson

      Integral Designs - eVENT Rain Pants
      ...Status:
      ...Monitor: Jason Boyle - Moderator: Rebecca
      ...Tester: Christine Korhonen
      ...Tester: Kathleen Waters
      ...Tester: Kenneth (Ken) Bigelow

      Keela USA - Rock Jacket
      ...Status: MANUF NOTIFIED 10/3
      ...Monitor: Rick Allnutt - Moderator: Rick/Coy
      ...Tester: Curt Peterson
      ...Tester: George Griffin
      ...Tester: Rosaleen Sullivan

      Gerber - Recon
      ...Status:
      ...Monitor: Jennifer Pope - Moderator: Dennis/Lynne
      ...Tester: David Hjelmar
      ...Tester: Jennifer Williams
      ...Tester: Mike Lipay

      Gerber - Triode
      ...Status:
      ...Monitor: Christine Korhonen - Moderator: Dennis/Lynne
      ...Tester: Josh Cormier
      ...Tester: Roger Caffin
      ...Tester: Will Rietveld

      Valandre - La Fayette
      ...Status: MANUF NOTIFIED 10/4
      ...Monitor: NOT SELECTED YET - Moderator: Stephanie
      ...Tester: Coy Starnes
      ...Tester: Stephanie Martin
      ...Tester: Steve Nelson

      IBEX Outdoor Clothing - Fall Line Pant
      ...Status:
      ...Monitor: NOT SELECTED YET - Moderator: Steph/Andy
      ...Tester: Andrew (Andy) Mytys
      ...Tester: Coy Starnes
      ...Tester: Jason Boyle

      IBEX Outdoor Clothing - Scout 1/2-Zip Shirt
      ...Status:
      ...Monitor: Thomas Vickers - Moderator: Stephanie/Andy
      ...Tester: Coy Starnes
      ...Tester: James E. Triplett
      ...Tester: Will Rietveld

      IBEX Outdoor Clothing - Shak Hoody
      ...Status:
      ...Monitor: Carol Crooker - Moderator: Steph/Andy
      ...Tester: Gail Staisil
      ...Tester: Jason Boyle
      ...Tester: Jennifer Williams

      Benchmade - 530
      ...Status: MANUF NOTIFIED 9/23
      ...Monitor: Jodi Cornelius - Moderator: Dennis
      ...Tester: Chuck Kime
      ...Tester: David Sowards-Emmerd
      ...Tester: Roger Caffin

      Benchmade - Mini Griptilion
      ...Status:
      ...Monitor: Thomas Vickers - Moderator: Dennis
      ...Tester: Coy Starnes
      ...Tester: Kathleen Waters
      ...Tester: Rick Dreher

      Bozeman Mountain Works - Cocoon Pullover
      ...Status: DELAYED UNTIL OCTOBER.
      ...Monitor: Tom Jones - Moderator: Jim S
      ...Tester: Rick Allnutt
      ...Tester: Roger Caffin
      ...Tester: Steve Nelson

      Crazy Creek Products - LEX Lightweight Hammock
      ...Status: MAN NOTIFIED 9/14
      ...Monitor: Christine Korhonen - Moderator: Rick
      ...Tester: Brian Tannehill
      ...Tester: Chuck Kime
      ...Tester: Jeff Jackson

      Moving Comfort - Kickback Pant
      ...Status: MANUF NOTIFIED 9/17
      ...Monitor: Rami Benhameda - Moderator: Rebecca
      ...Tester: Jennifer Pope
      ...Tester: Kathleen Waters
      ...Tester: Lynne Durham

      Moving Comfort - Daylight Bra
      ...Status: MANUF NOTIFIED 9/17
      ...Monitor: Jason Boyle - Moderator: Rebecca
      ...Tester: Jamie J. DeBenedetto
      ...Tester: Jennifer Williams
      ...Tester: Marie-Noelle Augendre

      Moving Comfort - Fiona Bra
      ...Status: MANUF NOTIFIED 9/17
      ...Monitor: Carol Crooker - Moderator: Rebecca
      ...Tester: Jennifer Pope
      ...Tester: Kathleen Waters
      ...Tester: Leesa Joiner

      Moving Comfort - Micro Panty
      ...Status: MANUF NOTIFIED 9/17
      ...Monitor: Carol Crooker - Moderator: Rebecca
      ...Tester: Colleen Porter
      ...Tester: Heather OakesPalmer
      ...Tester: Kathleen Waters

      ====================
      INITIAL REPORT PHASE
      ====================

      Molehill Mt. Equipment - Backpack Diaper Bag
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Tim Coughlin - Moderator: Jim
      .....Chuck Carnes...............DUE.....: 24 October 2005 - LATE
      .....Jamie J. DeBenedetto.......EDITED..: 25 October 2005
      .....Thomas Vickers.............POSTED..: 22 October 2005

      Integral Designs - PLQ Jacket
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Bill Jeffrey - Moderator: Rebecca
      .....Christine Korhonen.........ITEM NOT RECEIVED
      .....Edward (Ted) Ripley-Dugga..ITEM NOT RECEIVED
      .....Jason Boyle................DUE.....: 01 November 2005

      Sierra Designs - Hurricane Jacket and Pants
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Rosaleen Sullivan - Moderator: Stephanie
      .....Anthony (TJ) Smith.........COMPLETE: 26 October 2005
      .....Arron Robinson.............DUE.....: 27 October 2005
      .....Curt Peterson..............POSTED..: 26 October 2005

      Sierra Designs - Big Dog Sleeping Bag
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Chuck Carnes - Moderator: Steph
      .....Andre Corterier............EDITED..: 27 October 2005
      .....Anthony (TJ) Smith.........EDITED..: 27 October 2005
      .....David Posalski.............DUE.....: 07 October 2005 - LATE

      La Sportiva - Rajas Trail Runner
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: NOT SELECTED YET - Moderator: Stephanie/Andy
      .....Andrew Claus...............ITEM NOT RECEIVED
      .....Christine Korhonen.........DUE.....: 03 November 2005
      .....Gail Staisil...............DUE.....: 03 November 2005

      La Sportiva - Venture Mid XCR
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Michael Wheiler - Moderator: Stephanie/Andy
      .....Bob (Robert) Sanders.......DUE.....: 01 November 2005
      .....Coy Starnes................DUE.....: 02 November 2005
      .....Kathleen Waters............DUE.....: 03 November 2005

      Kershaw - Rainbow Leek Knife
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Alex Tweedly - Moderator: Jim
      .....Arron Robinson.............DUE.....: 03 November 2005
      .....Mike Lipay.................DUE.....: 03 November 2005
      .....Stephanie Martin...........DUE.....: 03 November 2005

      All Terrain - Hiker's Wonder Wash
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Will Rietveld - Moderator: Shane (Steph)
      .....Andre Corterier............COMPLETE: 20 October 2005
      .....Chuck Kime.................COMPLETE: 12 October 2005
      .....Colleen Porter.............EDITED..: 12 October 2005

      AntiGravityGear - Universal Alcohol Stove Accessory Pack
      ...Status: INITIAL REPORTS NOW DUE
      ...Monitor: Will Rietveld - Moderator: Rick
      .....Chuck Kime.................COMPLETE: 03 October 2005
      .....Pam Wyant..................COMPLETE: 30 September 2005
      .....Thomas Vickers.............EDITED..: 30 September 2005

      Atsko - Water Guard Spray and Sports Wash
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Edward (Ted) Ripley-Duggan - Moderator: Stephanie
      .....Andre Corterier............DUE.....: 01 November 2005
      .....Richard Lyon...............COMPLETE: 21 October 2005
      .....Rosaleen Sullivan..........COMPLETE: 26 October 2005

      Big Sky Products - Evolution 2P
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Jodi Cornelius - Moderator: Stephanie
      .....Graham Blamey..............ITEM NOT RECEIVED
      .....Lynne Durham...............COMPLETE: 23 August 2005
      .....Steve Nelson...............COMPLETE: 31 August 2005

      Big Sky Products - Warm-n-Cozy Epic Jackets
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Jennifer Pope - Moderator: Steph
      .....Jim Sabiston...............POSTED..: 27 October 2005
      .....Pam Wyant..................DUE.....: 28 October 2005
      .....Thomas Vickers.............DUE.....: 31 October 2005

      Big Sky Products - Warm-n-Cozy Full Zip Epic Pant
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Steve Nelson - Moderator: Steph
      .....Pam Wyant..................DUE.....: 28 October 2005
      .....Scott Michael Downard......DUE.....: 02 November 2005
      .....Thomas Vickers.............DUE.....: 31 October 2005

      Coleman - Xtreme Stove & Maintenance Kit
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Will Rietveld - Moderator: Stephanie
      .....Edward (Ted) Ripley-Dugga..COMPLETE: 22 October 2005
      .....Jerry Goller...............COMPLETE: 13 October 2005
      .....Leesa Joiner...............EDITED..: 21 October 2005

      Snugpak - Softie Chrysalis Micro Sleeping Bag
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Alex Tweedly - Moderator: Dennis
      .....Arron Robinson.............EDITED..: 14 October 2005
      .....Ralph Ditton...............COMPLETE: 15 October 2005
      .....Thomas Vickers.............COMPLETE: 10 October 2005

      Teko - Eco Merino Hiking Socks
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Kathleen Waters - Moderator: Jim / Andy
      .....Chuck Carnes...............COMPLETE: 29 September 2005
      .....Marie-Noelle Augendre......ITEM NOT RECEIVED
      .....Will Rietveld..............COMPLETE: 03 October 2005

      Thorlo - Level 1 UL Hiking Wool Blend
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Steve Nelson - Moderator: Steph/Andy
      .....Anthony (TJ) Smith.........POSTED..: 16 October 2005
      .....Richard Lyon...............POSTED..: 25 October 2005
      .....Russell Curry..............ITEM NOT RECEIVED

      Thorlo - Level 2 Hiker Socks
      ...Status: INITIAL REPORTS ARE NOW DUE
      ...Monitor: Jim Hatch - Moderator: Stephanie Martin
      .....Andre Corterier............DUE.....: 03 November 2005
      .....Jason Boyle................COMPLETE: 20 October 2005
      .....Jennifer Williams..........COMPLETE: 20 October 2005

      Ultralight Outfitters - Beercan Stove
      ...Status: FIELD TESTING
      ...Monitor: Chuck Kime - Moderator: Jim/ Andy
      .....Chuck Carnes...............COMPLETE: 07 October 2005
      .....Rosaleen Sullivan..........COMPLETE: 11 October 2005
      .....Scott Michael Downard......ITEM NOT RECEIVED

      ==================
      FIELD REPORT PHASE
      ==================

      Sierra Designs - Hercules Assault
      FR DUE: 03 January 2006 - LTR DUE: 28 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Coy Starnes - Moderator: Stephanie
      .....Chuck Carnes...............TESTING
      .....David Sowards-Emmerd.......TESTING
      .....Gail Staisil...............TESTING

      All Terrain - Recovery Rub
      FR DUE: 20 December 2005 - LTR DUE: 20 December 2005
      ...Status: FIELD TESTING
      ...Monitor: Jennifer Pope - Moderator: Shane (Steph)
      .....Andre Corterier............TESTING
      .....Chuck Kime.................TESTING
      .....Colleen Porter.............TESTING

      All Terrain - Hiker's Hand Sanz
      FR DUE: 03 January 2006 - LTR DUE: 03 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Christine Korhonen - Moderator: Shane (Steph)
      .....Andre Corterier............TESTING
      .....Chuck Kime.................TESTING
      .....Colleen Porter.............TESTING

      Aqua Star - UV Purifier Aquastar
      FR DUE: 29 November 2005 - LTR DUE: 24 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Jennifer Pope - Moderator: Shane (steph)
      .....Andy Rad...................TESTING
      .....Lynne Durham...............TESTING
      .....Rick Dreher................TESTING

      Coleman - F1 Lite Lantern
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Rami Benhameda - Moderator: Stephanie
      .....Curt Peterson..............TESTING
      .....James E. Triplett..........TESTING
      .....Rick Allnutt...............TESTING

      Coleman - Xcursion Lantern
      FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Sonjia Leyva - Moderator: Stephanie
      .....Edward (Ted) Ripley-Dugga..TESTING
      .....Jodi Cornelius.............TESTING
      .....Rebecca (Becki) Rose Stac..TESTING

      Coleman - Xtremecat Catalytic Heater
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Curt Peterson - Moderator: Stephanie
      .....David Posalski.............TESTING
      .....Jim Sabiston...............TESTING
      .....Jodi Cornelius.............TESTING

      Coleman - Krypton 2 Tent
      FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Leesa Joiner - Moderator: Stephanie
      .....David Posalski.............TESTING
      .....James E. Triplett..........TESTING
      .....Rebecca (Becki) Rose Stac..TESTING

      Coleman - Backpacker Table & Gear System
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Kenneth (Ken) Bigelow - Moderator: Stephanie
      .....Chuck Kime.................TESTING
      .....Jennifer Pope..............TESTING
      .....Jodi Cornelius.............TESTING

      Costa Del Mar - Fathom Sunglasses
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: David Posalski - Moderator: Steph
      .....Edward (Ted) Ripley-Dugga..TESTING
      .....Leesa Joiner...............TESTING
      .....Steve Nelson...............TESTING

      Delorme - Earthmate GPS LT-20
      FR DUE: 15 November 2005 - LTR DUE: 10 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Louis (Kiatikun) Luangkesorn - Moderator: Shane Steinkamp
      .....Brian Tannehill............TESTING
      .....Pam Wyant..................TESTING
      .....Sonjia Leyva...............TESTING

      Eastern Mountain Sports - Ridgeline Pack
      FR DUE: 25 October 2005 - LTR DUE: 10 January 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Roger Caffin - Moderator: Rebecca
      .....Lynne Durham...............COMPLETE: 26 October 2005
      .....Mark Wood..................DUE
      .....Scott Michael Downard......EDITED..: 28 October 2005

      Five Ten - Insight Trail Shoe
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Tom Jones - Moderator: Steph
      .....Andrew (Andy) Mytys........TESTING
      .....David Sowards-Emmerd.......TESTING
      .....Rosaleen Sullivan..........TESTING

      GSI Outdoors - 5 pc Anodized Cookset
      FR DUE: 03 January 2006 - LTR DUE: 28 February 2006
      ...Status: FIELD TESTING
      ...Monitor: David Posalski - Moderator: Stephanie
      .....Arron Robinson.............TESTING
      .....Graham Blamey..............TESTING
      .....Rebecca (Becki) Rose Stac..TESTING

      GoLite - Feather Sleeping Bag
      FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Rebecca (Becki) Rose Stacy - Moderator: Shane/Stephanie
      .....Chuck Kime.................TESTING
      .....Heather OakesPalmer........TESTING
      .....Rick Allnutt...............TESTING

      GoLite - Eisenhower Tunnel Shelter
      FR DUE: 30 August 2005 - LTR DUE: 03 January 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Leesa Joiner - Moderator: Shane
      .....Kathleen Waters............COMPLETE: 31 August 2005
      .....Thomas Vickers.............COMPLETE: 05 September 2005
      .....Tyler Nagel................EDITED..: 19 September 2005

      Gossamer Gear - Lightrek Plus Poles
      FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
      ...Status: FIELD TESTING
      ...Monitor: James E. Triplett - Moderator: Dennis
      .....Andrew (Andy) Mytys........TESTING
      .....Rick Allnutt...............TESTING
      .....Steve Nelson...............TESTING

      Gregory Mountain Products - G-pack
      FR DUE: 29 November 2005 - LTR DUE: 24 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Steve Nelson - Moderator: Stephanie
      .....Coy Starnes................TESTING
      .....Gail (Bosio) Staisil.......TESTING
      .....Graham Blamey..............TESTING

      INKA - Inka Pens
      FR DUE: 01 November 2005 - LTR DUE: 03 January 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Rosaleen Sullivan - Moderator: Jim
      .....Chuck Carnes...............TESTING
      .....Marie-Noelle Augendre......COMPLETE: 22 October 2005
      .....Mark Wood..................TESTING

      Jacks 'R Better - Pack Cover Gear Hammock
      FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Rick Allnutt - Moderator: Lynne
      .....Anthony (TJ) Smith.........TESTING
      .....Jodi Cornelius.............TESTING
      .....Marie-Noelle Augendre......TESTING

      Katadyn - Hiker Pro
      FR DUE: 15 November 2005 - LTR DUE: 17 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Scott Michael Downard - Moderator: Shane
      .....Coy Starnes................TESTING
      .....Jim Sabiston...............TESTING
      .....Kenneth (Ken) Bigelow......TESTING

      Kinesys - SPF 30 Spray On Sunblock
      FR DUE: 25 October 2005 - LTR DUE: 25 October 2005
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Carol Crooker - Moderator: Jim
      .....Jamie J. DeBenedetto.......EDITED..: 26 October 2005
      .....Jennifer Pope..............COMPLETE: 26 October 2005
      .....Lynne Durham...............COMPLETE: 19 October 2005

      Luxurylite Gear - Travel Pillow
      FR DUE: 29 November 2005 - LTR DUE: 31 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Alex Tweedly - Moderator: Rebecca
      .....Jason Boyle................TESTING
      .....Pam Wyant..................TESTING
      .....Scott Michael Downard......TESTING

      Merrell - Chameleon Kids Regular
      FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Sonjia Leyva - Moderator: Jim
      .....Anthony (TJ) Smith.........TESTING
      .....Colleen Porter.............TESTING
      .....Leesa Joiner...............TESTING

      Merrell - Waterpro Ultrasport
      FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Thomas Vickers - Moderator: Jim
      .....Arron Robinson.............TESTING
      .....Chuck Carnes...............TESTING
      .....Colleen Porter.............TESTING

      Molehill Mt. Equipment - Fleece Hooded Jacket
      FR DUE: 03 June 2006 - LTR DUE: 07 March 2006
      ...Status: FIELD TESTING
      ...Monitor: Bill Jeffrey - Moderator: Jim/Lynne
      .....Andre Corterier............TESTING
      .....Curt Peterson..............TESTING
      .....Jamie J. DeBenedetto.......TESTING

      Petzl - Tikka XP
      FR DUE: 06 December 2005 - LTR DUE: 31 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Bill Jeffrey - Moderator: Rebecca
      .....Andrew Priest..............TESTING
      .....Chuck Carnes...............TESTING
      .....Jason Boyle................TESTING

      Seattle Sports - LED Hedz Light
      FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Alex Tweedly - Moderator: Dennis/Andy
      .....Ralph Ditton...............TESTING
      .....Rebecca (Becki) Rose Stac..TESTING
      .....Russell Curry..............TESTING

      Spectrum Brands - Spectrum Brands Insect Repellent
      FR DUE: 01 November 2005 - LTR DUE: 03 January 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Will Rietveld - Moderator: Shane
      .....Andrew Priest..............TESTING
      .....Anthony (TJ) Smith.........TESTING
      .....Heather Oakes..............TESTING

      Spyderco - Salt 1 Spyderedge
      FR DUE: 29 November 2005 - LTR DUE: 31 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Mike Lipay - Moderator: Shane (Steph)/Coy
      .....Andre Corterier............TESTING
      .....Brian Tannehill............TESTING
      .....Mark Wood..................TESTING

      Spyderco - Vagabond Fixed Blade
      FR DUE: 06 December 2005 - LTR DUE: 31 January 2006
      ...Status: FIELD TESTING
      ...Monitor: Michael Herman - Moderator: Shane (Steph)/Coy
      .....Leesa Joiner...............TESTING
      .....Ralph Ditton...............TESTING
      .....Rick Allnutt...............TESTING

      Teko - Eco Merino Light Hiking Socks
      FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
      ...Status: FIELD TESTING
      ...Monitor: Jennifer Williams - Moderator: Jim
      .....Heather OakesPalmer........TESTING
      .....Jennifer Pope..............TESTING
      .....Thomas Vickers.............TESTING

      Thorlo - Level 3 Hiker Socks
      FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
      ...Status: FIELD TESTING
      ...Monitor: Arron Robinson - Moderator: Stephanie Martin
      .....Coy Starnes................TESTING
      .....Josh Cormier...............TESTING
      .....Rebecca (Becki) Rose Stac..TESTING

      Wayah Press - A Wildly Successful 200-Mile Hike
      FR DUE: 04 October 2005 - LTR DUE: 31 January 2006
      ...Status: FIELD REPORTS ARE NOW DUE
      ...Monitor: Chuck Carnes - Moderator: Shane
      .....Andrew (Andy) Mytys........POSTED..: 04 October 2005
      .....George Griffin.............COMPLETE: 07 October 2005
      .....John R Waters..............COMPLETE: 21 October 2005

      ======================
      LONG-TERM REPORT PHASE
      ======================

      Bask - Trekking Sleeping Bag
      LTR DUE: 29 November 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Thomas Vickers - Moderator: Jim
      .....Edward (Ted) Ripley-Dugga..TESTING
      .....James E. Triplett..........TESTING
      .....Shandra Hunt...............TESTING

      Bite Footwear - Xtension 2 sandal
      LTR DUE: 01 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Coy Starnes - Moderator: Stephanie
      .....Colleen Porter.............EDITED..: 25 October 2005
      .....James E. Triplett..........COMPLETE: 26 October 2005
      .....Lynne Durham...............COMPLETE: 24 October 2005

      Black Diamond Equipment - Terra CF Trekking Poles
      LTR DUE: 17 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: Andre Corterier - Moderator: Rick
      .....Curt Peterson..............TESTING
      .....Jim Sabiston...............TESTING
      .....Shandra Hunt...............TESTING

      Brunton - Liberty Lantern
      LTR DUE: 06 September 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Christine Korhonen - Moderator: Rick
      .....Cora (Hussey) Shea.........EDITED..: 05 October 2005
      .....David Sowards-Emmerd.......COMPLETE: 07 September 2005
      .....Mike Lipay.................COMPLETE: 09 September 2005

      Chaco Inc - Z/2
      LTR DUE: 22 November 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Tom Jones - Moderator: Rebecca Sowards-Emmerd
      .....Clifford R Haynes..........TESTING
      .....Edward (Ted) Ripley-Dugga..TESTING
      .....Marie-Noelle Augendre......TESTING

      Dunham - Alcatraz Trail Shoes
      LTR DUE: 10 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: Coy Starnes - Moderator: Rick
      .....Pam Wyant..................TESTING
      .....Rebecca Sowards-Emmerd.....TESTING
      .....Russell Curry..............TESTING

      Flatworld - Orikaso Picnic Set
      LTR DUE: 08 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Leesa Joiner - Moderator: Stephanie
      .....Christine Korhonen.........TESTING
      .....David Posalski.............TESTING
      .....Roger Caffin...............POSTED..: 27 October 2005

      Granite Gear - Winterizer
      LTR DUE: 13 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Jodi Cornelius - Moderator: Stephanie
      .....Edward (Ted) Ripley-Dugga..TESTING
      .....Pascal Deschênes...........TESTING
      .....Tim Coughlin...............TESTING

      Granite Gear - Nimbus Latitude Ki
      LTR DUE: 08 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Jason Boyle - Moderator: Stephanie
      .....Amanda Tikkanen............TESTING
      .....Kathleen Waters............TESTING
      .....Rebecca Sowards-Emmerd.....TESTING

      Hennessy Hammock - Supershelter
      LTR DUE: 13 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Chuck Kime - Moderator: Shane
      .....Jamie J. DeBenedetto.......TESTING
      .....Jim Sabiston...............TESTING
      .....Jodi Cornelius.............TESTING

      IBEX Outdoor Clothing - Approach Tights
      LTR DUE: 13 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Chuck Carnes - Moderator: Stephanie
      .....Cora (Hussey) Shea.........TESTING
      .....James E. Triplett..........TESTING
      .....Pascal Deschênes...........TESTING

      Imlay Canyon Gear - Imlay Canyon Knife
      LTR DUE: 08 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: David Sowards-Emmerd - Moderator: Stephanie
      .....Jason Boyle................EDITED..: 26 October 2005
      .....Pam Wyant..................TESTING
      .....Thomas Vickers.............TESTING

      Integral Designs - eVENT Rain Jacket
      LTR DUE: 22 November 2005
      ...Status: FIELD TESTING
      ...Monitor: Kenneth (Ken) Bigelow - Moderator: Rebecca
      .....Andy Rad...................TESTING
      .....David Sowards-Emmerd.......TESTING
      .....Will Rietveld..............TESTING

      Integral Designs - eVENT Shortie Gaiters
      LTR DUE: 22 November 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Jason Boyle - Moderator: Rebecca
      .....Kenneth (Ken) Bigelow......TESTING
      .....Todd Martin................TESTING
      .....Will Rietveld..............TESTING

      Integral Designs - Silcoat Pack Cover
      LTR DUE: 06 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Attila Hargitai - Moderator: Rebecca
      .....Bill Jeffrey...............TESTING
      .....Curt Peterson..............TESTING
      .....Kenneth (Ken) Bigelow......TESTING

      Integral Designs - Silcoat Backpack
      LTR DUE: 06 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Edward (Ted) Ripley-Duggan - Moderator: Rebecca
      .....Andy Rad...................TESTING
      .....Bill Jeffrey...............TESTING
      .....Laurie Corbin..............TESTING

      Integral Designs - Silshelter Bug Liner
      LTR DUE: 06 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Coy Starnes - Moderator: Rebecca
      .....Bill Jeffrey...............TESTING
      .....David Sowards-Emmerd.......TESTING
      .....Todd Martin................TESTING

      JetBoil - PCS stove assembly
      LTR DUE: 27 September 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Tom Jones - Moderator: Shane
      .....Jodi Cornelius.............EDITED..: 14 October 2005
      .....Mark Keskes................DUE
      .....Rebecca Sowards-Emmerd.....COMPLETE: 18 October 2005

      Keen Footwear - Taos
      LTR DUE: 29 November 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Coy Starnes - Moderator: Rebecca
      .....Jennifer Joy...............TESTING
      .....Jennifer Pope..............TESTING
      .....Rami Benhameda.............TESTING

      Keen Footwear - Boulder
      LTR DUE: 13 December 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Leesa Joiner - Moderator: Rebecca
      .....Ashlee Gunter..............TESTING
      .....Kenneth (Ken) Bigelow......TESTING
      .....Stephanie Martin...........TESTING

      National Geographic - TOPO! Streets & 3-D Views
      LTR DUE: 08 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Colleen Porter - Moderator: Shane
      .....Jennifer Pope..............TESTING
      .....Kenneth (Ken) Bigelow......POSTED..: 27 October 2005
      .....Raymond Estrella...........TESTING

      Sierra Designs - Rock Creek and Osage
      LTR DUE: 22 November 2005
      ...Status: LONG-TERM TESTING
      ...Monitor: Michael Wheiler - Moderator: Stephanie Martin
      .....Andrew Priest..............TESTING
      .....Leesa Joiner...............TESTING
      .....Lynne Durham...............TESTING

      Six Moon Designs - Comet Pack
      LTR DUE: 22 November 05
      ...Status: LONG-TERM TESTING
      ...Monitor: Brian Tannehill - Moderator: Stephanie
      .....Colleen Porter.............DUE
      .....George Griffin.............DUE
      .....Jamie J. DeBenedetto.......DUE

      SmartWool - Microweight Fitted T
      LTR DUE: 22 November 2005
      ...Status: FIELD TESTING
      ...Monitor: Jamie J. DeBenedetto - Moderator: Rebecca
      .....Andre Corterier............TESTING
      .....Christine Korhonen.........TESTING
      .....Lynne Durham...............TESTING

      Smith - Theory
      LTR DUE: 20 September 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Rami Benhameda - Moderator: Rebecca
      .....Ashlee Gunter..............DUE
      .....Gail Bosio.................COMPLETE: 23 September 2005
      .....Rebecca Sowards-Emmerd.....COMPLETE: 24 September 2005

      Speer Hammocks - Segmented Pad Extender
      LTR DUE: 03 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: Curt Peterson - Moderator: Rick
      .....Arron Robinson.............TESTING
      .....Christine Korhonen.........TESTING
      .....Kenneth (Ken) Bigelow......TESTING

      Spenco - Day Hiker Insole
      LTR DUE: 10 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: Rami Benhameda - Moderator: Rebecca
      .....Jennifer Pope..............TESTING
      .....Jennifer Williams..........TESTING
      .....Mike Lipay.................TESTING

      Spenco - Backpacker Insole
      LTR DUE: 10 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: Pam Wyant - Moderator: Rebecca
      .....Rebecca (Becki) Stacy......TESTING
      .....Russell Curry..............TESTING
      .....Will Rietveld..............TESTING

      Teva Sport Sandals - Steep XCR
      LTR DUE: 08 November 2005
      ...Status: LONG-TERM REPORTS ARE NOW DUE
      ...Monitor: Colleen Porter - Moderator: Stephanie
      .....Heather Oakes..............TESTING
      .....Jason Boyle................TESTING
      .....Jennifer Williams..........TESTING

      Ultimate Direction - Cohiba Pack
      LTR DUE: 13 September 2005
      ...Status: LONG-TERM REPORTS NOW DUE
      ...Monitor: Sonjia Leyva - Moderator: Stephanie
      .....Chuck Carnes...............COMPLETE: 13 September 2005
      .....James E. Triplett..........COMPLETE: 15 September 2005
      .....Thomas Peltier II..........EDITED..: 26 September 2005

      Vargo Outdoors - Titanium 'Jet-ti' stove
      LTR DUE: 10 January 2006
      ...Status: LONG-TERM TESTING
      ...Monitor: George Griffin - Moderator: Shane
      .....Anthony (TJ) Smith.........TESTING
      .....John R Waters..............TESTING
      .....Ralph Ditton...............TESTING



      REPORT END.



      ==
      Senior Edit Moderator and List Moderator
      http://BackpackGearTest.org

      ICQ No. 38215599
      MSN Messenger: aushiker@...
      Yahoo Messenger: aushiker
    • Thomas Vickers
      AntiGravityGear - Universal Alcohol Stove Accessory Pack ...Status: INITIAL REPORTS NOW DUE ...Monitor: Will Rietveld - Moderator: Rick .....Chuck
      Message 2 of 5 , Oct 27, 2005
      • 0 Attachment
        AntiGravityGear - Universal Alcohol Stove Accessory Pack
        ...Status: INITIAL REPORTS NOW DUE
        ...Monitor: Will Rietveld - Moderator: Rick
        .....Chuck Kime.................COMPLETE: 03 October 2005
        .....Pam Wyant..................COMPLETE: 30 September 2005
        .....Thomas Vickers.............EDITED..: 30 September 2005


        Andrew,
        My report is posted. I even fixed a booboo for you.

        Tv
      • André Corterier
        short form: OOP until November 3. semi-affected: atsko IR André long version: According to http://groups.yahoo.com/group/backpackgeartesters/message/8021 we
        Message 3 of 5 , Oct 28, 2005
        • 0 Attachment
          short form:

          OOP until November 3.
          semi-affected: atsko IR

          André

          long version:
          According to
          http://groups.yahoo.com/group/backpackgeartesters/message/8021
          we were given two weeks for the IR on the Atsko products to be able
          to comment on application. With the Thorlo IR due on November 3 and a
          long weekend ahead in which I'll be away from my computer (testing!),
          followed by a business trip, I will need some of that additional
          time, too.
          I will try to get that socks IR in on time. The atsko IR, too - but
          inside the longer two-week window.


          --- In backpackgeartesters@yahoogroups.com, Andrew Priest
          <apriest@b...> wrote:
          <snip>
          > Atsko - Water Guard Spray and Sports Wash
          > ...Status: INITIAL REPORTS ARE NOW DUE
          > ...Monitor: Edward (Ted) Ripley-Duggan - Moderator: Stephanie
          > .....Andre Corterier............DUE.....: 01 November 2005
          > .....Richard Lyon...............COMPLETE: 21 October 2005
          > .....Rosaleen Sullivan..........COMPLETE: 26 October 2005
          <snip>
          > Thorlo - Level 2 Hiker Socks
          > ...Status: INITIAL REPORTS ARE NOW DUE
          > ...Monitor: Jim Hatch - Moderator: Stephanie Martin
          > .....Andre Corterier............DUE.....: 03 November 2005
          > .....Jason Boyle................COMPLETE: 20 October 2005
          > .....Jennifer Williams..........COMPLETE: 20 October 2005
        • Andrew Priest
          ... Thanks for letting me know TV. Now fixed. Andrew == Senior Edit Moderator and List Moderator http://BackpackGearTest.org ICQ No. 38215599 MSN Messenger:
          Message 4 of 5 , Oct 28, 2005
          • 0 Attachment
            At 11:52 AM 28/10/2005, you wrote:


            >AntiGravityGear - Universal Alcohol Stove Accessory Pack
            >...Status: INITIAL REPORTS NOW DUE
            >...Monitor: Will Rietveld - Moderator: Rick
            >.....Chuck Kime.................COMPLETE: 03 October 2005
            >.....Pam Wyant..................COMPLETE: 30 September 2005
            >.....Thomas Vickers.............EDITED..: 30 September 2005
            >
            >
            >Andrew,
            >My report is posted. I even fixed a booboo for you.

            Thanks for letting me know TV. Now fixed.

            Andrew

            ==
            Senior Edit Moderator and List Moderator
            http://BackpackGearTest.org

            ICQ No. 38215599
            MSN Messenger: aushiker@...
            Yahoo Messenger: aushiker


            [Non-text portions of this message have been removed]
          • Andrew Priest
            Dear Group This is one of two reports reporting on the status of current tests at BackpackGearTest.org. TEST MONITORS should review this report for any issues
            Message 5 of 5 , Dec 1, 2005
            • 0 Attachment
              Dear Group

              This is one of two reports reporting on the
              status of current tests at BackpackGearTest.org.

              TEST MONITORS should review this report for any
              issues requiring their attention. However,
              before commenting on the content please note the
              report date and check the second report!

              Test Monitors are also reminded that you are
              expected to monitor your tests and to follow up
              any reporting issues as per the Survival Guide.

              Regards
              Andrew Priest
              List Moderator

              REPORT DATE: 30 November 2005

              ===============
              REPORT CONTENTS
              ===============

              SPECIAL NOTICES
              LIST OF TESTS IN PROGRESS
              ...NOT YET STARTED
              ...INITIAL REPORTING
              ...FIELD TEST PHASE
              ...LONG-TERM TEST PHASE

              ===============
              SPECIAL NOTICES
              ===============

              We have 108 tests in progress at present.

              ==========================================
              CALLS CLOSED BUT YET TO COMMENCE REPORTING
              ==========================================

              Bozeman Mountain Works - Cocoon Pullover
              ...Status: DELAYED UNTIL OCTOBER.
              ...Monitor: Tom Jones - Moderator: Jim S
              ...Tester: Rick Allnutt
              ...Tester: Roger Caffin
              ...Tester: Steve Nelson

              Duofold - Varitherm Midweight Base Layers
              ...Status:
              ...Monitor: Jamie J. DeBenedetto - Moderator: Rebecca
              ...Tester: Jim Hatch
              ...Tester: Marie-Noelle Augendre
              ...Tester: Ryan L. Christen sen

              Duofold - Multisport Mid Layer Jacket
              ...Status:
              ...Monitor: Pam Wyant - Moderator: Rebecca
              ...Tester: Chuck Kime
              ...Tester: Graham Blamey
              ...Tester: Jeffrey W. Jackson

              Gerber - Recon
              ...Status:
              ...Monitor: Jennifer Pope - Moderator: Dennis/Lynne
              ...Tester: David Hjelmar
              ...Tester: Jennifer Williams
              ...Tester: Mike Lipay

              Gerber - Triode
              ...Status:
              ...Monitor: Christine Korhonen - Moderator: Dennis/Lynne
              ...Tester: Josh Cormier
              ...Tester: Roger Caffin
              ...Tester: Will Rietveld

              Humm Foods Inc - Larabar
              ...Status: MAN NOTIFIED 11/21
              ...Monitor: Brian Tannehill - Moderator: Jim
              ...Tester: Kevin Lerner
              ...Tester: Matt Mauceri
              ...Tester: Raymond Estrella

              Kahtoola - KTS-Steel
              ...Status:
              ...Monitor: Colleen Porter - Moderator: Rebecca
              ...Tester: Jim Sabiston
              ...Tester: Lynne Durham
              ...Tester: Rick Dreher

              Magellan - EXplorist 600
              ...Status: MANUF NOTIFIED 10/18
              ...Monitor: Kathleen Waters - Moderator: Rebecca
              ...Tester: Bill Jeffrey
              ...Tester: Pam Wyant
              ...Tester: Steve Nelson

              Magellan - Mapsend Topo 3D USA
              ...Status:
              ...Monitor: Chuck Kime - Moderator: ...Tester: Bill Jeffrey
              ...Tester: Rebecca (Becki) Rose Stacy
              ...Tester: Steve Nelson

              Outdoor Research - Rando Cap
              ...Status:
              ...Monitor: David Sowards-Emmerd - Moderator: Rick
              ...Tester: Andrew (Andy) Mytys
              ...Tester: Chuck Kime
              ...Tester: Raymond Estrella

              Outdoor Research - Talon Gloves
              ...Status:
              ...Monitor: George Griffin - Moderator: Rick
              ...Tester: Andrew Henrichs
              ...Tester: Chad Fie
              ...Tester: Will Rietveld

              Valandre - Shocking Blue
              ...Status: MAN NOTIFIED 11/
              ...Monitor: Colleen Porter - Moderator: Steph
              ...Tester: Carol Crooker
              ...Tester: Jerry Goller
              ...Tester: Jim Sabiston

              ====================
              INITIAL REPORT PHASE
              ====================

              Atsko - Snowseal
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Jason Boyle - Moderator: Stephanie
              .....Kathryn Doiron.............DUE.....: 08 December 2005
              .....Richard Lyon...............POSTED..: 30 November 2005
              .....Rick Allnutt...............COMPLETE: 26 November 2005

              IBEX Outdoor Clothing - Fall Line Pant
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Rosaleen Sullivan - Moderator: Steph/Andy
              .....Andrew (Andy) Mytys........EDITED..: 28 November 2005
              .....Coy Starnes................COMPLETE: 16 November 2005
              .....Jason Boyle................COMPLETE: 26 November 2005

              Integral Designs - PLQ Jacket
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Bill Jeffrey - Moderator: Rebecca
              .....Christine Korhonen.........EDITED..: 29 November 2005
              .....Edward (Ted) Ripley-Dugga..COMPLETE: 06 November 2005
              .....Jason Boyle................COMPLETE: 06 November 2005

              La Sportiva - Rajas Trail Runner
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Roger Caffin - Moderator: Stephanie/Andy
              .....Andrew Claus...............POSTED..: 20 November 2005
              .....Christine Korhonen.........EDITED..: 26 November 2005
              .....Gail Staisil...............COMPLETE: 03 November 2005

              Sierra Designs - Echo/Electra
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Carol Crooker - Moderator: Steph
              .....Gail Staisil...............POSTED..: 01 December 2005
              .....Kenneth (Ken) Bigelow......COMPLETE: 28 November 2005
              .....Rebecca Sowards-Emmerd.....EDITED..: 30 November 2005

              Thorlo - Level 1 UL Hiking Wool Blend
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: Steve Nelson - Moderator: Steph/Andy
              .....Anthony (TJ) Smith.........COMPLETE: 08 November 2005
              .....Richard Lyon...............COMPLETE: 08 November 2005
              .....Russell Curry..............ITEM NOT RECEIVED

              Ultralight Outfitters - Beercan Stove
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Chuck Kime - Moderator: Jim/ Andy
              .....Chuck Carnes...............COMPLETE: 07 October 2005
              .....Rosaleen Sullivan..........COMPLETE: 11 October 2005
              .....Scott Michael Downard......COMPLETE: 01 December 2005

              Valandre - La Fayette
              ...Status: INITIAL REPORTS ARE NOW DUE
              ...Monitor: David Sowards-Emmerd - Moderator: Stephanie
              .....Coy Starnes................POSTED..: 30 November 2005
              .....Stephanie Martin...........POSTED..: 29 November 2005
              .....Steve Nelson...............DUE.....: 21 November 2005 - LATE

              ==================
              FIELD REPORT PHASE
              ==================

              All Terrain - Recovery Rub
              FR DUE: 20 December 2005 - LTR DUE: 20 December 2005
              ...Status: FIELD TESTING
              ...Monitor: Jennifer Pope - Moderator: Shane (Steph)
              .....Andre Corterier............TESTING
              .....Chuck Kime.................TESTING
              .....Colleen Porter.............TESTING

              All Terrain - Hiker's Hand Sanz
              FR DUE: 03 January 2006 - LTR DUE: 03 January 2006
              ...Status: FIELD TESTING
              ...Monitor: Christine Korhonen - Moderator: Shane (Steph)
              .....Andre Corterier............TESTING
              .....Chuck Kime.................TESTING
              .....Colleen Porter.............TESTING

              All Terrain - Hiker's Wonder Wash
              FR DUE: 03 January 2006 - LTR DUE: 03 January 2006
              ...Status: FIELD TESTING
              ...Monitor: Will Rietveld - Moderator: Shane (Steph)
              .....Andre Corterier............TESTING
              .....Chuck Kime.................TESTING
              .....Colleen Porter.............TESTING

              AntiGravityGear - Universal Alcohol Stove Accessory Pack
              FR DUE: 29 November 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Will Rietveld - Moderator: Rick
              .....Chuck Kime.................COMPLETE: 29 November 2005
              .....Pam Wyant..................EDITED..: 30 November 2005
              .....Thomas Vickers.............COMPLETE: 29 November 2005

              Atsko - Water Guard Spray and Sports Wash
              FR DUE: 14 March 2006 - LTR DUE: 14 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Edward (Ted) Ripley-Duggan - Moderator: Stephanie
              .....Andre Corterier............TESTING
              .....Richard Lyon...............TESTING
              .....Rosaleen Sullivan..........TESTING

              Benchmade - 530
              FR DUE: 24 January 2006 - LTR DUE: 28 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Jodi Cornelius - Moderator: Dennis
              .....Chuck Kime.................TESTING
              .....David Sowards-Emmerd.......TESTING
              .....Roger Caffin...............TESTING

              Big Sky Products - Warm-n-Cozy Epic Jackets
              FR DUE: 03 January 2006 - LTR DUE: 28 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Jennifer Pope - Moderator: Steph
              .....Jim Sabiston...............TESTING
              .....Pam Wyant..................TESTING
              .....Thomas Vickers.............TESTING

              Big Sky Products - Warm-n-Cozy Full Zip Epic Pant
              FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Steve Nelson - Moderator: Steph
              .....Pam Wyant..................TESTING
              .....Scott Michael Downard......TESTING
              .....Thomas Vickers.............TESTING

              Black Diamond Equipment - Spot Headlamp
              FR DUE: 10 January 2006 - LTR DUE: 14 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Rick Allnutt - Moderator: Rick
              .....Andrew Henrichs............TESTING
              .....Bill Jeffrey...............TESTING
              .....Josh Cormier...............TESTING

              Coleman - F1 Lite Lantern
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Rami Benhameda - Moderator: Stephanie
              .....Curt Peterson..............TESTING
              .....James E. Triplett..........TESTING
              .....Rick Allnutt...............TESTING

              Coleman - Xcursion Lantern
              FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Sonjia Leyva - Moderator: Stephanie
              .....Edward (Ted) Ripley-Dugga..POSTED..: 01 December 2005
              .....Jodi Cornelius.............TESTING
              .....Rebecca (Becki) Rose Stac..TESTING

              Coleman - Xtremecat Catalytic Heater
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Curt Peterson - Moderator: Stephanie
              .....David Posalski.............TESTING
              .....Jim Sabiston...............TESTING
              .....Jodi Cornelius.............TESTING

              Coleman - Krypton 2 Tent
              FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Leesa Joiner - Moderator: Stephanie
              .....David Posalski.............TESTING
              .....James E. Triplett..........TESTING
              .....Rebecca (Becki) Rose Stac..TESTING

              Coleman - Backpacker Table & Gear System
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Kenneth (Ken) Bigelow - Moderator: Stephanie
              .....Chuck Kime.................TESTING
              .....Jennifer Pope..............TESTING
              .....Jodi Cornelius.............TESTING

              Coleman - Xtreme Stove & Maintenance Kit
              FR DUE: 03 January 2006 - LTR DUE: 27 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Will Rietveld - Moderator: Stephanie
              .....Edward (Ted) Ripley-Dugga..TESTING
              .....Jerry Goller...............TESTING
              .....Leesa Joiner...............TESTING

              Costa Del Mar - Fathom Sunglasses
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: David Posalski - Moderator: Steph
              .....Edward (Ted) Ripley-Dugga..POSTED..: 27 November 2005
              .....Leesa Joiner...............TESTING
              .....Steve Nelson...............TESTING

              Darn Tough Vermont - Boot Sock Full Cushion
              FR DUE: 10 January 2006 - LTR DUE: 14 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Jodi Cornelius - Moderator: Rebecca
              .....Gail Staisil...............TESTING
              .....John R Waters..............TESTING
              .....Roger Caffin...............TESTING

              Delorme - Earthmate GPS LT-20
              FR DUE: 15 November 2005 - LTR DUE: 10 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Louis (Kiatikun) Luangkesorn - Moderator: Shane Steinkamp
              .....Brian Tannehill............COMPLETE: 27 November 2005
              .....Pam Wyant..................COMPLETE: 26 November 2005
              .....Sonjia Leyva...............EDITED..: 29 November 2005

              Five Ten - Insight Trail Shoe
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Tom Jones - Moderator: Steph
              .....Andrew (Andy) Mytys........TESTING
              .....David Sowards-Emmerd.......TESTING
              .....Rosaleen Sullivan..........TESTING

              GSI Outdoors - 5 pc Anodized Cookset
              FR DUE: 03 January 2006 - LTR DUE: 28 February 2006
              ...Status: FIELD TESTING
              ...Monitor: David Posalski - Moderator: Stephanie
              .....Arron Robinson.............TESTING
              .....Graham Blamey..............TESTING
              .....Rebecca (Becki) Rose Stac..TESTING

              GoLite - Feather Sleeping Bag
              FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Rebecca (Becki) Rose Stacy - Moderator: Shane/Stephanie
              .....Chuck Kime.................TESTING
              .....Heather OakesPalmer........TESTING
              .....Rick Allnutt...............TESTING

              Gossamer Gear - Lightrek Plus Poles
              FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: James E. Triplett - Moderator: Dennis
              .....Andrew (Andy) Mytys........TESTING
              .....Rick Allnutt...............TESTING
              .....Steve Nelson...............TESTING

              Gregory Mountain Products - G-pack
              FR DUE: 29 November 2005 - LTR DUE: 24 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Steve Nelson - Moderator: Stephanie
              .....Coy Starnes................POSTED..: 24 November 2005
              .....Gail (Bosio) Staisil.......POSTED..: 21 November 2005
              .....Graham Blamey..............DUE

              IBEX Outdoor Clothing - Scout 1/2-Zip Shirt
              FR DUE: 17 January 2006 - LTR DUE: 21 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Thomas Vickers - Moderator: Stephanie/Andy
              .....Coy Starnes................TESTING
              .....James E. Triplett..........TESTING
              .....Will Rietveld..............TESTING

              IBEX Outdoor Clothing - Shak Hoody
              FR DUE: 24 January 2006 - LTR DUE: 21 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Carol Crooker - Moderator: Steph/Andy
              .....Gail Staisil...............TESTING
              .....Jason Boyle................TESTING
              .....Jennifer Williams..........TESTING

              Integral Designs - eVENT Rain Pants
              FR DUE: 17 January 2006 - LTR DUE: 21 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Jason Boyle - Moderator: Rebecca
              .....Christine Korhonen.........TESTING
              .....Kathleen Waters............TESTING
              .....Kenneth (Ken) Bigelow......TESTING

              Jacks 'R Better - Pack Cover Gear Hammock
              FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Rick Allnutt - Moderator: Lynne
              .....Anthony (TJ) Smith.........TESTING
              .....Jodi Cornelius.............TESTING
              .....Marie-Noelle Augendre......POSTED..: 30 November 2005

              Keela USA - Rock Jacket
              FR DUE: 24 January 2006 - LTR DUE: 28 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Rick Allnutt - Moderator: Rick/Coy
              .....Curt Peterson..............TESTING
              .....George Griffin.............TESTING
              .....Rosaleen Sullivan..........TESTING

              Kershaw - Rainbow Leek Knife
              FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Alex Tweedly - Moderator: Jim
              .....Arron Robinson.............TESTING
              .....Mike Lipay.................TESTING
              .....Stephanie Martin...........TESTING

              La Sportiva - Venture Mid XCR
              FR DUE: 10 January 2006 - LTR DUE: 14 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Michael Wheiler - Moderator: Stephanie/Andy
              .....Bob (Robert) Sanders.......TESTING
              .....Coy Starnes................TESTING
              .....Kathleen Waters............TESTING

              Luxurylite Gear - Travel Pillow
              FR DUE: 29 November 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Alex Tweedly - Moderator: Rebecca
              .....Jason Boyle................COMPLETE: 27 November 2005
              .....Pam Wyant..................EDITED..: 01 December 2005
              .....Scott Michael Downard......DUE

              Merrell - Chameleon Kids Regular
              FR DUE: 13 December 2005 - LTR DUE: 14 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Sonjia Leyva - Moderator: Jim
              .....Anthony (TJ) Smith.........TESTING
              .....Colleen Porter.............TESTING
              .....Leesa Joiner...............TESTING

              Merrell - Waterpro Ultrasport
              FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Thomas Vickers - Moderator: Jim
              .....Arron Robinson.............TESTING
              .....Chuck Carnes...............TESTING
              .....Colleen Porter.............TESTING

              Molehill Mt. Equipment - Backpack Diaper Bag
              FR DUE: 10 January 2006 - LTR DUE: 14 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Tim Coughlin - Moderator: Jim
              .....Chuck Carnes...............TESTING
              .....Jamie J. DeBenedetto.......TESTING
              .....Thomas Vickers.............TESTING

              Molehill Mt. Equipment - Fleece Hooded Jacket
              FR DUE: 03 June 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Bill Jeffrey - Moderator: Jim/Lynne
              .....Andre Corterier............TESTING
              .....Curt Peterson..............TESTING
              .....Jamie J. DeBenedetto.......TESTING

              Petzl - Tikka XP
              FR DUE: 06 December 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Bill Jeffrey - Moderator: Rebecca
              .....Andrew Priest..............TESTING
              .....Chuck Carnes...............TESTING
              .....Jason Boyle................POSTED..: 30 November 2005

              Seattle Sports - LED Hedz Light
              FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Alex Tweedly - Moderator: Dennis/Andy
              .....Ralph Ditton...............TESTING
              .....Rebecca (Becki) Rose Stac..TESTING
              .....Russell Curry..............POSTED..: 29 November 2005

              Sierra Designs - Hurricane Jacket and Pants
              FR DUE: 10 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Rosaleen Sullivan - Moderator: Stephanie
              .....Anthony (TJ) Smith.........TESTING
              .....Arron Robinson.............TESTING
              .....Curt Peterson..............TESTING

              Sierra Designs - Big Dog Sleeping Bag
              FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Chuck Carnes - Moderator: Steph
              .....Andre Corterier............TESTING
              .....Anthony (TJ) Smith.........TESTING
              .....David Posalski.............TESTING

              Sierra Designs - Hercules Assault
              FR DUE: 03 January 2006 - LTR DUE: 28 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Coy Starnes - Moderator: Stephanie
              .....Chuck Carnes...............TESTING
              .....David Sowards-Emmerd.......TESTING
              .....Gail Staisil...............TESTING

              Sierra Designs - Cirque/Mist
              FR DUE: 17 January 2006 - LTR DUE: 21 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Heather OakesPalmer - Moderator: Steph
              .....Andrew Claus...............TESTING
              .....Christine Korhonen.........TESTING
              .....Jim Hatch..................TESTING

              Snugpak - Softie Chrysalis Micro Sleeping Bag
              FR DUE: 13 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Alex Tweedly - Moderator: Dennis
              .....Arron Robinson.............TESTING
              .....Ralph Ditton...............POSTED..: 29 November 2005
              .....Thomas Vickers.............TESTING

              Spyderco - Salt 1 Spyderedge
              FR DUE: 29 November 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Mike Lipay - Moderator: Shane (Steph)/Coy
              .....Andre Corterier............COMPLETE: 25 November 2005
              .....Brian Tannehill............EDITED..: 30 November 2005
              .....Mark Wood..................DUE

              Spyderco - Vagabond Fixed Blade
              FR DUE: 06 December 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Michael Herman - Moderator: Shane (Steph)/Coy
              .....Leesa Joiner...............TESTING
              .....Ralph Ditton...............POSTED..: 23 November 2005
              .....Rick Allnutt...............TESTING

              Teko - Eco Merino Light Hiking Socks
              FR DUE: 06 December 2005 - LTR DUE: 07 February 2006
              ...Status: FIELD TESTING
              ...Monitor: Jennifer Williams - Moderator: Jim
              .....Heather OakesPalmer........TESTING
              .....Jennifer Pope..............TESTING
              .....Thomas Vickers.............TESTING

              Teko - Eco Merino Hiking Socks
              FR DUE: 06 December 2005 - LTR DUE: 31 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Kathleen Waters - Moderator: Jim / Andy
              .....Chuck Carnes...............TESTING
              .....Marie-Noelle Augendre......TESTING
              .....Will Rietveld..............TESTING

              Thorlo - Level 2 Hiker Socks
              FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Jim Hatch - Moderator: Stephanie Martin
              .....Andre Corterier............TESTING
              .....Jason Boyle................TESTING
              .....Jennifer Williams..........TESTING

              Thorlo - Level 3 Hiker Socks
              FR DUE: 03 January 2006 - LTR DUE: 07 March 2006
              ...Status: FIELD TESTING
              ...Monitor: Arron Robinson - Moderator: Stephanie Martin
              .....Coy Starnes................TESTING
              .....Josh Cormier...............TESTING
              .....Rebecca (Becki) Rose Stac..TESTING

              ======================
              LONG-TERM REPORT PHASE
              ======================

              Aqua Star - UV Purifier Aquastar
              LTR DUE: 24 January 2006
              ...Status: FIELD REPORTS ARE NOW DUE
              ...Monitor: Jennifer Pope - Moderator: Shane (steph)
              .....Andy Rad...................TESTING
              .....Lynne Durham...............TESTING
              .....Rick Dreher................TESTING

              Bask - Trekking Sleeping Bag
              LTR DUE: 29 November 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Thomas Vickers - Moderator: Jim
              .....Edward (Ted) Ripley-Dugga..COMPLETE: 15 November 2005
              .....James E. Triplett..........EDITED..: 29 November 2005
              .....Shandra Hunt...............EDITED..: 29 November 2005

              Big Sky Products - Evolution 2P
              LTR DUE: 27 December 2005
              ...Status: LONG-TERM TESTING
              ...Monitor: Jodi Cornelius - Moderator: Stephanie
              .....Graham Blamey..............TESTING
              .....Lynne Durham...............TESTING
              .....Steve Nelson...............TESTING

              Black Diamond Equipment - Terra CF Trekking Poles
              LTR DUE: 17 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Andre Corterier - Moderator: Rick
              .....Curt Peterson..............TESTING
              .....Jim Sabiston...............TESTING
              .....Shandra Hunt...............TESTING

              Chaco Inc - Z/2
              LTR DUE: 22 November 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Tom Jones - Moderator: Rebecca Sowards-Emmerd
              .....Clifford R Haynes..........POSTED..: 23 November 2005
              .....Edward (Ted) Ripley-Dugga..COMPLETE: 16 November 2005
              .....Marie-Noelle Augendre......COMPLETE: 17 November 2005

              Dunham - Alcatraz Trail Shoes
              LTR DUE: 10 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Coy Starnes - Moderator: Rick
              .....Pam Wyant..................TESTING
              .....Rebecca Sowards-Emmerd.....TESTING
              .....Russell Curry..............TESTING

              Eastern Mountain Sports - Ridgeline Pack
              LTR DUE: 10 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Roger Caffin - Moderator: Rebecca
              .....Lynne Durham...............TESTING
              .....Mark Wood..................TESTING
              .....Scott Michael Downard......TESTING

              Flatworld - Orikaso Picnic Set
              LTR DUE: 08 November 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Leesa Joiner - Moderator: Stephanie
              .....Christine Korhonen.........COMPLETE: 26 November 2005
              .....David Posalski.............EDITED..: 25 November 2005
              .....Roger Caffin...............COMPLETE: 17 November 2005

              GoLite - Eisenhower Tunnel Shelter
              LTR DUE: 03 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Leesa Joiner - Moderator: Shane
              .....Kathleen Waters............TESTING
              .....Thomas Vickers.............TESTING
              .....Tyler Nagel................TESTING

              Granite Gear - Winterizer
              LTR DUE: 13 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Jodi Cornelius - Moderator: Stephanie
              .....Edward (Ted) Ripley-Dugga..POSTED..: 29 November 2005
              .....Pascal Deschênes...........TESTING
              .....Tim Coughlin...............TESTING

              Hennessy Hammock - Supershelter
              LTR DUE: 13 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Chuck Kime - Moderator: Shane
              .....Jamie J. DeBenedetto.......TESTING
              .....Jim Sabiston...............TESTING
              .....Jodi Cornelius.............TESTING

              IBEX Outdoor Clothing - Approach Tights
              LTR DUE: 13 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Chuck Carnes - Moderator: Stephanie
              .....Cora (Hussey) Shea.........TESTING
              .....James E. Triplett..........TESTING
              .....Pascal Deschênes...........TESTING

              INKA - Inka Pens
              LTR DUE: 03 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Rosaleen Sullivan - Moderator: Jim
              .....Chuck Carnes...............TESTING
              .....Marie-Noelle Augendre......TESTING
              .....Mark Wood..................TESTING

              Integral Designs - Silcoat Pack Cover
              LTR DUE: 06 December 2005
              ...Status: LONG-TERM TESTING
              ...Monitor: Attila Hargitai - Moderator: Rebecca
              .....Bill Jeffrey...............TESTING
              .....Curt Peterson..............TESTING
              .....Kenneth (Ken) Bigelow......EDITED..: 01 December 2005

              Integral Designs - Silcoat Backpack
              LTR DUE: 06 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Edward (Ted) Ripley-Duggan - Moderator: Rebecca
              .....Andy Rad...................TESTING
              .....Bill Jeffrey...............TESTING
              .....Laurie Corbin..............TESTING

              Integral Designs - Silshelter Bug Liner
              LTR DUE: 06 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Coy Starnes - Moderator: Rebecca
              .....Bill Jeffrey...............TESTING
              .....David Sowards-Emmerd.......COMPLETE: 29 November 2005
              .....Todd Martin................TESTING

              Katadyn - Hiker Pro
              LTR DUE: 17 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Scott Michael Downard - Moderator: Shane
              .....Coy Starnes................TESTING
              .....Jim Sabiston...............TESTING
              .....Kenneth (Ken) Bigelow......TESTING

              Keen Footwear - Taos
              LTR DUE: 29 November 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Coy Starnes - Moderator: Rebecca
              .....Jennifer Joy...............EDITED..: 02 December 2005
              .....Jennifer Pope..............EDITED..: 01 December 2005
              .....Rami Benhameda.............EDITED..: 02 December 2005

              Keen Footwear - Boulder
              LTR DUE: 13 December 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Leesa Joiner - Moderator: Rebecca
              .....Ashlee Gunter..............TESTING
              .....Kenneth (Ken) Bigelow......TESTING
              .....Stephanie Martin...........TESTING

              Sierra Designs - Rock Creek and Osage
              LTR DUE: 22 November 2005
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Michael Wheiler - Moderator: Stephanie Martin
              .....Andrew Priest..............DUE
              .....Leesa Joiner...............COMPLETE: 29 December 2005
              .....Lynne Durham...............COMPLETE: 28 November 2005

              Six Moon Designs - Comet Pack
              LTR DUE: 22 November 05
              ...Status: LONG-TERM REPORTS ARE NOW DUE
              ...Monitor: Brian Tannehill - Moderator: Stephanie
              .....Colleen Porter.............DUE
              .....George Griffin.............COMPLETE: 29 November 2005
              .....Jamie J. DeBenedetto.......EDITED..: 26 November 2005

              Spectrum Brands - Spectrum Brands Insect Repellent
              LTR DUE: 03 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Will Rietveld - Moderator: Shane
              .....Andrew Priest..............TESTING
              .....Anthony (TJ) Smith.........TESTING
              .....Heather Oakes..............TESTING

              Speer Hammocks - Segmented Pad Extender
              LTR DUE: 03 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Curt Peterson - Moderator: Rick
              .....Arron Robinson.............TESTING
              .....Christine Korhonen.........TESTING
              .....Kenneth (Ken) Bigelow......TESTING

              Spenco - Day Hiker Insole
              LTR DUE: 10 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Rami Benhameda - Moderator: Rebecca
              .....Jennifer Pope..............TESTING
              .....Jennifer Williams..........TESTING
              .....Mike Lipay.................TESTING

              Spenco - Backpacker Insole
              LTR DUE: 10 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Pam Wyant - Moderator: Rebecca
              .....Rebecca (Becki) Stacy......TESTING
              .....Russell Curry..............TESTING
              .....Will Rietveld..............TESTING

              Vargo Outdoors - Titanium 'Jet-ti' stove
              LTR DUE: 10 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: George Griffin - Moderator: Shane
              .....Anthony (TJ) Smith.........TESTING
              .....John R Waters..............TESTING
              .....Ralph Ditton...............TESTING

              Wayah Press - A Wildly Successful 200-Mile Hike
              LTR DUE: 31 January 2006
              ...Status: LONG-TERM TESTING
              ...Monitor: Chuck Carnes - Moderator: Shane
              .....Andrew (Andy) Mytys........TESTING
              .....George Griffin.............TESTING
              .....John R Waters..............TESTING



              REPORT END.



              =
              School of Accounting, Finance and Economics
              Faculty of Business and Law
              Edith Cowan University
              Pearson Street
              Churchlands

              Phone: + 8 9273 8116
              Fax: + 8 9273 8121

              Skype Voice: Aushiker
              ICQ No. 38215599
              MSN Messenger: aushiker@...
              Yahoo Messenger: aushiker
            Your message has been successfully submitted and would be delivered to recipients shortly.